Data center project · Taylor County, Texas
Stargate Abilene (Lancium Clean Campus)
Under construction · The first Stargate campus, an eight-building AI campus that Crusoe is building on Lancium land for Oracle and OpenAI. Also known as: Project Radiance, Lancium Clean Campus.
- Status
- Under construction · as of April 2026
- Approved by
- Abilene City Council
Tax abatement agreements (Phases 1/2 through 8) with Lancium LLC and the Abilene DC entities, plus amendments to the 2025 restated abatement agreements (Resolution No. 171-2025), Aug. 28, 2025
The resolution recites earlier City Council approvals of Lancium abatement agreements on Dec. 17, 2021, June 13, 2024 and Feb. 13, 2025, and a reinvestment zone (RZ21-1) designated Feb. 13, 2025. Vote count is not shown on the resolution. Reporting says the agreement is tied to the Development Corporation of Abilene. (City of Abilene, Aug. 28, 2025; Business Insider (via AOL), July 17, 2025) - Approved by
- Taylor County Commissioners Court
20-year county property tax abatement
KACU reports that Taylor County commissioners approved a 20-year abatement after the project was announced, but gives no date and does not name the agreement holder; confirm against county minutes. (KACU (via KTTZ), Sept. 4, 2026) - Location
- far north Abilene · Taylor County
- Status note
- Partly energized; Epoch AI estimated about half of eight buildings running in April 2026, with full build-out projected for late 2026.
- Power
- 1,200 MW
Crusoe-stated campus capacity of 1.2 GW; Epoch AI put operating facility power at roughly 0.3 GW in April 2026. - Floor area
- 4,000,000 sq ft
- Investment
- Up to $3.5 billion committed by Crusoe under its abatement deal, per Business Insider
- Developer and team
- Crusoe; Lancium
- End user
- Oracle for OpenAI (Stargate)
- Incentives
- City of Abilene abatement of 80% once operating (KTAB) or 85% (Business Insider), tied to an agreement with the Development Corporation of Abilene; Taylor County commissioners approved a 20-year property tax abatement (KACU).
- Evidence
- News reports; primary records not yet obtained
- Size class
- 50 MW or more (tracker scope)
Updates, newest first
- Sept. 2, 2026 An Abilene Chamber panel heard resident concerns about rents, power bills, water and the county's 20-year abatement. (KACU (via KTTZ), Sept. 4, 2026)
- April 17, 2026 Epoch AI reported roughly four of eight buildings operating and projected completion in the fourth quarter of 2026. (Epoch AI, April 17, 2026)
- July 2025 Taylor County commissioners heard that a tenant was protesting the site's appraised value; preliminary new value on the Lancium property was about $560 million. (KTAB/KRBC (BigCountryHomepage.com), July 9, 2025; Business Insider (via AOL), July 17, 2025)
- March 18, 2025 Crusoe announced a second phase of six more buildings, bringing the campus to eight buildings and 1.2 GW. (KTAB/KRBC (BigCountryHomepage.com), March 24, 2025)
- June 2024 Crusoe began work on the first two buildings, totaling about 980,000 square feet and more than 200 MW. (KTAB/KRBC (BigCountryHomepage.com), March 24, 2025)
Conflicts and open questions
- City abatement share reported as 80% (KTAB) and 85% (Business Insider); the abatement agreement itself was not located.
- The KACU report does not say which project the 20-year Taylor County abatement covers; confirm against county minutes.
- A planned expansion to 2.1 GW at this site was dropped, per Epoch AI; the adjacent Microsoft campus is tracked separately.