16 data center projects in Indiana.
Reviewed hyperscale and contested campuses, IURC large-load dockets (46097, 46322), the state sales-tax exemption and its cost, and 2025-2026 legislation. CAC's tracker counted 57 Indiana proposals as of June 2026 (31 proposed, 7 under construction or operating, 18 withdrawn or defeated). IU's Environmental Resilience Institute counted at least 17 counties with temporary moratoriums and two with bans (Marshall, Cass) by mid-2026; only moratoriums with a dated record are listed here. Notably absent: Cass, White, Putnam and Madison County actions (no dated record reviewed); Amazon's other unnamed $15 billion NW Indiana sites; Meta's reported $800 million southern Indiana project; and smaller Indianapolis projects with no reported MW (Metrobloks, about 14 acres, $500 million; DC Blox, $2 billion). The last two are left out of projects under the size rule but named in the Indianapolis moratorium.
Dot positions are approximate, from the reported address or area. “None found” means our statewide review of news, trackers and county records found nothing; it is not proof none exists.
Every project
Select a heading to sort. Operating hyperscale campuses are included for context.
- Operating
- Built and serving customers.
- Under construction
- Building permits issued or construction reported under way.
- Approved
- A government body has approved land use, zoning or a development agreement for data center use. Other permits may still be pending.
- Proposed
- An application, announcement or public proposal exists; no approval yet.
- Site zoned or marketed
- Land zoned or marketed for possible data center use; no project filed.
- Paused by moratorium
- A local moratorium or ban blocks new applications or approvals.
- Stalled
- No formal application, or blocked by a missing permit or utility capacity.
- Inquiry only
- A developer asked local officials about a site; nothing was filed.
- Withdrawn
- The developer withdrew its application or proposal.
- Denied
- A government body voted it down.
State law and rates
- Indiana's 2019 data center law lets qualifying operators skip the 7% state sales and use tax on equipment and electricity for terms of up to 50 years, set by the Indiana Economic Development Corp. (IEDC) based on how much is invested; a 2024 state tax incentive evaluation projected $2.2 billion to $13.2 billion in qualifying purchases by Amazon, Google and Microsoft, or roughly $150 million to $900 million in forgone sales tax. (WFYI / Mirror Indy, June 10, 2025; Inside INdiana Business / Indianapolis Business Journal, May 1, 2025; Purdue University Dept. of Agricultural Economics (presentation by Ben Inskeep, Citizens Action Coalition), July 7, 2026)
- Exemption cost: after a WTHR and Good Jobs First investigation, the IEDC reported more than $655 million in data center sales and use tax exemptions, about $561 million of it to Amazon; the figure leaves out local property tax abatements and some 2025 reports that were still missing. (The Sales Tax People (summarizing WTHR and Good Jobs First), June 23, 2026)
- HEA 1007 (2025) created a fast-track 'expedited generation resource' process for utilities expecting large load growth and requires that about 80% of the cost of new generation built for big new customers be charged to those customers. It also added tax credits for small modular reactor manufacturing. (WBOI / Indiana Public Broadcasting, April 15, 2025; Earthjustice (press release for Citizens Action Coalition), Nov. 10, 2025; 21Alive (WPTA), Jan. 29, 2026)
- HEA 1210 (2026, signed March 12, 2026) requires a qualified data center user to sign an agreement with local officials before it can use its sales tax award certificate. The Citizens Action Coalition says the act also directs a 1% payment on a data center's electricity use to the host community. (ION Analytics / DWM, June 2026; Citizens Action Coalition, March 2026)
