Data center project · Licking County, Ohio
Meta Prometheus AI data center
Under construction · Meta's New Albany AI campus, described as the first data center expected to need more than a gigawatt, was reported nearing completion in 2026. Also known as: Prometheus.
- Status
- Under construction · as of Jan. 19, 2026
- Approved by
- Not named in the records found
No record opened names the body that approved Meta's New Albany (Prometheus) campus. - Location
- New Albany · Licking County
- Status note
- Reported as finishing construction in 2026.
- Power
- 1,000 MW
Reported as more than 1 GW. - Developer and team
- Meta Platforms
- End user
- Meta
- Evidence
- News reports; primary records not yet obtained
- Size class
- 50 MW or more (tracker scope)
Updates, newest first
- Jan. 19, 2026 WOSU reported Meta was wrapping up construction on Prometheus in New Albany in 2026. (WOSU (via WYSO), Jan. 19, 2026)
Conflicts and open questions
- Only a photo caption was found in the sources opened; county placement (Licking) needs confirmation from a parcel or abatement record.
- Signal Ohio reported 17 New Albany data centers have property tax abatements of 65% to 100% for 15 years; project-by-project terms were not pulled.