25 data center projects in Texas.
Reviewed Stargate and hyperscale campuses, contested county proposals in Hood, Hill, Bastrop, Brazoria, Hays, Williamson and Tarrant, local moratoriums, SB 6 and PUCT/ERCOT large-load rules, and the state sales tax exemption. Not yet covered: Compass and other Ellis County (Red Oak) campuses, operating Microsoft (San Antonio), Meta (Fort Worth, Temple) and AWS campuses, the Google-backed TeraWulf/Fluidstack site in Abernathy, Fort Worth's Edged project, CloudBurst in Hays County, and other Hill and Caldwell County proposals; no xAI campus in Texas was found.
Dot positions are approximate, from the reported address or area. “None found” means our statewide review of news, trackers and county records found nothing; it is not proof none exists.
Every project
| Fermi America Project Matador (HyperGrid campus) | Carson | Fermi America | 11,000 | Under construction | Feb. 25, 2026 | 50 MW+ |
| Vantage Frontier | Shackelford | Vantage Data Centers | 1,400 | Under construction | April 2026 | 50 MW+ |
| Stargate Abilene (Lancium Clean Campus) | Taylor | Crusoe; Lancium | 1,200 | Under construction | April 2026 | 50 MW+ |
| Stargate Milam County (SB Energy) | Milam | SB Energy (SoftBank) | 1,200 | Under construction | April 2026 | 50 MW+ |
| Meta El Paso data center | El Paso | Meta | 1,000 | Under construction | Oct. 2025 | 50 MW+ |
| Crusoe Abilene campus for Microsoft | Taylor | Crusoe | 900 | Under construction | March 27, 2026 | 50 MW+ |
| Riot Platforms Rockdale data center site | Milam | Riot Platforms | 700 | Under construction | Jan. 16, 2026 | 50 MW+ |
| Old Ocean Data Center | Brazoria | Nightpeak Energy | 620 | Proposed | March 10, 2026 | 50 MW+ |
| Pacifico Cedar Creek data center and power campus | Bastrop | Pacifico Energy; Black Chamber Partners | 490 | Proposed | Aug. 19, 2026 | 50 MW+ |
| CyrusOne DFW10 at Thad Hill Energy Center | Bosque | CyrusOne | 144 | Under construction | July 31, 2025 | 50 MW+ |
| Fort Spunky data center | Hood | Pacifico Energy | 100 | Denied | March 10, 2026 | 50 MW+ |
| EdgeConneX Cedar Creek campus (DFW33220N) | Bastrop | EdgeConneX | 96 | Under construction | Sept. 24, 2025 | 50 MW+ |
| Amazon Pecos County data center campus | Pecos | Amazon | — | Proposed | Aug. 11, 2026 | 50 MW+ |
| Black Mountain data center campus | Tarrant | Black Mountain | — | Proposed | July 2026 | 50 MW+ |
| Comanche Circle | Hood | Sailfish Investors | — | Stalled | Oct. 13, 2026 | 50 MW+ |
| Crusoe data center south of Claude | Armstrong | Crusoe | — | Approved | Oct. 14, 2025 | 50 MW+ |
| EdgeConneX second Bastrop County campus | Bastrop | EdgeConneX | — | Proposed | March 26, 2026 | 50 MW+ |
| Google Haskell County campuses | Haskell | — | Proposed | Nov. 17, 2025 | Under 50 MW | |
| Google Midlothian and Red Oak campuses | Ellis | — | Operating | Nov. 2025 | Under 50 MW | |
| Haskell County Ranger RZ 2026 data center | Haskell | Ascendant Site Solutions LLC | — | Proposed | Jan. 9, 2026 | 50 MW+ |
| Highlander SM One data center | Hays | Highlander SM One LLC | — | Denied | Feb. 17, 2026 | 50 MW+ |
| Kilby (Chevron power for Microsoft data center) | Reeves | Chevron (Energy Forge One); Engine No. 1 | — | Proposed | June 22, 2026 | Under 50 MW |
| Project Aquila (RCM Hill LLC) | Hill | RCM Hill LLC | — | Proposed | July 15, 2026 | 50 MW+ |
| Project Red and Project Yellow | Hood | — | — | Proposed | June 2026 | 50 MW+ |
| Taylor Technology Campus | Williamson | Big Watt Digital; PowerHouse Data Centers | — | Approved | Oct. 8, 2026 | 50 MW+ |
Select a heading to sort. Operating hyperscale campuses are included for context.
