Where the data centers are going,
and where they were stopped.
Every large data center campus we can document, proposed, approved, under construction, withdrawn or denied, with the local votes, moratoriums and money behind it. Each project has its own page and a dated log of updates, each linked to its record.
Dots are projects, sized by reported power; positions are approximate. “Not yet checked” is not the same as “none”.
Latest updates
- Oct. 15, 2026 Microsoft West Valley campus (Goodyear) · ABC15 names Microsoft among the operators in the Goodyear Airpark area data center cluster. (ABC15 Arizona, Oct. 15, 2026)
- Oct. 15, 2026 Stream Data Centers Phoenix campus (Goodyear) · ABC15 names Stream Data Centers among the operators in the Goodyear Airpark area data center cluster. (ABC15 Arizona, Oct. 15, 2026)
- Oct. 15, 2026 Meta Mesa data center · ABC15 names Meta among the operators in the far East Valley, Mesa data center cluster. (ABC15 Arizona, Oct. 15, 2026)
- Oct. 15, 2026 Apple Mesa data center · ABC15 names Apple among the operators in the far East Valley, Mesa data center cluster. (ABC15 Arizona, Oct. 15, 2026)
- Oct. 15, 2026 NTT Mesa campus · ABC15 names NTT among the operators in the far East Valley, Mesa data center cluster. (ABC15 Arizona, Oct. 15, 2026)
- Oct. 15, 2026 EdgeConneX Mesa campus · ABC15 names EdgeConneX among the operators in the far East Valley, Mesa data center cluster. (ABC15 Arizona, Oct. 15, 2026)
- Oct. 15, 2026 CyrusOne Chandler campus · ABC15 names CyrusOne among the operators in the south Chandler data center cluster. (ABC15 Arizona, Oct. 15, 2026)
- Oct. 13, 2026 Comanche Circle · Commissioners voted 3-1 to reject a settlement that would have shrunk the project to about 1,375 acres, then unanimously denied Sailfish's appeal on its on-site permits. (KERA (via Texas Public Radio), Oct. 13, 2026)
- Oct. 9, 2026 Project Tango · PBA Holdings sues the county to force the special-magistrate hearing, claiming Commissioner Maria Sachs prejudged the vote. (The Palm Beach Post (syndicated), Oct. 13, 2026)
- Oct. 8, 2026 Taylor Technology Campus · The City Council approved the annexation agreement 5-0; a petition to restrict data centers was ruled ineligible under Texas law. (CBS Austin, Oct. 8, 2026)
- Oct. 8, 2026 Taylor: Ban petition (rejected) · City officials said a resident petition to restrict data centers could not go forward through the initiative process under Texas law. (CBS Austin, Oct. 8, 2026; San Antonio Express-News (via GovTech/TNS), July 17, 2026)
- Oct. 7, 2026 Project Tango · County staff administratively approve DRO-2026-00966: 2.02 million sq ft within the existing master plan, including 698,000 sq ft of data center space plus accessory office, with no public hearing. (Palm Beach County Zoning Division, Oct. 7, 2026)
- Oct. 7, 2026 Duval County · JEA says it has received large-load inquiries, has none under evaluation, and lacks power and water capacity for a hyperscale campus. It is building a 50 MW-plus rate class through 2027. (News4JAX, Oct. 7, 2026)
- Oct. 6, 2026 Volusia County: Ban (pending) · First reading Oct. 6; final hearing Oct. 20, 2026. (Spectrum News 13, Oct. 6, 2026)
- Oct. 2, 2026 Taylor Technology Campus · The city announced a negotiated annexation deal setting rules for noise, water, setbacks and community benefits. (KUT 90.5, Oct. 2, 2026)
Every project
| Fermi America Project Matador (HyperGrid campus) | Texas | Carson | Fermi America | 11,000 | Under construction | Feb. 25, 2026 | 50 MW+ |