- IURC Cause No. 46097 (approved Feb. 19, 2025): Indiana Michigan Power's large-load settlement for customers of 70 MW at one site or 150 MW in aggregate sets a contract of at least 12 years after a load-ramp period, an 80% minimum monthly billing demand, collateral requirements and exit fees. Signers included Amazon, Google, Microsoft, the Data Center Coalition, the consumer counselor (OUCC) and the Citizens Action Coalition (CAC). (Indiana Utility Regulatory Commission, Feb. 19, 2025; American Electric Power / Indiana Michigan Power (company release), Feb. 19, 2025; Utility Dive, Feb. 20, 2025)
- The IURC approved NIPSCO's plan for a separate generation affiliate, NIPSCO Generation LLC (GenCo), in September 2025 and reaffirmed it on Nov. 19, 2025. GenCo builds and owns power plants for data center customers so that existing NIPSCO customers are shielded from those costs; the cause number was not confirmed in sources reviewed. (NiSource (company release), Sept. 24, 2025; Utility Dive, Nov. 25, 2025)
- IURC Cause No. 46322 (approved June 17, 2026) approved NIPSCO's 15-year special contract with Amazon Data Services, ramping to 2,400 MW by the end of 2032, along with a GenCo power purchase agreement for about 3,000 MW of new gas and battery capacity. Amazon-related costs go in a separate business segment kept out of other customers' rates; CAC opposed the settlement. (Indiana Utility Regulatory Commission, June 17, 2026; NiSource via Business Wire (company release), June 23, 2026; FactSet Insight, Feb. 2, 2026)
- On Jan. 28, 2026, the IURC approved Indiana Michigan Power's expedited generation plan under HEA 1007; the utility expects its peak demand to nearly double by 2030, partly because of data centers. CAC had estimated the plan at more than $7 billion and argued at least 39% of its 2030 costs would fall on other customers. (21Alive (WPTA), Jan. 29, 2026; Earthjustice (press release for Citizens Action Coalition), Nov. 10, 2025)
- Gov. Mike Braun said in March 2026 that data centers coming to Indiana must supply all of their own energy, and on July 23, 2026, he signed the White House's expanded Ratepayer Protection Pledge. Both are policy commitments, not statutes. (Indiana Public Radio (WFYI), March 10, 2026; Indiana Capital Chronicle (via Indiana Public Media), July 23, 2026)
Local moratoriums and bans
| Indianapolis / Marion County | Moratorium | Aug. 19, 2026 | The City-County Council voted 23-1 on Aug. 10 and the Metropolitan Development Commission 6-0 on Aug. 19 to stop new data center approvals through Dec. 31, 2027 while the city writes data center rules. Three projects already approved are exempt: Sabey (Decatur Township), Metrobloks (Martindale-Brightwood) and DC Blox (former Ford Visteon site). (Mirror Indy, Aug. 19, 2026; FOX59, Aug. 19, 2026; Mirror Indy (WFYI), May 5, 2026; Mirror Indy, July 15, 2026; FOX59, July 8, 2026) |
| Wabash County | Moratorium | Aug. 2026 | Commissioners imposed a temporary moratorium on accepting or approving permits for any data center structure in unincorporated areas, lasting until the zoning code is amended or 18 months, whichever comes first. (Wabash County Board of Commissioners, Aug. 2026) |
| Boone County | Moratorium | June 15, 2026 | Commissioners voted unanimously for a one-year moratorium on accepting or reviewing new data center applications in unincorporated areas, in effect through June 15, 2027, at the area plan commission's recommendation. (WRTV, June 15, 2026; Boone County, Indiana, June 15, 2026) |
| Marshall County | Ban | April 20, 2026 | Commissioners adopted a permanent ban on data centers, which county leaders said may be the first in Indiana. (WNDU, April 20, 2026; WFYI, July 6, 2026) |
| Grant County | Moratorium | March 2, 2026 | Commissioners voted 3-0, pending attorney review, for a 24-month moratorium on data center development on unincorporated land; they said no project had been proposed. (Chronicle-Tribune (Marion), March 7, 2026) |
Updates, newest first
- Aug. 19, 2026 Sabey Data Centers Decatur Township campus · The project is exempt from Indianapolis's new data center moratorium because it was already approved. (Mirror Indy, Aug. 19, 2026)
