Data center project · Orange County, Florida

HostDime global headquarters

Under construction · Enterprise data center headquarters, years late.

← Florida data centers
Alachua CountyBaker CountyBay CountyBradford CountyBrevard CountyBroward CountyCalhoun CountyCharlotte CountyCitrus CountyClay CountyCollier CountyColumbia CountyDeSoto CountyDixie CountyDuval CountyEscambia CountyFlagler CountyFranklin CountyGadsden CountyGilchrist CountyGlades CountyGulf CountyHamilton CountyHardee CountyHendry CountyHernando CountyHighlands CountyHillsborough CountyHolmes CountyIndian River CountyJackson CountyJefferson CountyLafayette CountyLake CountyLee CountyLeon CountyLevy CountyLiberty CountyMadison CountyManatee CountyMarion CountyMartin CountyMiami-Dade CountyMonroe CountyNassau CountyOkaloosa CountyOkeechobee CountyOrange CountyOsceola CountyPalm Beach CountyPasco CountyPinellas CountyPolk CountyPutnam CountySanta Rosa CountySarasota CountySeminole CountySt. Johns CountySt. Lucie CountySumter CountySuwannee CountyTaylor CountyUnion CountyVolusia CountyWakulla CountyWalton CountyWashington CountyHostDime global headquarters · Under construction · 20 MW
Status
Under construction · as of Sept. 16, 2026
Approved by
Not named in the records found
Development agreement with the Town of Eatonville (approval body and date not found)
DCD says the project was 'originally approved in 2016' and mentions a development agreement with the town, but no record found names the vote or approving body. WFTV reports that the Eatonville town council imposed the $250-a-day fine after the July 2025 deadline was missed. (DatacenterDynamics, Sept. 3, 2025; WFTV via WDBO, Sept. 16, 2026)
Location
Eatonville (Wymore Rd.) · Orange County
Status note
Years behind schedule; the town has fined HostDime $250 a day since July 2025 (more than $100,000).
Power
20 MW
Cleanview; the 2019 plan cited more than 10 MW from Duke.
Floor area
110,000 sq ft
100,000–120,000 sq ft.
Developer and team
HostDime; Robins & Morton (construction manager, 2019)
Utility
Duke Energy (2019 plan)
Water
Closed loop.
Evidence
News reports; primary records not yet obtained
Size class
Under 50 MW (outside main scope; kept for completeness)
Map position approximate, from the reported address or area. Updated Oct. 17, 2026.

Updates, newest first

  1. Sept. 16, 2026 Heated confrontation at the Eatonville council over delays and fines. (WFTV via WDBO, Sept. 16, 2026; HostDime (company blog), March 25, 2019)