Provident Realty Chesterton data center campus

Withdrawn · Provident withdrew a $1.3 billion, eight-building campus after the town council said it could never support the project at that scale and location. Also known as: Brassie Golf Course site.

← Indiana data centers
Adams CountyAllen CountyBartholomew CountyBenton CountyBlackford CountyBoone CountyBrown CountyCarroll CountyCass CountyClark CountyClay CountyClinton CountyCrawford CountyDaviess CountyDearborn CountyDecatur CountyDeKalb CountyDelaware CountyDubois CountyElkhart CountyFayette CountyFloyd CountyFountain CountyFranklin CountyFulton CountyGibson CountyGrant CountyGreene CountyHamilton CountyHancock CountyHarrison CountyHendricks CountyHenry CountyHoward CountyHuntington CountyJackson CountyJasper CountyJay CountyJefferson CountyJennings CountyJohnson CountyKnox CountyKosciusko CountyLaGrange CountyLake CountyLaPorte CountyLawrence CountyMadison CountyMarion CountyMarshall CountyMartin CountyMiami CountyMonroe CountyMontgomery CountyMorgan CountyNewton CountyNoble CountyOhio CountyOrange CountyOwen CountyParke CountyPerry CountyPike CountyPorter CountyPosey CountyPulaski CountyPutnam CountyRandolph CountyRipley CountyRush CountyScott CountyShelby CountySpencer CountySt. Joseph CountyStarke CountySteuben CountySullivan CountySwitzerland CountyTippecanoe CountyTipton CountyUnion CountyVanderburgh CountyVermillion CountyVigo CountyWabash CountyWarren CountyWarrick CountyWashington CountyWayne CountyWells CountyWhite CountyWhitley CountyProvident Realty Chesterton data center campus · Withdrawn
Status
Withdrawn · as of June 10, 2024
Location
Chesterton (including the former Brassie Golf Course annexation) · Porter County
Floor area
1,200,000 sq ft
Land
200 acres
Investment
$1.3 billion
Developer and team
Provident Realty Advisors
End user
Unnamed hyperscaler
Evidence
News reports; primary records not yet obtained
Size class
50 MW or more (tracker scope)
Map position approximate, from the reported address or area. Updated Oct. 17, 2026.

Updates, newest first

  1. June 10, 2024 Provident tells Chesterton officials it is withdrawing the campus and its 27-acre annexation request. (DatacenterDynamics, June 14, 2024; Inside INdiana Business (via The Times of Northwest Indiana), June 12, 2024)

Conflicts and open questions

  • sqft = eight buildings of 150,000 sq ft each.