| DCIP AI campus | Florida | DeSoto | DCIP Group (CEO Jon Brown) | 4,000 | Approved | March 2026 | 50 MW+ |
| AWS New Carlisle campus (Project Rainier) | Indiana | St. Joseph | Amazon Web Services | 2,200 | Operating | Oct. 29, 2025 | 50 MW+ |
| Project Bunkhouse | Georgia | Bartow | Taurus DC SPE LLC | 1,830 | Approved | June 4, 2025 | 50 MW+ |
| Buckeye Tech Corridor (Tract) | Arizona | Maricopa | Tract | 1,800 | Approved | Aug. 6, 2024 | 50 MW+ |
| Vantage Frontier | Texas | Shackelford | Vantage Data Centers | 1,400 | Under construction | April 2026 | 50 MW+ |
| Bolingbroke Technology Campus | Georgia | Monroe | Bolingbroke Technology Center | 1,200 | Denied | Aug. 5, 2025 | 50 MW+ |
| Fort Meade campus | Florida | Polk | Stonebridge (Bethesda, Md.); Fort Meade LLC (shares Stonebridge’s address) | 1,200 | Approved | April 14, 2026 | 50 MW+ |
| Stargate Abilene (Lancium Clean Campus) | Texas | Taylor | Crusoe; Lancium | 1,200 | Under construction | April 2026 | 50 MW+ |
| Stargate Milam County (SB Energy) | Texas | Milam | SB Energy (SoftBank) | 1,200 | Under construction | April 2026 | 50 MW+ |
| Switch Atlanta campus (The Keep) | Georgia | Bartow | Switch | 1,200 | Operating | Oct. 22, 2025 | 50 MW+ |
| Rumble Technology Park | Georgia | Monroe | Cloverleaf Infrastructure; Rum Creek DevCo LLC; Datacore Innovations LLC | 1,120 | Approved | Nov. 2024 | 50 MW+ |
| Hassayampa Ranch | Arizona | Maricopa | Arizona Land Consulting (CEO Anita Verma-Lallian) | 1,000 | Approved | Dec. 10, 2025 | 50 MW+ |
| La Osa Energy Center | Arizona | Pinal | Vermaland | 1,000 | Denied | Aug. 26, 2026 | 50 MW+ |
| Meta El Paso data center | Texas | El Paso | Meta | 1,000 | Under construction | Oct. 2025 | 50 MW+ |
| Meta Prometheus AI data center | Ohio | Licking | Meta Platforms | 1,000 | Under construction | Jan. 19, 2026 | 50 MW+ |
| Page data center site (Huntley LLC) | Arizona | Coconino | Huntley LLC | 1,000 | Site zoned or marketed | Oct. 22, 2025 | 50 MW+ |
| Sentinel Grove Technology Park | Florida | St. Lucie | Timberline Real Estate Partners; HJA Design Studio | 1,000 | Withdrawn | Feb. 26, 2026 | 50 MW+ |
| Silver Fox Road proposal | Florida | Martin | Silver Fox 606 LLC (Juno Beach) | 1,000 | Withdrawn | April 29, 2026 | 50 MW+ |
| Crusoe Abilene campus for Microsoft | Texas | Taylor | Crusoe | 900 | Under construction | March 27, 2026 | 50 MW+ |
| Project Sail | Georgia | Coweta | Prologis; Atlas Development LLC | 900 | Approved | April 7, 2026 | 50 MW+ |
| Beale Marana data center campus (Luckett Road) | Arizona | Pima | Beale Infrastructure | 750 | Approved | Jan. 6, 2026 | 50 MW+ |
| Riot Platforms Rockdale data center site | Texas | Milam | Riot Platforms | 700 | Under construction | Jan. 16, 2026 | 50 MW+ |
| Old Ocean Data Center | Texas | Brazoria | Nightpeak Energy | 620 | Proposed | March 10, 2026 | 50 MW+ |
| Project Blue | Arizona | Pima | Beale Infrastructure (backed by Blue Owl); Humphrey's Peak Power LLC | 600 | Under construction | April 24, 2026 | 50 MW+ |
| Project West | Georgia | Troup | Project West WHP - GA LLC | 600 | Proposed | March 10, 2025 | 50 MW+ |
| Pacifico Cedar Creek data center and power campus | Texas | Bastrop | Pacifico Energy; Black Chamber Partners | 490 | Proposed | Aug. 19, 2026 | 50 MW+ |
| Cielo Haines City | Florida | Polk | Cielo Digital Infrastructure (Texas) | 300 | Stalled | June 25, 2026 | 50 MW+ |
