Data center project · Morgan County, Indiana
Google Morgan County data center campus (Monrovia)
Approved · After months of secrecy under nondisclosure agreements, Google confirmed in October 2025 that it is behind a five-building campus on rezoned farmland east of Monrovia.
- Status
- Approved · as of Oct. 2025
- Approved by
- Morgan County Board of Commissioners (Indiana)
Rezoning of about 390 acres of farmland, Feb. 18, 2025, vote Unanimous (WFIU/WTIU News (Indiana Public Media), Feb. 19, 2025) - Approved by
- Morgan County Board of Commissioners (Indiana)
Rezoning of 158 additional acres along State Road 42, Oct. 2025
Vote count not reported. (WFIU/WTIU News (Indiana Public Media), Oct. 22, 2025; Inside INdiana Business / Indianapolis Business Journal, Oct. 21, 2025) - Location
- East of Monrovia along State Road 42 · Morgan County
- Status note
- County commissioners rezoned about 390 acres in February 2025 and 158 more in October 2025. A resident lawsuit was pending, and in April 2026 Monrovia began exploring annexation of the site.
- Land
- 548 acres
- Investment
- Not disclosed; local officials call it a billion-dollar project.
- Developer and team
- End user
- Incentives
- IEDC approved incentives in June 2025 (amount not reported).
- Evidence
- News reports; primary records not yet obtained
- Size class
- 50 MW or more (tracker scope)
Updates, newest first
- April 3, 2026 Monrovia's town council votes 3-2 to explore annexing the site. (WFIU/WTIU News (Indiana Public Media), April 3, 2026)
- Oct. 21, 2025 Google confirms it is the developer; commissioners had approved the additional acreage that month. (Inside INdiana Business / Indianapolis Business Journal, Oct. 21, 2025; WFIU/WTIU News (Indiana Public Media), Oct. 22, 2025)
- Sept. 29, 2025 The county plan commission holds a hearing on rezoning another 158 acres along State Road 42. (WRTV, Sept. 26, 2025)
- July 21, 2025 Protesters rally outside the Morgan County Justice Complex against the five-building campus. (WFIU/WTIU News (Indiana Public Media), July 22, 2025)
- March 20, 2025 Residents sue in Morgan Superior Court over the rezoning. (Indianapolis Business Journal, July 4, 2025)
- Feb. 18, 2025 Morgan County commissioners vote unanimously to rezone about 390 acres for a data center whose developer was unnamed; residents raise concerns about noise, water, energy and secrecy. (WFIU/WTIU News (Indiana Public Media), Feb. 19, 2025)
Conflicts and open questions
- Acreage varies: about 390 acres first rezoned plus 158 more (about 548 total), versus 500 acres in IBJ's headline.
- The Feb. 18 vote date is inferred from a report describing a 'Tuesday' vote published Feb. 19, 2025.
- MW not disclosed.
Have records about this project? Send them to tips@signaldata.org.