Data center project · Miami-Dade County, Florida

Iron Mountain MIA-1

Under construction · 16 MW colocation data center under construction; the only Florida data center with a documented general contractor.

← Florida data centers
Alachua CountyBaker CountyBay CountyBradford CountyBrevard CountyBroward CountyCalhoun CountyCharlotte CountyCitrus CountyClay CountyCollier CountyColumbia CountyDeSoto CountyDixie CountyDuval CountyEscambia CountyFlagler CountyFranklin CountyGadsden CountyGilchrist CountyGlades CountyGulf CountyHamilton CountyHardee CountyHendry CountyHernando CountyHighlands CountyHillsborough CountyHolmes CountyIndian River CountyJackson CountyJefferson CountyLafayette CountyLake CountyLee CountyLeon CountyLevy CountyLiberty CountyMadison CountyManatee CountyMarion CountyMartin CountyMiami-Dade CountyMonroe CountyNassau CountyOkaloosa CountyOkeechobee CountyOrange CountyOsceola CountyPalm Beach CountyPasco CountyPinellas CountyPolk CountyPutnam CountySanta Rosa CountySarasota CountySeminole CountySt. Johns CountySt. Lucie CountySumter CountySuwannee CountyTaylor CountyUnion CountyVolusia CountyWakulla CountyWalton CountyWashington CountyIron Mountain MIA-1 · Under construction · 16 MW
Status
Under construction · as of Aug. 8, 2025
Approved by
Not named in the records found
No record found that names an approving body or permit. The Miami Herald (via GovTech) reports that Miami-Dade treats data centers as 'telecommunications hubs' that need no new permissions, and says the projects are too small for the state law's hearing requirement. DCD names Mayor Daniella Levine Cava only as praising the investment, not as approving it. (DatacenterDynamics, Feb. 27, 2025; Miami Herald via GovTech, July 17, 2026)
Location
Westview, Miami · Miami-Dade County
Power
16 MW
Cleanview lists 23 MW.
Floor area
150,000 sq ft
Land
3.4 acres
Developer and team
Iron Mountain; Brasfield & Gorrie (general contractor)
Utility
FPL (unconfirmed)
Evidence
News reports; primary records not yet obtained
Size class
Under 50 MW (outside main scope; kept for completeness)
Map position approximate, from the reported address or area. Updated Oct. 17, 2026.

Updates, newest first

  1. Aug. 8, 2025 Building topped out; general contractor Brasfield & Gorrie. (DatacenterDynamics, Aug. 8, 2025)
  2. Feb. 27, 2025 Iron Mountain breaks ground. (DatacenterDynamics, Feb. 27, 2025)

Have records about this project? Send them to tips@signaldata.org.