| Atlas Compute Fort Pierce | Florida | St. Lucie | Atlas Compute (Miami) | 240 | Proposed | March 12, 2026 | 50 MW+ |
| CyrusOne DFW10 at Thad Hill Energy Center | Texas | Bosque | CyrusOne | 144 | Under construction | July 31, 2025 | 50 MW+ |
| Fort Spunky data center | Texas | Hood | Pacifico Energy | 100 | Denied | March 10, 2026 | 50 MW+ |
| Google LaGrange data center | Georgia | Troup | Google; Thor Equities (former owner); Form8ation (former developer) | 100 | Under construction | April 21, 2026 | 50 MW+ |
| Project Swan | Florida | Polk | Ryan Companies (Tyler Lohmiller) | 100 | Paused by moratorium | Aug. 3, 2026 | 50 MW+ |
| EdgeConneX Cedar Creek campus (DFW33220N) | Texas | Bastrop | EdgeConneX | 96 | Under construction | Sept. 24, 2025 | 50 MW+ |
| HostDime global headquarters | Florida | Orange | HostDime; Robins & Morton (construction manager, 2019) | 20 | Under construction | Sept. 16, 2026 | Under 50 MW |
| Double Branch proposal | Florida | Pasco | Not named | 19.9 | Paused by moratorium | July 14, 2026 | Under 50 MW |
| Iron Mountain MIA-1 | Florida | Miami-Dade | Iron Mountain; Brasfield & Gorrie (general contractor) | 16 | Under construction | Aug. 8, 2025 | Under 50 MW |
| Metrobloks MIA-MB01 | Florida | Miami-Dade | Metrobloks (Los Angeles) | 15.2 | Under construction | July 17, 2026 | Under 50 MW |
| Project Apollo | Florida | Miami-Dade | Not disclosed (team with past work for Amazon, Meta and Iron Mountain) | 15 | Proposed | Dec. 3, 2024 | Under 50 MW |
| DC Blox Palm Coast | Florida | Flagler | DC Blox / Tarpon Services | 10 | Under construction | March 26, 2026 | Under 50 MW |
| Okee-One | Florida | Okeechobee | Indian River State College | 10 | Denied | April 23, 2026 | Under 50 MW |
| AWS Butts County campus | Georgia | Butts | Amazon Web Services | — | Proposed | Jan. 8, 2025 | Under 50 MW |
| AWS Douglas County campus | Georgia | Douglas | Amazon Web Services | — | Proposed | Sept. 17, 2025 | 50 MW+ |
| AWS Sidney data center campus | Ohio | Shelby | Amazon Web Services | — | Approved | Oct. 5, 2026 | Under 50 MW |
| AWS Wilmington data center campus | Ohio | Clinton | Amazon Web Services | — | Approved | Sept. 3, 2026 | 50 MW+ |
| Adairsville data center (Atlas Development) | Georgia | Bartow | Atlas Development | — | Proposed | Sept. 17, 2025 | 50 MW+ |
| Agincourt Valparaiso data center proposal | Indiana | Porter | Agincourt | — | Withdrawn | March 11, 2025 | Under 50 MW |
| Amazon Hobart data center campus (Hobart Tech Park) | Indiana | Lake | Amazon | — | Approved | Feb. 2026 | Under 50 MW |
| Amazon Lamar County site | Georgia | Lamar | Amazon | — | Site zoned or marketed | July 2025 | 50 MW+ |
| Amazon Pecos County data center campus | Texas | Pecos | Amazon | — | Proposed | Aug. 11, 2026 | 50 MW+ |
| Apple Mesa data center | Arizona | Maricopa | Apple | — | Operating | Oct. 2026 | Under 50 MW |
| Black Mountain data center campus | Texas | Tarrant | Black Mountain | — | Proposed | July 2026 | 50 MW+ |
| Byrd Farms data center | Georgia | Columbia | — | — | Denied | Feb. 2026 | 50 MW+ |
| Comanche Circle | Texas | Hood | Sailfish Investors | — | Stalled | Oct. 13, 2026 | 50 MW+ |
| Crusoe data center south of Claude | Texas | Armstrong | Crusoe | — | Approved | Oct. 14, 2025 | 50 MW+ |
| CyrusOne Chandler campus | Arizona | Maricopa | CyrusOne | — | Operating | Oct. 2026 | Under 50 MW |
| Devlin Technology Park | Virginia | Prince William | Stanley Martin Homes | — | Approved | Sept. 16, 2025 | 50 MW+ |
