Data center project · St. Lucie County, Florida

Sentinel Grove Technology Park

Withdrawn · 1 GW campus over former citrus groves, withdrawn. Also known as: Project Jarvis.

← Florida data centers
Alachua CountyBaker CountyBay CountyBradford CountyBrevard CountyBroward CountyCalhoun CountyCharlotte CountyCitrus CountyClay CountyCollier CountyColumbia CountyDeSoto CountyDixie CountyDuval CountyEscambia CountyFlagler CountyFranklin CountyGadsden CountyGilchrist CountyGlades CountyGulf CountyHamilton CountyHardee CountyHendry CountyHernando CountyHighlands CountyHillsborough CountyHolmes CountyIndian River CountyJackson CountyJefferson CountyLafayette CountyLake CountyLee CountyLeon CountyLevy CountyLiberty CountyMadison CountyManatee CountyMarion CountyMartin CountyMiami-Dade CountyMonroe CountyNassau CountyOkaloosa CountyOkeechobee CountyOrange CountyOsceola CountyPalm Beach CountyPasco CountyPinellas CountyPolk CountyPutnam CountySanta Rosa CountySarasota CountySeminole CountySt. Johns CountySt. Lucie CountySumter CountySuwannee CountyTaylor CountyUnion CountyVolusia CountyWakulla CountyWalton CountyWashington CountySentinel Grove Technology Park · Withdrawn · 1,000 MW
Status
Withdrawn · as of Feb. 26, 2026
Location
West of Fort Pierce (Minute Maid Rd.) · St. Lucie County
Status note
Planning and zoning board recommended denial; developer withdrew, saying it would wait on state legislation (SB 484). Local officials told WPBF it could return (per the Tampa Bay Times).
Power
1,000 MW
Floor area
15,000,000 sq ft
Land
1,218 acres
Investment
$13–13.5 billion
Developer and team
Timberline Real Estate Partners; HJA Design Studio
End user
Not confirmed.
Utility
Near FPL 500 kV lines
Evidence
News reports; primary records not yet obtained
Size class
50 MW or more (tracker scope)
Map position approximate, from the reported address or area. Updated Oct. 17, 2026.

Updates, newest first

  1. June 17, 2026 Timberline Real Estate Partners gives $7,000 to Friends of Byron Donalds PAC; eight Timberline LLCs give $3,000 each to Donalds' campaign on June 30. (Florida Division of Elections, Oct. 16, 2026; Tampa Bay Times (syndicated by Tribune Content Agency), Aug. 1, 2026)
  2. Feb. 26, 2026 Developer withdraws its application after the planning board recommends denial. (DatacenterDynamics, Feb. 26, 2026; TCPalm (syndicated), Jan. 15, 2026)
  3. Oct. 16, 2025 Proposal filed. (DatacenterDynamics, Feb. 26, 2026)

Political money tied to this project

  • Timberline Real Estate Partners and affiliated LLCs$31,000 to Byron Donalds ($7,000 on June 17, 2026 to Friends of Byron Donalds PAC (PAC); $3,000 on June 30, 2026 to Donalds, Byron (REP)(GOV); $3,000 on June 30, 2026 to Donalds, Byron (REP)(GOV); $3,000 on June 30, 2026 to Donalds, Byron (REP)(GOV); $3,000 on June 30, 2026 to Donalds, Byron (REP)(GOV); $3,000 on June 30, 2026 to Donalds, Byron (REP)(GOV); $3,000 on June 30, 2026 to Donalds, Byron (REP)(GOV); $3,000 on June 30, 2026 to Donalds, Byron (REP)(GOV); $3,000 on June 30, 2026 to Donalds, Byron (REP)(GOV)) · Texas developer of Sentinel Grove (“Project Jarvis”), a 1 GW campus in St. Lucie County, withdrawn. (Florida Division of Elections, Oct. 16, 2026)

FL Division of Elections. Details and every other recipient in the Data Center File. The records do not show that any contribution influenced a decision.