Data center project · St. Joseph County, Indiana
Microsoft Granger data center campus
Proposed · Microsoft plans 5-6 data center buildings on about 930 acres of farmland in Granger; residents are worried about Juday Creek, drainage and generator emissions. Also known as: St. Joe Farm site.
- Status
- Proposed · as of March 17, 2026
- Location
- Granger, former St. Joe Farm property · St. Joseph County
- Status note
- The county redevelopment commission approved a pre-development MOU on March 17, 2026; there is no final site plan yet. Construction is expected in late 2026 or early 2027.
- Land
- 930 acres
- Investment
- Not disclosed; Microsoft paid $77.5 million for the land, and pre-development work is capped at about $12.6 million.
- Developer and team
- Microsoft
- End user
- Microsoft
- Water
- Mishawaka is the water and sewer provider; Microsoft is to pay about $30 million for domestic service. A county councilman says cooling will use a closed-loop coolant trucked in from outside the county.
- Incentives
- A proposal to add the site to an expanded TIF district was pending in August 2026.
- Evidence
- News reports; primary records not yet obtained
- Size class
- 50 MW or more (tracker scope)
Updates, newest first
- Aug. 18, 2026 A proposal to put the site in an expanded TIF district goes before county officials. (WNDU, Aug. 18, 2026)
- July 29, 2026 A county council candidate calls for a county data center moratorium and says four of nine council members support one. (WNDU, July 29, 2026)
- March 17, 2026 The St. Joseph County Redevelopment Commission approves a pre-development MOU with Microsoft and Mishawaka. (WNDU, March 17, 2026; WNDU, March 20, 2026)
- Feb. 18, 2026 St. Joseph County describes a 5-6 building campus with several hundred acres kept as green space; the project was delayed over a year by a dispute about who would provide water and sewer. (ABC57, Feb. 18, 2026)
- Jan. 7, 2025 County records show Microsoft bought nearly 930 acres from St. Joe Farm for $77.5 million. (Inside INdiana Business, Jan. 7, 2025)
Conflicts and open questions
- One resident said she was told the campus would have 300 gas generators, but a county councilman says it will have no on-site generation. This conflict is unresolved.
- MW and serving utility not confirmed.
Have records about this project? Send them to tips@signaldata.org.