| EdgeConneX Mesa campus | Arizona | Maricopa | EdgeConneX | — | Operating | Oct. 2026 | Under 50 MW |
| EdgeConneX second Bastrop County campus | Texas | Bastrop | EdgeConneX | — | Proposed | March 26, 2026 | 50 MW+ |
| EdgeCore Mesa campus | Arizona | Maricopa | EdgeCore | — | Operating | Oct. 2026 | Under 50 MW |
| Effingham County data center campus | Georgia | Effingham | — | — | Proposed | Aug. 27, 2026 | Under 50 MW |
| Energy Generation and Technology Campus | Arizona | Pinal | — | — | Under construction | Dec. 17, 2025 | 50 MW+ |
| Etowah River data center proposal | Georgia | Bartow | — | — | Proposed | July 16, 2026 | 50 MW+ |
| Google Columbus data center | Ohio | Franklin | — | Under construction | June 20, 2024 | Under 50 MW | |
| Google Fort Wayne data center campus (Project Zodiac) | Indiana | Allen | — | Operating | Dec. 11, 2025 | 50 MW+ | |
| Google Franklin Township data center (Indianapolis) | Indiana | Marion | — | Withdrawn | Sept. 22, 2025 | 50 MW+ | |
| Google Haskell County campuses | Texas | Haskell | — | Proposed | Nov. 17, 2025 | Under 50 MW | |
| Google Lancaster data center | Ohio | Fairfield | — | Operating | June 20, 2024 | Under 50 MW | |
| Google Midlothian and Red Oak campuses | Texas | Ellis | — | Operating | Nov. 2025 | Under 50 MW | |
| Google Morgan County data center campus (Monrovia) | Indiana | Morgan | — | Approved | Oct. 2025 | 50 MW+ | |
| Google New Albany data center campus | Ohio | Licking | — | Operating | June 20, 2024 | Under 50 MW | |
| Haskell County Ranger RZ 2026 data center | Texas | Haskell | Ascendant Site Solutions LLC | — | Proposed | Jan. 9, 2026 | 50 MW+ |
| Highlander SM One data center | Texas | Hays | Highlander SM One LLC | — | Denied | Feb. 17, 2026 | 50 MW+ |
| Holder Industrial Park expansion | Florida | Citrus | Deltona Corp. | — | Withdrawn | June 23, 2026 | 50 MW+ |
| Kenansville hyperscale site listing | Florida | Osceola | CBRE (listing broker); owner not stated | — | Site zoned or marketed | Sept. 29, 2026 | 50 MW+ |
| Kilby (Chevron power for Microsoft data center) | Texas | Reeves | Chevron (Energy Forge One); Engine No. 1 | — | Proposed | June 22, 2026 | Under 50 MW |
| Meta Lebanon data center campus (LEAP District) | Indiana | Boone | Meta Platforms | — | Under construction | Feb. 11, 2026 | 50 MW+ |
| Meta Mesa data center | Arizona | Maricopa | Meta | — | Operating | Oct. 2026 | Under 50 MW |
| Meta Stanton Springs (Newton Data Center) | Georgia | Newton | Meta Platforms (believed); Baymare LLC | — | Operating | Oct. 2025 | 50 MW+ |
| Microsoft East US 3 region (Fulton and Douglas) | Georgia | Fulton | Microsoft | — | Approved | Feb. 11, 2021 | Under 50 MW |
| Microsoft Granger data center campus | Indiana | St. Joseph | Microsoft | — | Proposed | March 17, 2026 | 50 MW+ |
| Microsoft Heath data center site | Ohio | Licking | Microsoft | — | Stalled | April 8, 2025 | 50 MW+ |
| Microsoft Hebron data center site | Ohio | Licking | Microsoft | — | Stalled | April 8, 2025 | 50 MW+ |
| Microsoft La Porte data center campus | Indiana | LaPorte | Microsoft | — | Under construction | June 17, 2026 | 50 MW+ |
| Microsoft New Albany data center | Ohio | Licking | Microsoft | — | Stalled | April 8, 2025 | 50 MW+ |
| Microsoft West Valley campus (Goodyear) | Arizona | Maricopa | Microsoft | — | Operating | Oct. 2026 | Under 50 MW |
| Mount Orab Mega Site data center proposal | Ohio | Brown | — | — | Proposed | Sept. 16, 2026 | 50 MW+ |