- Operating
- Built and serving customers.
- Under construction
- Building permits issued or construction reported under way.
- Approved
- A government body has approved land use, zoning or a development agreement for data center use. Other permits may still be pending.
- Proposed
- An application, announcement or public proposal exists; no approval yet.
- Site zoned or marketed
- Land zoned or marketed for possible data center use; no project filed.
- Paused by moratorium
- A local moratorium or ban blocks new applications or approvals.
- Stalled
- No formal application, or blocked by a missing permit or utility capacity.
- Inquiry only
- A developer asked local officials about a site; nothing was filed.
- Withdrawn
- The developer withdrew its application or proposal.
- Denied
- A government body voted it down.
State law and rates
- SB 6 (89th Legislature, 2025) makes the PUCT set interconnection standards for loads of 75 MW or more in ERCOT, requiring site control, study fees, financial security, disclosure of duplicate requests and backup generation, and emergency curtailment of new large loads; effective June 20, 2025, with PUCT rules due by Dec. 31, 2026 (Projects 58479-58484, 58000). (POWER Magazine, Aug. 4, 2026; Foley & Lardner, March 31, 2026)
- PUCT draft large-load interconnection rule (published March 2026) would require $50,000 per MW in security, $100,000-$300,000 study fees, a $50,000-per-MW nonrefundable fee and full customer payment of direct interconnection costs; interconnection standards rulemaking (Project 58481) was still in scoping as of August 2026. (Foley & Lardner, March 31, 2026; POWER Magazine, Aug. 4, 2026)
- ERCOT batch study framework (NPRR1325/PGRR145), approved by the PUCT June 18, 2026, required $50,000 per MW of security by July 10 for 'Batch Zero', with results due April 2027; large-load requests totaled about 474 GW in June 2026, about 421 GW of it data centers. (POWER Magazine, Aug. 4, 2026)
- Gov. Abbott's Aug. 3, 2026 directive ordered the PUCT and ERCOT to audit every data center in the interconnection queue and deny grid access to projects that fail to disclose ownership, financial, water and community-impact information, which several outlets described as a de facto statewide pause. (POWER Magazine, Aug. 4, 2026; E&E News by POLITICO, Aug. 11, 2026)
- State sales and use tax exemption for qualifying data centers (Tax Code Secs. 151.359 and 151.3595; created by HB 1223, 83rd Legislature, 2013, expanded 2015); the Comptroller has certified 138 data centers, and estimates of cost run from about $3.2 billion for 2026-27 to $3.3 billion for 2028-29. (Public Citizen (testimony to Texas Senate Finance Committee), July 27, 2026; Texas Public Radio / The Texas Newsroom, July 28, 2026)
- Local property tax abatements under Tax Code Chapter 312 are the main county and city incentive; school-district value limits under Chapter 313 expired at the end of 2022 and were replaced by the JETI program (HB 5, 88th Legislature, 2023), which data center power projects such as Pacifico's Bastrop proposal have applied to. (Community Impact, Feb. 23, 2024; Community Impact, July 15, 2026; Haskell County Commissioners Court, Jan. 9, 2026)
Local moratoriums and bans
| Taylor | Ban petition (rejected) | Oct. 8, 2026 | City officials said a resident petition to restrict data centers could not go forward through the initiative process under Texas law. (CBS Austin, Oct. 8, 2026; San Antonio Express-News (via GovTech/TNS), July 17, 2026) |