- Aug. 19, 2026 Indianapolis / Marion County: Moratorium · The City-County Council voted 23-1 on Aug. 10 and the Metropolitan Development Commission 6-0 on Aug. 19 to stop new data center approvals through Dec. 31, 2027 while the city writes data center rules. Three projects already approved are exempt: Sabey (Decatur Township), Metrobloks (Martindale-Brightwood) and DC Blox (former Ford Visteon site). (Mirror Indy, Aug. 19, 2026; FOX59, Aug. 19, 2026; Mirror Indy (WFYI), May 5, 2026; Mirror Indy, July 15, 2026; FOX59, July 8, 2026)
- Aug. 18, 2026 Microsoft Granger data center campus · A proposal to put the site in an expanded TIF district goes before county officials. (WNDU, Aug. 18, 2026)
- Aug. 2026 Wabash County: Moratorium · Commissioners imposed a temporary moratorium on accepting or approving permits for any data center structure in unincorporated areas, lasting until the zoning code is amended or 18 months, whichever comes first. (Wabash County Board of Commissioners, Aug. 2026)
- July 29, 2026 Microsoft Granger data center campus · A county council candidate calls for a county data center moratorium and says four of nine council members support one. (WNDU, July 29, 2026)
- July 15, 2026 AWS New Carlisle campus (Project Rainier) · An Epoch AI tracker update lists buildings 1-16 as operating, with more projected for October 2026 and March 2028. (Epoch AI (data center directory), July 15, 2026)
- June 17, 2026 Amazon Hobart data center campus (Hobart Tech Park) · The IURC approves NIPSCO's Amazon special contract; the data center sites are listed in a confidential exhibit. (Indiana Utility Regulatory Commission, June 17, 2026)
- June 17, 2026 Microsoft La Porte data center campus · Microsoft breaks ground and proposes a second phase of six buildings on about 500 acres east of the first. (Northwest Indiana Business Magazine, June 18, 2026)
- June 15, 2026 Meta Lebanon data center campus (LEAP District) · Boone County adopts a one-year moratorium on new data centers in unincorporated areas; the Lebanon LEAP site is inside city limits. (WRTV, June 15, 2026)
- June 15, 2026 Boone County: Moratorium · Commissioners voted unanimously for a one-year moratorium on accepting or reviewing new data center applications in unincorporated areas, in effect through June 15, 2027, at the area plan commission's recommendation. (WRTV, June 15, 2026; Boone County, Indiana, June 15, 2026)
- April 20, 2026 Marshall County: Ban · Commissioners adopted a permanent ban on data centers, which county leaders said may be the first in Indiana. (WNDU, April 20, 2026; WFYI, July 6, 2026)
- April 3, 2026 Google Morgan County data center campus (Monrovia) · Monrovia's town council votes 3-2 to explore annexing the site. (WFIU/WTIU News (Indiana Public Media), April 3, 2026)
- March 18, 2026 Sabey Data Centers Decatur Township campus · The Metropolitan Development Commission approves variances for the campus. Because it came as variances rather than a rezoning, the council could not call it down. (WFYI (Indiana Public Media), March 19, 2026; WRTV, April 3, 2026)
- March 17, 2026 Microsoft Granger data center campus · The St. Joseph County Redevelopment Commission approves a pre-development MOU with Microsoft and Mishawaka. (WNDU, March 17, 2026; WNDU, March 20, 2026)
- March 2, 2026 Grant County: Moratorium · Commissioners voted 3-0, pending attorney review, for a 24-month moratorium on data center development on unincorporated land; they said no project had been proposed. (Chronicle-Tribune (Marion), March 7, 2026)
- Feb. 18, 2026 Microsoft Granger data center campus · St. Joseph County describes a 5-6 building campus with several hundred acres kept as green space; the project was delayed over a year by a dispute about who would provide water and sewer. (ABC57, Feb. 18, 2026)
- Feb. 11, 2026 Meta Lebanon data center campus (LEAP District) · Gov. Braun and Meta break ground on the $10 billion-plus campus, which is expected to bring about 300 permanent jobs and 4,000 construction jobs at peak. (Indiana Economic Development Corp., Feb. 11, 2026; Indiana Capital Chronicle, Feb. 11, 2026)