| NTT Mesa campus | Arizona | Maricopa | NTT | — | Operating | Oct. 2026 | Under 50 MW |
| Newton County Technology Park | Georgia | Newton | — | — | Proposed | Sept. 17, 2025 | 50 MW+ |
| NextNRG site | Florida | Nassau | NextNRG (Miami) | — | Proposed | Sept. 22, 2025 | 50 MW+ |
| Price Road Innovation Campus | Arizona | Maricopa | Active Infrastructure (New York) | — | Denied | Dec. 11, 2025 | Under 50 MW |
| Prince William Digital Gateway | Virginia | Prince William | QTS Realty Trust (Blackstone); Compass Datacenters | — | Withdrawn | July 2, 2026 | 50 MW+ |
| Project Aquila (RCM Hill LLC) | Texas | Hill | RCM Hill LLC | — | Proposed | July 15, 2026 | 50 MW+ |
| Project Peach | Georgia | Coweta | North Coweta Investors | — | Approved | 2025 | 50 MW+ |
| Project Range (Tract) | Arizona | Maricopa | Tract | — | Withdrawn | 2024 | Under 50 MW |
| Project Red and Project Yellow | Texas | Hood | — | — | Proposed | June 2026 | 50 MW+ |
| Project Tango | Florida | Palm Beach | PBA Holdings, Inc.; WPB Logistics Owner, LLC (owns ~60 acres; rival plan) | — | Approved | Oct. 7, 2026 | 50 MW+ |
| Prologis Kosciusko County data center proposal | Indiana | Kosciusko | Prologis | — | Denied | April 22, 2025 | Under 50 MW |
| Provident Realty Burns Harbor data center proposal | Indiana | Porter | Provident Realty Advisors | — | Withdrawn | May 2025 | Under 50 MW |
| Provident Realty Chesterton data center campus | Indiana | Porter | Provident Realty Advisors | — | Withdrawn | June 10, 2024 | 50 MW+ |
| Pumpkin Center data center | Georgia | Columbia | — | — | Approved | Feb. 2026 | 50 MW+ |
| QTS Fayetteville campus | Georgia | Fayette | QTS Data Centers | — | Under construction | July 13, 2026 | 50 MW+ |
| QTS Union Township campus (Jeremiah A and B) | Indiana | Porter | QTS Data Centers (Blackstone) | — | Withdrawn | Sept. 4, 2025 | 50 MW+ |
| Ranch House data center rezoning | Arizona | Pima | The Planning Center (applicant) | — | Proposed | June 26, 2026 | Under 50 MW |
| Sabey Data Centers Decatur Township campus | Indiana | Marion | Sabey Data Centers | — | Approved | March 18, 2026 | 50 MW+ |
| Stellaris Data Centers campus | Florida | Pasco | Stellaris Data Centers | — | Proposed | Aug. 11, 2026 | Under 50 MW |
| Stream Data Centers Phoenix campus (Goodyear) | Arizona | Maricopa | Stream Data Centers | — | Operating | Oct. 2026 | Under 50 MW |
| Surge Development Hancock County data center megasite | Indiana | Hancock | Surge Development LLC | — | Withdrawn | May 15, 2025 | 50 MW+ |
| Taylor Technology Campus | Texas | Williamson | Big Watt Digital; PowerHouse Data Centers | — | Approved | Oct. 8, 2026 | 50 MW+ |
| Tesoro Groves PUD (FPL) | Florida | Martin | Florida Power & Light | — | Site zoned or marketed | April 30, 2026 | 50 MW+ |
| Twiggs County data center (Dry Branch) | Georgia | Twiggs | Eagle Rock Partners | — | Approved | Sept. 18, 2025 | 50 MW+ |
| Vantage Data Centers Pittsboro campus | Indiana | Hendricks | Vantage Data Centers | — | Approved | March 2025 | 50 MW+ |
| White Oak Technology Park | Georgia | Columbia | Kinetic Infrastructure; Trammell Crow Company | — | Approved | July 23, 2026 | Under 50 MW |
| XF Group inquiry | Florida | Sarasota | XF Group | — | Inquiry only | July 8, 2026 | Under 50 MW |
| “Fishbowl” micro data center | Florida | Miami-Dade | ReadySetFundGrow | — | Under construction | July 17, 2026 | Under 50 MW |
- Operating
- Built and serving customers.
