Data center project · Porter County, Indiana

QTS Union Township campus (Jeremiah A and B)

Withdrawn · QTS pulled its planned-unit-development request for two campuses totaling about 786 acres near Union Township schools after a town hall drew more than 1,000 opponents. Also known as: Jeremiah A, Jeremiah B.

← Indiana data centers
Adams CountyAllen CountyBartholomew CountyBenton CountyBlackford CountyBoone CountyBrown CountyCarroll CountyCass CountyClark CountyClay CountyClinton CountyCrawford CountyDaviess CountyDearborn CountyDecatur CountyDeKalb CountyDelaware CountyDubois CountyElkhart CountyFayette CountyFloyd CountyFountain CountyFranklin CountyFulton CountyGibson CountyGrant CountyGreene CountyHamilton CountyHancock CountyHarrison CountyHendricks CountyHenry CountyHoward CountyHuntington CountyJackson CountyJasper CountyJay CountyJefferson CountyJennings CountyJohnson CountyKnox CountyKosciusko CountyLaGrange CountyLake CountyLaPorte CountyLawrence CountyMadison CountyMarion CountyMarshall CountyMartin CountyMiami CountyMonroe CountyMontgomery CountyMorgan CountyNewton CountyNoble CountyOhio CountyOrange CountyOwen CountyParke CountyPerry CountyPike CountyPorter CountyPosey CountyPulaski CountyPutnam CountyRandolph CountyRipley CountyRush CountyScott CountyShelby CountySpencer CountySt. Joseph CountyStarke CountySteuben CountySullivan CountySwitzerland CountyTippecanoe CountyTipton CountyUnion CountyVanderburgh CountyVermillion CountyVigo CountyWabash CountyWarren CountyWarrick CountyWashington CountyWayne CountyWells CountyWhite CountyWhitley CountyQTS Union Township campus (Jeremiah A and B) · Withdrawn
Status
Withdrawn · as of Sept. 4, 2025
Location
Union Township near Wheeler, around County Road 450 North between 650 West and 750 West · Porter County
Land
786 acres
Investment
$2 billion
Developer and team
QTS Data Centers (Blackstone)
Evidence
News reports; primary records not yet obtained
Size class
50 MW or more (tracker scope)
Map position approximate, from the reported address or area. Updated Oct. 17, 2026.

Updates, newest first

  1. Sept. 4, 2025 QTS calls county staff to withdraw its application, according to the commissioners' president. (Shorewood Forest News (solwd.net) / Post-Tribune, Sept. 6, 2025; DatacenterDynamics, Sept. 10, 2025)
  2. May 13, 2025 A standing-room-only town hall at the Porter County Expo Center draws more than 1,000 people, most opposed. (Shorewood Forest News (solwd.net) / Post-Tribune, Sept. 6, 2025)

Conflicts and open questions

  • Acreage: 351.85 + 434.46 parcels (solwd/Post-Tribune). DCD rounds to 800. The Sept. 4 date is inferred from a 'Thursday' call reported Sept. 6, 2025.

Have records about this project? Send them to tips@signaldata.org.