- Feb. 8, 2026 Amazon Hobart data center campus (Hobart Tech Park) · A resident asks a Lake County judge for a temporary injunction against the fill permit the plan commission had just approved. (FOX 32 Chicago, Feb. 8, 2026)
- Feb. 5, 2026 Amazon Hobart data center campus (Hobart Tech Park) · Reporting says the council approved the project in January; residents object that no site plan or environmental study has been released. (FOX 32 Chicago, Feb. 5, 2026; Hoodline, Feb. 6, 2026)
- Jan. 7, 2026 Amazon Hobart data center campus (Hobart Tech Park) · Ahead of the council vote on the abatement, the mayor says the campus could have up to 25 buildings. (NBC Chicago, Jan. 7, 2026)
- Dec. 16, 2025 Amazon Hobart data center campus (Hobart Tech Park) · Residents have sued the plan commission and city council over the rezoning of residential land for the project. (Inside INdiana Business / Indianapolis Business Journal, Dec. 16, 2025)
- Dec. 11, 2025 Google Fort Wayne data center campus (Project Zodiac) · The campus is reported operating; Google has agreed to a demand-response program with I&M that shifts non-urgent computing away from peak hours. (DatacenterDynamics, Dec. 11, 2025; Site Selection, Dec. 8, 2025)
- Nov. 25, 2025 Amazon Hobart data center campus (Hobart Tech Park) · Mayor Josh Huddlestun confirms Hobart has reached an agreement with Amazon for a campus. (WNDU, Nov. 25, 2025; 21Alive (Inside INdiana Business), Nov. 25, 2025)
- Nov. 24, 2025 Amazon Hobart data center campus (Hobart Tech Park) · Amazon announces $15 billion for new northern Indiana data center campuses adding 2.4 GW, with a NIPSCO deal it says will save other customers about $1 billion over 15 years. (Amazon (company announcement), Nov. 24, 2025; WNDU, Nov. 24, 2025)
- Oct. 29, 2025 AWS New Carlisle campus (Project Rainier) · AWS turns on Project Rainier: seven buildings holding nearly 500,000 Trainium2 chips, used to train and run Anthropic's models. (Converge Digest, Oct. 29, 2025)
- Oct. 21, 2025 Google Morgan County data center campus (Monrovia) · Google confirms it is the developer; commissioners had approved the additional acreage that month. (Inside INdiana Business / Indianapolis Business Journal, Oct. 21, 2025; WFIU/WTIU News (Indiana Public Media), Oct. 22, 2025)
- Sept. 29, 2025 Google Morgan County data center campus (Monrovia) · The county plan commission holds a hearing on rezoning another 158 acres along State Road 42. (WRTV, Sept. 26, 2025)
- Sept. 22, 2025 Google Franklin Township data center (Indianapolis) · Google's attorney withdraws Proposal No. 306 at the City-County Council after most councilors signal opposition; Protect Franklin Township had organized against it. (Mirror Indy, Sept. 22, 2025; WRTV, Sept. 23, 2025)
- Sept. 16, 2025 Google Fort Wayne data center campus (Project Zodiac) · The Indiana Department of Environmental Management issues a permit letting Google fill a little over two acres of wetlands for five more buildings. Most public comments opposed it, and no hearing was held. (DatacenterDynamics, Sept. 22, 2025)
- Sept. 4, 2025 QTS Union Township campus (Jeremiah A and B) · QTS calls county staff to withdraw its application, according to the commissioners' president. (Shorewood Forest News (solwd.net) / Post-Tribune, Sept. 6, 2025; DatacenterDynamics, Sept. 10, 2025)
- July 21, 2025 Google Morgan County data center campus (Monrovia) · Protesters rally outside the Morgan County Justice Complex against the five-building campus. (WFIU/WTIU News (Indiana Public Media), July 22, 2025)
- July 4, 2025 Google Franklin Township data center (Indianapolis) · The project, whose public face is Deep Meadow Ventures LLC, is awaiting a Metropolitan Development Commission rezoning vote; the developer has made 35 written commitments. (Indianapolis Business Journal, July 4, 2025)
