Data center project · Miami-Dade County, Florida
Project Apollo
Proposed · 15 MW data center seeking a county jobs incentive.
- Status
- Proposed · as of Dec. 3, 2024
- Location
- Unincorporated Miami-Dade, Commission District 12 · Miami-Dade County
- Status note
- County incentive item on the Dec. 3, 2024 agenda; outcome unconfirmed. Target online 2027.
- Power
- 15 MW
- Floor area
- 75,000 sq ft
- Investment
- $150 million capital investment; 27 jobs
- Developer and team
- Not disclosed (team with past work for Amazon, Meta and Iron Mountain)
- Utility
- FPL
- Incentives
- Miami-Dade Targeted Jobs Incentive Fund, up to $3,633,902 over FY2029-30 to FY2038-39.
- Evidence
- Primary public records
- Size class
- Under 50 MW (outside main scope; kept for completeness)
Updates, newest first
- Dec. 3, 2024 Incentive item before the county commission. (Miami-Dade County, Dec. 3, 2024; DatacenterDynamics, Nov. 27, 2024)