Data centers · Polk County, Florida
Polk County
3 projects on record · 1 moratorium or ban action
← Statewide map| Fort Meade campus | Stonebridge (Bethesda, Md.); Fort Meade LLC (shares Stonebridge’s address) | 1,200 | Approved | April 14, 2026 | 50 MW+ |
| Cielo Haines City | Cielo Digital Infrastructure (Texas) | 300 | Stalled | June 25, 2026 | 50 MW+ |
| Project Swan | Ryan Companies (Tyler Lohmiller) | 100 | Paused by moratorium | Aug. 3, 2026 | 50 MW+ |
Moratoriums and bans
- Aug. 3, 2026 Lakeland: Moratorium. One year, 4-3; bars city utility service. (LkldNow via WUSF, Aug. 3, 2026)
Updates, newest first
- Aug. 3, 2026 Project Swan · Lakeland adopts a one-year moratorium, 4-3. (LkldNow via WUSF, Aug. 3, 2026)
- Aug. 3, 2026 Lakeland: Moratorium · One year, 4-3; bars city utility service. (LkldNow via WUSF, Aug. 3, 2026)
- July 7, 2026 Project Swan · Moratorium hearing draws a crowd; concept review only, no application filed. (LkldNow, July 7, 2026)
- June 30, 2026 Fort Meade campus · Fort Meade LLC, which shares an address with Stonebridge, gives $10,000 to Friends of Byron Donalds PAC. (Florida Division of Elections, Oct. 16, 2026; Tampa Bay Times (syndicated by Tribune Content Agency), Aug. 1, 2026)
- June 25, 2026 Cielo Haines City · Project stalls; city lacks water capacity. (FOX 13 Tampa Bay, June 25, 2026)
- April 17, 2026 Fort Meade campus · FloridaCommerce Secretary J. Alex Kelly writes that the plan is fundamentally flawed and its water estimate too low. (WUSF, April 20, 2026; FOX 13 Tampa Bay, April 16, 2026)
- April 14, 2026 Fort Meade campus · City commissioners unanimously approve a 20-year development agreement; SWFWMD tells the city a new water permit is needed. (FOX 13 Tampa Bay, April 14, 2026; WUSF, April 15, 2026)
- 2025 Fort Meade campus · Rezoning and tax break approved. (WUSF via WLRN, April 8, 2026)
Statewide
Florida’s data center law, SB 484, took effect July 1, 2026: large-load customers pay the full cost of their power, and local governments keep the power to deny projects. The state’s sales-tax exemption for data centers of 100 MW or more runs to 2037. The rules →