Data centers · Pasco County, Florida

Pasco County

2 projects on record · 2 moratorium or ban actions

← Statewide map
Alachua CountyBaker CountyBay CountyBradford CountyBrevard CountyBroward CountyCalhoun CountyCharlotte CountyCitrus CountyClay CountyCollier CountyColumbia CountyDeSoto CountyDixie CountyDuval CountyEscambia CountyFlagler CountyFranklin CountyGadsden CountyGilchrist CountyGlades CountyGulf CountyHamilton CountyHardee CountyHendry CountyHernando CountyHighlands CountyHillsborough CountyHolmes CountyIndian River CountyJackson CountyJefferson CountyLafayette CountyLake CountyLee CountyLeon CountyLevy CountyLiberty CountyMadison CountyManatee CountyMarion CountyMartin CountyMiami-Dade CountyMonroe CountyNassau CountyOkaloosa CountyOkeechobee CountyOrange CountyOsceola CountyPalm Beach CountyPasco CountyPinellas CountyPolk CountyPutnam CountySanta Rosa CountySarasota CountySeminole CountySt. Johns CountySt. Lucie CountySumter CountySuwannee CountyTaylor CountyUnion CountyVolusia CountyWakulla CountyWalton CountyWashington CountyDouble Branch proposal · Paused by moratorium · 19.9 MW
Projects in Pasco County
Double Branch proposalNot named19.9Paused by moratoriumJuly 14, 2026Under 50 MW
Stellaris Data Centers campusStellaris Data Centers—ProposedAug. 11, 2026Under 50 MW

Moratoriums and bans

  1. June 8, 2026 Zephyrhills: Moratorium. City council approved a moratorium on data center development; WUSF reports one year. (Bay News 9, June 9, 2026; WUSF, June 24, 2026)
  2. July 14, 2026 Pasco County: Moratorium. One year, unanimous, retroactive to May 27, 2026. (Tampa Bay Beacons, July 20, 2026)

Updates, newest first

  1. Aug. 11, 2026 Stellaris Data Centers campus · Listed by a third-party tracker. (More Than Just Parks (data center tracker), Aug. 11, 2026)
  2. July 14, 2026 Double Branch proposal · Pasco adopts a one-year moratorium, unanimous. (Tampa Bay Beacons, July 20, 2026)
  3. July 14, 2026 Pasco County: Moratorium · One year, unanimous, retroactive to May 27, 2026. (Tampa Bay Beacons, July 20, 2026)
  4. June 8, 2026 Zephyrhills: Moratorium · City council approved a moratorium on data center development; WUSF reports one year. (Bay News 9, June 9, 2026; WUSF, June 24, 2026)

Statewide

Florida’s data center law, SB 484, took effect July 1, 2026: large-load customers pay the full cost of their power, and local governments keep the power to deny projects. The state’s sales-tax exemption for data centers of 100 MW or more runs to 2037. The rules →