Data centers · Pasco County, Florida
Pasco County
2 projects on record · 2 moratorium or ban actions
← Statewide map| Double Branch proposal | Not named | 19.9 | Paused by moratorium | July 14, 2026 | Under 50 MW |
| Stellaris Data Centers campus | Stellaris Data Centers | — | Proposed | Aug. 11, 2026 | Under 50 MW |
Moratoriums and bans
- June 8, 2026 Zephyrhills: Moratorium. City council approved a moratorium on data center development; WUSF reports one year. (Bay News 9, June 9, 2026; WUSF, June 24, 2026)
- July 14, 2026 Pasco County: Moratorium. One year, unanimous, retroactive to May 27, 2026. (Tampa Bay Beacons, July 20, 2026)
Updates, newest first
- Aug. 11, 2026 Stellaris Data Centers campus · Listed by a third-party tracker. (More Than Just Parks (data center tracker), Aug. 11, 2026)
- July 14, 2026 Double Branch proposal · Pasco adopts a one-year moratorium, unanimous. (Tampa Bay Beacons, July 20, 2026)
- July 14, 2026 Pasco County: Moratorium · One year, unanimous, retroactive to May 27, 2026. (Tampa Bay Beacons, July 20, 2026)
- June 8, 2026 Zephyrhills: Moratorium · City council approved a moratorium on data center development; WUSF reports one year. (Bay News 9, June 9, 2026; WUSF, June 24, 2026)
Statewide
Florida’s data center law, SB 484, took effect July 1, 2026: large-load customers pay the full cost of their power, and local governments keep the power to deny projects. The state’s sales-tax exemption for data centers of 100 MW or more runs to 2037. The rules →