- June 30, 2025 Vantage Data Centers Pittsboro campus · Eight residents' suit in Hendricks Circuit Court asks to void the annexation and rezoning and block permits. (Inside INdiana Business / Indianapolis Business Journal, June 30, 2025; Indianapolis Business Journal, July 4, 2025)
- May 15, 2025 Surge Development Hancock County data center megasite · Surge withdraws the request, saying it will work directly with interested users before any future zoning request. (Inside INdiana Business / Indianapolis Business Journal, May 15, 2025)
- May 13, 2025 QTS Union Township campus (Jeremiah A and B) · A standing-room-only town hall at the Porter County Expo Center draws more than 1,000 people, most opposed. (Shorewood Forest News (solwd.net) / Post-Tribune, Sept. 6, 2025)
- May 1, 2025 Provident Realty Burns Harbor data center proposal · IBJ lists the Burns Harbor proposal among northwest Indiana projects scrapped after opposition. (Inside INdiana Business / Indianapolis Business Journal, May 1, 2025)
- April 22, 2025 Prologis Kosciusko County data center proposal · County commissioners vote against the rezoning; no member of the zoning board or commission had supported it. (Inside INdiana Business / Indianapolis Business Journal, May 1, 2025)
- April 16, 2025 Surge Development Hancock County data center megasite · Surge files for a rezoning of up to 776 acres. No end user was signed, and the first phase was about five buildings. (Inside INdiana Business / Indianapolis Business Journal, April 16, 2025)
- March 20, 2025 Google Morgan County data center campus (Monrovia) · Residents sue in Morgan Superior Court over the rezoning. (Indianapolis Business Journal, July 4, 2025)
- March 11, 2025 Agincourt Valparaiso data center proposal · The mayor announces Agincourt has withdrawn and released its option on the land. (Lakeshore Public Media, March 11, 2025; Inside INdiana Business / Indianapolis Business Journal, May 1, 2025)
How this page is built
Each project’s status is the latest public record found in a statewide review of local news, government records, utility filings and trackers; every update links to its source, and the reporting that found it is credited. The review covers campuses of 50 MW or more, or 100 acres or more when power is not reported, plus operating hyperscale campuses for context. Map positions are approximate. A county with no project listed was not found in this review; that is not proof none exists. Political money around these projects has not yet been traced in this state.
Have a filing, agenda or record? Send it to tips@signaldata.org.
Sources
- Mirror Indy, Peter Blanchard, “Indy data center moratorium clears final hurdle,” Aug. 19, 2026
- FOX59, “Metropolitan Development Commission unanimously approves data center moratorium in Indy,” Aug. 19, 2026
- WNDU, “Microsoft data center in Granger could join expanded TIF district,” Aug. 18, 2026
- Wabash County Board of Commissioners, “Ordinance Imposing a Temporary Moratorium on the Issuance of Improvement Location Permits for the Development of Data Centers,” Aug. 2026
- WNDU, “St. Joseph County Council candidate calls for data center moratorium,” July 29, 2026
- Indiana Capital Chronicle (via Indiana Public Media), Leslie Bonilla Muñiz, “Indiana governor signs Trump data center ratepayer protection pledge,” July 23, 2026
- Mirror Indy, Darian Benson, “DC Blox data center OK'd by city officials,” July 15, 2026
- Epoch AI (data center directory), “Anthropic-Amazon New Carlisle,” July 15, 2026
- FOX59, “Georgia developer finalizes plans to downsize $2 billion data center on Indy's east side; cites community feedback,” July 8, 2026
- Purdue University Dept. of Agricultural Economics (presentation by Ben Inskeep, Citizens Action Coalition), Ben Inskeep, “Impact and Policy: Data Centers in Indiana and Surrounding States,” July 7, 2026
- WFYI, Farrah Anderson, “Nearly a third of Indiana counties have moved to restrict data centers,” July 6, 2026
- The Sales Tax People (summarizing WTHR and Good Jobs First), “Indiana Just Revealed It's Giving Away $655 Million a Year in Data Center Sales Tax Exemptions. Most of It Goes to Amazon.,” June 23, 2026
