Data center project · Clinton County, Ohio
AWS Wilmington data center campus
Approved · Amazon's proposed $4 billion campus off US 68 has drawn sustained resident opposition, a blocked ballot initiative and a lawsuit over emergency rezoning.
- Status
- Approved · as of Sept. 3, 2026
- Approved by
- Wilmington City Council (Ohio)
Rezoning from rural residential to light industrial, passed as emergency legislation, Sept. 3, 2026, vote 7-0
At the previous meeting the emergency rezoning had failed 5-2 because it needed 75% of the vote. On Feb. 19, 2026 council had voted 5-2 to rezone four parcels of more than 545 acres near the site. Final passage of the tax agreement and site plan approval were not confirmed. (FOX19 (WXIX), Sept. 4, 2026; FOX19 (WXIX), Sept. 18, 2026; WCPO 9, Feb. 20, 2026) - Location
- 1488 South US 68, Wilmington (some reports give 1588) · Clinton County
- Status note
- Council rezoned land for the campus, most recently under emergency procedures on Sept. 3, 2026; final passage of the tax agreement and approval of the site plan were not confirmed in the sources opened.
- Land
- 471 acres
- Investment
- About $4 billion, plus about $25 million in public infrastructure (sewer, a 1-million-gallon water tower, about 2.5 miles of water main, US 68 and SR 730 road work)
- Developer and team
- Amazon Web Services
- End user
- Amazon Web Services
- Incentives
- Proposed Ordinance O-25-73: a compensation agreement among AWS, the city and the Clinton County Port Authority with up to 30 years of tax exemption, under which Amazon would pay 30% of the property tax otherwise owed each year; Wilmington City Schools approved its compensation agreement on Nov. 19, 2025
- Evidence
- News reports; primary records not yet obtained
- Size class
- 50 MW or more (tracker scope)
Updates, newest first
- Sept. 18, 2026 The Supreme Court of Ohio upheld the Clinton County Board of Elections' refusal to place a citizen data center zoning initiative on the Nov. 3 ballot, finding the city could not create the private right to sue it contained. (FOX19 (WXIX), Sept. 18, 2026)
- Sept. 3, 2026 Council passed a rezoning from rural residential to light industrial under emergency procedures, following an August noise ordinance also passed as an emergency; a resident sued over the emergency rezoning. (FOX19 (WXIX), Sept. 18, 2026)
- Feb. 19, 2026 Council voted 5-2 to rezone four parcels of more than 545 acres from rural residential to light industrial near the site, against a regional planning commission recommendation to table. (WCPO 9, Feb. 20, 2026; WHIO, Feb. 6, 2026)
- Jan. 7, 2026 Wilmington Planning Commission unanimously tabled the site plan, citing incomplete traffic, lighting and water studies. (DatacenterDynamics, Jan. 7, 2026)
- Dec. 4, 2025 Council moved the tax agreement past the first of three required readings. (WCPO 9, Dec. 4, 2025)
- Nov. 25, 2025 City council delayed its vote on the tax agreement to Dec. 4 after about 40 residents spoke, many urging rejection. (DatacenterDynamics, Nov. 28, 2025)
Conflicts and open questions
- Address given as 1588 South US 68 by DCD in November 2025 and 1488 South US 68 in later reports.
- Reporting describes the annual payroll as $8 million (WCPO) and $8bn (DCD); $8 million is the plausible figure.
- Searches surfaced a Local 12 report that a judge ordered the city to redo data center ordinances over an open-meetings violation; that page could not be opened, so it is not entered as an event.
Have records about this project? Send them to tips@signaldata.org.