| Fort Worth | Moratorium (proposed) | Aug. 12, 2026 | The council voted unanimously to start the process for a 90-day moratorium on new data center construction, created a data center committee, and required proof of state grid approval before applications; the pause would not take effect until 2027. (FOX 4 Dallas-Fort Worth, Aug. 11, 2026; Fort Worth Report (via Green Source Texas), July 9, 2026) |
| Brownsville | Moratorium (proposed) | Aug. 4, 2026 | A commission workshop weighed a 90-day pause, extendable to 180 days, plus rules limiting data centers to heavy industrial zones with special permits and closed-loop cooling. (City of Brownsville, Aug. 4, 2026; KRGV, Aug. 2026) |
| Athens | Ban (disputed) | Aug. 2026 | CRE Daily reported a 3-2 vote to ban data centers; KETK reported the city instead halted drafting local rules until state guidance arrives. (CRE Daily, Sept. 8, 2026; KETK, Aug. 7, 2026) |
| Laredo | Moratorium (dropped) | Aug. 2026 | City weighed and then dropped a moratorium. (CRE Daily, Sept. 8, 2026) |
| Lockhart | Regulations (in drafting) | July 16, 2026 | City leaders asked staff for very strict data center standards rather than an outright ban, citing litigation risk. (San Antonio Express-News (via GovTech/TNS), July 17, 2026) |
| Hays County | Pause on discretionary approvals | June 23, 2026 | After tabling a moratorium in February, commissioners unanimously suspended discretionary approvals such as abatements for data centers and other water-heavy projects through year-end and created a water review board. (KUT 90.5, June 23, 2026; Spectrum News, May 19, 2026) |
| San Marcos | Ban | June 16, 2026 | The council voted 4-3 to bar data centers from every zoning district; an April 21 version failed 3-4. (Community Impact, June 17, 2026) |
| Hill County | Moratorium (rescinded) | May 2026 | Commissioners voted 3-2 for a one-year pause on new data center construction in unincorporated areas, then voted unanimously on June 4 to rescind it after a $100 million federal lawsuit and to adopt a data center checklist. (KWTX, July 15, 2026; The Texas Tribune, June 5, 2026; K&L Gates, June 10, 2026) |
| Somervell County | Resolution | May 2026 | Commissioners unanimously passed a resolution opposing data center construction until the Legislature acts, after an earlier moratorium motion failed. (Spectrum News, May 19, 2026) |
| Hood County | Moratorium (failed) | Feb. 10, 2026 | A six-month pause on new industrial development including data centers failed 3-2; a second try failed by the same margin on Feb. 24 after a state senator questioned county authority. (The Texas Tribune, Feb. 10, 2026; CBS News Texas, Feb. 24, 2026) |
| Henderson County | Resolution | 2026 | Commissioners passed a resolution voicing concern about large data centers' effects on infrastructure and natural resources. (KETK, Aug. 7, 2026) |
| El Paso County | Regulations | 2026 | New rules require special permits, water and emissions disclosures, and a 300-foot buffer from neighborhoods. (CRE Daily, Sept. 8, 2026) |
| Lewisville | Restriction | 2026 | Data centers barred from residential areas; new applications need a special-use permit and two public hearings. (CRE Daily, Sept. 8, 2026) |
Updates, newest first
- Oct. 13, 2026 Comanche Circle · Commissioners voted 3-1 to reject a settlement that would have shrunk the project to about 1,375 acres, then unanimously denied Sailfish's appeal on its on-site permits. (KERA (via Texas Public Radio), Oct. 13, 2026)
- Oct. 8, 2026 Taylor Technology Campus · The City Council approved the annexation agreement 5-0; a petition to restrict data centers was ruled ineligible under Texas law. (CBS Austin, Oct. 8, 2026)
- Oct. 8, 2026 Taylor: Ban petition (rejected) · City officials said a resident petition to restrict data centers could not go forward through the initiative process under Texas law. (CBS Austin, Oct. 8, 2026; San Antonio Express-News (via GovTech/TNS), July 17, 2026)
