Data center project · Polk County, Florida
Project Swan
Paused by moratorium · About 100 MW cloud facility proposed for annexation into Lakeland; paused.
- Status
- Paused by moratorium · as of Aug. 3, 2026
- Location
- West Lakeland (923 Wilkinson Rd., per one tracker) · Polk County
- Status note
- Concept review only; Lakeland adopted a one-year moratorium 4-3 that bars city utility service to data centers.
- Power
- 100 MW
- Floor area
- 550,000 sq ft
500,000–600,000 sq ft. - Developer and team
- Ryan Companies (Tyler Lohmiller)
- End user
- Not stated. The developer says it is a cloud and edge facility, not an AI data center.
- Utility
- Lakeland Electric
- Evidence
- News reports; primary records not yet obtained
- Size class
- 50 MW or more (tracker scope)
Updates, newest first
- Aug. 3, 2026 Lakeland adopts a one-year moratorium, 4-3. (LkldNow via WUSF, Aug. 3, 2026)
- July 7, 2026 Moratorium hearing draws a crowd; concept review only, no application filed. (LkldNow, July 7, 2026)
Have records about this project? Send them to tips@signaldata.org.