- NiSource via Business Wire (company release), “Regulatory Approvals Underscore Strength of NiSource's Customer-Focused Data Center Strategy Supporting Growth in Indiana,” June 23, 2026
- Northwest Indiana Business Magazine, Heather Pfundstein, “Microsoft breaks ground on La Porte data center,” June 18, 2026
- Indiana Utility Regulatory Commission, “Order, Cause No. 46322: Verified Joint Petition of NIPSCO and NIPSCO Generation LLC (Amazon special contract, GenCo PPA),” June 17, 2026
- WRTV, “Boone County approves moratorium on new data centers,” June 15, 2026
- Boone County, Indiana, Sean Horan, “Boone County Commissioners Approve Moratorium on Data Centers,” June 15, 2026
- ION Analytics / DWM, “Data Center Legislative Tracker: Passed (version 1.2),” June 2026
- Mirror Indy (WFYI), Farrah Anderson, “Indianapolis council approves data center for Martindale-Brightwood,” May 5, 2026
- WNDU, “Marshall County commissioners ban data centers, advance new limit on solar projects,” April 20, 2026
- WRTV, “Metrobloks' $500 million data center approved despite neighborhood concerns,” April 3, 2026
- WFIU/WTIU News (Indiana Public Media), Ethan Sandweiss, “Monrovia explores annexing site of future Google data center,” April 3, 2026
- WNDU, “Answering your Microsoft data center questions,” March 20, 2026
- WFYI (Indiana Public Media), Farrah Anderson, “Indianapolis approves plan to build $4B data center in Decatur Township after months of pushback,” March 19, 2026
- WNDU, John Beomsoo Kim, “Microsoft data center MOU approved in St. Joseph County amid resident concerns,” March 17, 2026
- Indiana Public Radio (WFYI), Ben Thorp, “Braun touts efforts to bring down energy costs following session, highlights data center agreement,” March 10, 2026
- Chronicle-Tribune (Marion), Laura Mack, “Commissioners pass data center moratorium,” March 7, 2026
- Citizens Action Coalition, “2026 Week 10 Final Statehouse Report,” March 2026
- ABC57, Dante Stanton, “County provides update on Microsoft data center development,” Feb. 18, 2026
- Indiana Economic Development Corp., “Gov. Braun Breaks Ground on $10B Meta Data Center Campus at LEAP District,” Feb. 11, 2026
- Indiana Capital Chronicle, Niki Kelly, “Details on long-expected Meta data center campus unveiled,” Feb. 11, 2026
- FOX 32 Chicago, Bret Buganski, “Lawsuit seeks to block Amazon data center permit in Hobart, Ind.,” Feb. 8, 2026
- Hoodline, “Hobart Neighbors Rage as Amazon Data Hub Plan Hits New Roadblock,” Feb. 6, 2026
- FOX 32 Chicago, Bret Buganski, “'We want transparency before approvals happen': Residents oppose proposed $11 billion Amazon data center,” Feb. 5, 2026
- FactSet Insight, Eric Yussman, “NIPSCO Proposes Special Contract for Amazon Data Centers in Indiana,” Feb. 2, 2026
- 21Alive (WPTA), “Indiana Utility Regulatory Commission approves I&M's latest power plan,” Jan. 29, 2026
- NBC Chicago, Vi Nguyen, “Hobart to vote on property tax abatement on Amazon data center project,” Jan. 7, 2026
- Inside INdiana Business / Indianapolis Business Journal, Cameron Shaw, “Hobart city officials sued by residents over rezoning for new Amazon data center,” Dec. 16, 2025
- DatacenterDynamics, Georgia Butler, “Google's $2bn data center now operational in Fort Wayne, Indiana,” Dec. 11, 2025
- Site Selection, Daniel Monaghan, “Google This: $2 Billion in Fort Wayne,” Dec. 8, 2025
- WNDU, “Amazon planning $15 billion data center project in Hobart,” Nov. 25, 2025
- Utility Dive, “NIPSCO to supply 3 GW to Amazon data centers in northern Indiana,” Nov. 25, 2025
- 21Alive (Inside INdiana Business), “Hobart reaches agreement with Amazon for next-gen data center,” Nov. 25, 2025
- WNDU, John Bailey and WNDU Staff, “Amazon announces $15 billion investment in data center campuses in Northern Indiana,” Nov. 24, 2025
- Amazon (company announcement), Amazon Staff, “Amazon plans to invest $15 billion in Northern Indiana to build new data center campuses and advance AI innovation,” Nov. 24, 2025