- Oct. 2, 2026 Taylor Technology Campus · The city announced a negotiated annexation deal setting rules for noise, water, setbacks and community benefits. (KUT 90.5, Oct. 2, 2026)
- Sept. 2, 2026 Stargate Abilene (Lancium Clean Campus) · An Abilene Chamber panel heard resident concerns about rents, power bills, water and the county's 20-year abatement. (KACU (via KTTZ), Sept. 4, 2026)
- Aug. 19, 2026 Pacifico Cedar Creek data center and power campus · The developers withdrew both county abatement applications. (Elgin Courier, Aug. 25, 2026)
- Aug. 12, 2026 Fort Worth: Moratorium (proposed) · The council voted unanimously to start the process for a 90-day moratorium on new data center construction, created a data center committee, and required proof of state grid approval before applications; the pause would not take effect until 2027. (FOX 4 Dallas-Fort Worth, Aug. 11, 2026; Fort Worth Report (via Green Source Texas), July 9, 2026)
- Aug. 11, 2026 Amazon Pecos County data center campus · Amazon confirmed it will pay to power its planned Pecos County campus with new on-site generation; state regulators had already approved the plant's air emissions. (E&E News by POLITICO, Aug. 11, 2026)
- Aug. 11, 2026 Kilby (Chevron power for Microsoft data center) · E&E News placed Chevron's gas facility for Microsoft in Reeves County. (E&E News by POLITICO, Aug. 11, 2026)
- Aug. 4, 2026 Brownsville: Moratorium (proposed) · A commission workshop weighed a 90-day pause, extendable to 180 days, plus rules limiting data centers to heavy industrial zones with special permits and closed-loop cooling. (City of Brownsville, Aug. 4, 2026; KRGV, Aug. 2026)
- Aug. 2026 Athens: Ban (disputed) · CRE Daily reported a 3-2 vote to ban data centers; KETK reported the city instead halted drafting local rules until state guidance arrives. (CRE Daily, Sept. 8, 2026; KETK, Aug. 7, 2026)
- Aug. 2026 Laredo: Moratorium (dropped) · City weighed and then dropped a moratorium. (CRE Daily, Sept. 8, 2026)
- July 31, 2026 Google Midlothian and Red Oak campuses · An Ellis County commissioner told a Red Oak residents' meeting the county intends to shrink future data center abatements. (Waxahachie Sun, Aug. 2026)
- July 17, 2026 Vantage Frontier · The Shackelford County judge invited residents to talk with him informally about reinvestment zones. (KTXS, July 17, 2026)
- July 16, 2026 Lockhart: Regulations (in drafting) · City leaders asked staff for very strict data center standards rather than an outright ban, citing litigation risk. (San Antonio Express-News (via GovTech/TNS), July 17, 2026)
- July 15, 2026 Project Aquila (RCM Hill LLC) · KWTX reported RCM Hill dismissed the case; minutes show the county agreed to pay $100,000 in legal fees. (KWTX, July 15, 2026)
- July 9, 2026 Black Mountain data center campus · The Fort Worth Report said Black Mountain asked to delay its rezoning requests until December. (Fort Worth Report (via Green Source Texas), July 9, 2026)
- June 24, 2026 Pacifico Cedar Creek data center and power campus · Pacifico filed a JETI application with the Texas Comptroller. (Community Impact, July 15, 2026)
- June 23, 2026 Hays County: Pause on discretionary approvals · After tabling a moratorium in February, commissioners unanimously suspended discretionary approvals such as abatements for data centers and other water-heavy projects through year-end and created a water review board. (KUT 90.5, June 23, 2026; Spectrum News, May 19, 2026)
- June 22, 2026 Kilby (Chevron power for Microsoft data center) · Chevron and Microsoft signed a 20-year power purchase agreement for the Kilby project. (World Oil, June 22, 2026)