- Under construction
- Building permits issued or construction reported under way.
- Approved
- A government body has approved land use, zoning or a development agreement for data center use. Other permits may still be pending.
- Proposed
- An application, announcement or public proposal exists; no approval yet.
- Site zoned or marketed
- Land zoned or marketed for possible data center use; no project filed.
- Paused by moratorium
- A local moratorium or ban blocks new applications or approvals.
- Stalled
- No formal application, or blocked by a missing permit or utility capacity.
- Inquiry only
- A developer asked local officials about a site; nothing was filed.
- Withdrawn
- The developer withdrew its application or proposal.
- Denied
- A government body voted it down.
Coverage
| Alabama | Not yet checked | — |
| Alaska | Not yet checked | — |
| Arizona | Reviewed Oct. 17, 2026 | 18 |
| Arkansas | Not yet checked | — |
| California | Not yet checked | — |
| Colorado | Not yet checked | — |
| Connecticut | Not yet checked | — |
| Delaware | Not yet checked | — |
| District of Columbia | Not yet checked | — |
| Florida | Reviewed Oct. 17, 2026 | 22 |
| Georgia | Reviewed Oct. 17, 2026 | 22 |
| Hawaii | Not yet checked | — |
| Idaho | Not yet checked | — |
| Illinois | Not yet checked | — |
| Indiana | Reviewed Oct. 17, 2026 | 16 |
| Iowa | Not yet checked | — |
| Kansas | Not yet checked | — |
| Kentucky | Not yet checked | — |
| Louisiana | Not yet checked | — |
| Maine | Not yet checked | — |
| Maryland | Not yet checked | — |
| Massachusetts | Not yet checked | — |
| Michigan | Not yet checked | — |
| Minnesota | Not yet checked | — |
| Mississippi | Not yet checked | — |
| Missouri | Not yet checked | — |
| Montana | Not yet checked | — |
| Nebraska | Not yet checked | — |
| Nevada | Not yet checked | — |
| New Hampshire | Not yet checked | — |
| New Jersey | Not yet checked | — |
| New Mexico | Not yet checked | — |
| New York | Not yet checked | — |
| North Carolina | Not yet checked | — |
| North Dakota | Not yet checked | — |
| Ohio | Reviewed Oct. 17, 2026 | 10 |
| Oklahoma | Not yet checked | — |
| Oregon | Not yet checked | — |
| Pennsylvania | Not yet checked | — |
| Rhode Island | Not yet checked | — |
| South Carolina | Not yet checked | — |
| South Dakota | Not yet checked | — |
| Tennessee | Not yet checked | — |
| Texas | Reviewed Oct. 17, 2026 | 25 |
| Utah | Not yet checked | — |
| Vermont | Not yet checked | — |
| Virginia | Reviewed Oct. 17, 2026 | 2 |
| Washington | Not yet checked | — |
| West Virginia | Not yet checked | — |
| Wisconsin | Not yet checked | — |
| Wyoming | Not yet checked | — |
What this map covers
The tracker covers campuses of 50 MW or more (or 100 acres or more when power is not reported) that were proposed, approved or contested since 2024, plus operating hyperscale campuses for context. Smaller projects found along the way are kept and can be shown with the switch above the map.
A project’s status is the latest public record we have found: a vote, a filing, a permit or a withdrawal. Every update links to its source, and we credit the reporting that first found it. Positions are approximate. States are added one at a time; a state marked “not yet checked” has not been reviewed, which is not the same as having no projects.
Have a filing, agenda or record about a data center? Send it to tips@signaldata.org.