- Earthjustice (press release for Citizens Action Coalition), Kathryn McGrath, “Indiana Utility I&M Proposes More Than $7 Billion Generation Plan for Amazon and Google AI Data Centers,” Nov. 10, 2025
- Converge Digest, Jim Carroll, “AWS Activates Project Rainier Data Center Campus,” Oct. 29, 2025
- WFIU/WTIU News (Indiana Public Media), “After months of mystery, Google confirmed as data center developer in Morgan County,” Oct. 22, 2025
- Inside INdiana Business / Indianapolis Business Journal, Marek Mazurek, “Google reveals itself as developer behind 500-acre Morgan County data center campus,” Oct. 21, 2025
- WRTV, “Morgan County hopes to rezone more land for proposed data center,” Sept. 26, 2025
- NiSource (company release), “NiSource Achieves IURC Regulatory Approval for GenCo Strategy,” Sept. 24, 2025
- WRTV, “Google withdraws rezoning petition for proposed data center in Franklin Township,” Sept. 23, 2025
- Mirror Indy, Elizabeth Gabriel, “Southsiders prevail in fight against Google data center,” Sept. 22, 2025
- DatacenterDynamics, Charlotte Trueman, “Indiana approves expanding Google's Fort Wayne data center campus onto protected wetlands, despite local opposition,” Sept. 22, 2025
- DatacenterDynamics, Matthew Gooding, “QTS cans data center scheme in Porter County, Indiana, after protests,” Sept. 10, 2025
- Shorewood Forest News (solwd.net) / Post-Tribune, “QTS withdraws proposal for two Union Township data centers,” Sept. 6, 2025
- WFIU/WTIU News (Indiana Public Media), “Protesters say planned Monrovia data center exploits residents,” July 22, 2025
- Indianapolis Business Journal, Susan Orr, “Data center projects facing local pushback,” July 4, 2025
- Inside INdiana Business / Indianapolis Business Journal, Susan Orr, “Pittsboro residents ask court to halt planned Hendricks County data center,” June 30, 2025
- WFYI / Mirror Indy, Elizabeth Gabriel, “Data center tax breaks could leave Indiana $2.2 billion short,” June 10, 2025
- Inside INdiana Business / Indianapolis Business Journal, Marek Mazurek, “Developer withdraws plans for massive Hancock County data center,” May 15, 2025
- Inside INdiana Business / Indianapolis Business Journal, Marek Mazurek, “Indiana state officials want to attract data centers. Local communities are beginning to push back,” May 1, 2025
- Inside INdiana Business / Indianapolis Business Journal, Mickey Shuey, “Hancock County officials to consider proposal for 776-acre data center campus,” April 16, 2025
- WBOI / Indiana Public Broadcasting, Rebecca Thiele, “Bill to help power AI data centers puts more risk on tech companies, but Hoosiers would still pay,” April 15, 2025
- Lakeshore Public Media, Michael Gallenberger, “Valpo pulls plug on data center proposal following public opposition,” March 11, 2025
- Utility Dive, Ethan Howland, “Indiana regulators approve 'large load' interconnection rules,” Feb. 20, 2025
- Indiana Utility Regulatory Commission, “Order, Cause No. 46097: Verified Petition of Indiana Michigan Power Co. for approval of modifications to its Industrial Power Tariff (Tariff I.P.),” Feb. 19, 2025
- WFIU/WTIU News (Indiana Public Media), Clayton Baumgarth, “Proposed Monrovia data center clears another hurdle,” Feb. 19, 2025
- American Electric Power / Indiana Michigan Power (company release), “Indiana Michigan Power Receives Order in Large Load Settlement,” Feb. 19, 2025
- Inside INdiana Business, Alex Brown, “Plans progressing for Microsoft's northern Indiana data centers,” Jan. 7, 2025
- DatacenterDynamics, Georgia Butler, “Application for $1.3bn data center in Chesterton, Indiana, withdrawn,” June 14, 2024
- Inside INdiana Business (via The Times of Northwest Indiana), “Chesterton data center project withdrawn,” June 12, 2024
- Indianapolis Business Journal (Inside INdiana Business), Alex Brown, “Microsoft planning $1B data center in Indiana,” June 4, 2024
- WANE 15, “'Historic day': Google's $2 billion data center campus to partner with I&M, Ivy Tech,” April 26, 2024
- Inside INdiana Business, IBJ Staff, “Amazon Web Services plans $11B data center campus near South Bend,” April 25, 2024