Data center project · Monroe County, Georgia
Bolingbroke Technology Campus
Denied · A 1.2 GW, nine-building proposal on 970 residential acres that Monroe commissioners rejected unanimously.
- Status
- Denied · as of Aug. 5, 2025
- Denied by
- Monroe County Board of Commissioners (Georgia)
Rezoning of the land for commercial use, Aug. 5, 2025, vote Unanimous (DatacenterDynamics, Aug. 6, 2025) - Location
- Northwest of Macon along U.S. 41, Wadley Road and I-475 · Monroe County
- Power
- 1,200 MW
Six 100 MW and three 200 MW buildings - Land
- 970 acres
- Developer and team
- Bolingbroke Technology Center
- Evidence
- News reports; primary records not yet obtained
- Size class
- 50 MW or more (tracker scope)
Updates, newest first
- Aug. 5, 2025 The Monroe County Commission unanimously denied rezoning the land for commercial use. (DatacenterDynamics, Aug. 6, 2025)