- June 16, 2026 San Marcos: Ban · The council voted 4-3 to bar data centers from every zoning district; an April 21 version failed 3-4. (Community Impact, June 17, 2026)
- June 9, 2026 Meta El Paso data center · El Paso City Council votes 5-3 against starting to end the Meta agreement. (KTSM 9 News, June 9, 2026)
- June 9, 2026 Comanche Circle · Commissioners voted 3-1 to approve the concept plan without conditions, moving it to site development review. (KERA (via KWBU), June 10, 2026)
- June 4, 2026 Project Aquila (RCM Hill LLC) · The county unanimously rescinded the moratorium and adopted a data center checklist. (The Texas Tribune, June 5, 2026)
- June 2, 2026 Fort Spunky data center · The Texas Tribune reported that the county revoked the concept plan 3-2 and that Pacifico had sued, seeking at least $250,000. (The Texas Tribune, June 2, 2026)
- June 2, 2026 Project Red and Project Yellow · The Texas Tribune reported the county had delayed votes twice and required the developers to meet new rules first; a suit accused the county of illegal delay. (The Texas Tribune, June 2, 2026)
- May 27, 2026 Project Aquila (RCM Hill LLC) · RCM Hill sued Hill County in federal court, saying the moratorium made its purchase rights to more than 800 acres worthless. (KWTX, July 15, 2026; K&L Gates, June 10, 2026)
- May 2026 Hill County: Moratorium (rescinded) · Commissioners voted 3-2 for a one-year pause on new data center construction in unincorporated areas, then voted unanimously on June 4 to rescind it after a $100 million federal lawsuit and to adopt a data center checklist. (KWTX, July 15, 2026; The Texas Tribune, June 5, 2026; K&L Gates, June 10, 2026)
- May 2026 Somervell County: Resolution · Commissioners unanimously passed a resolution opposing data center construction until the Legislature acts, after an earlier moratorium motion failed. (Spectrum News, May 19, 2026)
- April 17, 2026 Stargate Abilene (Lancium Clean Campus) · Epoch AI reported roughly four of eight buildings operating and projected completion in the fourth quarter of 2026. (Epoch AI, April 17, 2026)
- April 17, 2026 Vantage Frontier · Epoch AI reported the first building under roof and projected completion in late 2028. (Epoch AI, April 17, 2026)
- April 17, 2026 Stargate Milam County (SB Energy) · Epoch AI reported construction under way since the third quarter of 2025, with completion projected for late 2028. (Epoch AI, April 17, 2026)
- April 8, 2026 Black Mountain data center campus · Fort Worth's zoning commission unanimously recommended a planned development amendment for the campus. (Fort Worth Star-Telegram (via GovTech/TNS), April 9, 2026)
- March 27, 2026 Crusoe Abilene campus for Microsoft · Crusoe announced the two-building, 900 MW campus beside its existing Abilene site. (Crusoe (company announcement), March 27, 2026)
- March 26, 2026 EdgeConneX second Bastrop County campus · An EdgeConneX executive announced the second campus at a business panel in Bastrop. (Community Impact, March 31, 2026)
- March 10, 2026 Fort Spunky data center · Hood County commissioners reject the Fort Spunky concept plan, 3-2. (Texas Scorecard, March 10, 2026)
- March 10, 2026 Old Ocean Data Center · Brazoria County commissioners unanimously denied four 100% abatements after residents cited noise, water and power. (Bisnow Houston, March 11, 2026)
- Feb. 25, 2026 Fermi America Project Matador (HyperGrid campus) · TCEQ gave final approval to the project's air permit, letting vertical power construction proceed. (KFDA/KCBD NewsChannel 10, Feb. 25, 2026)
- Feb. 17, 2026 Highlander SM One data center · The San Marcos council denied a Preferred Scenario Map amendment and rezoning for the project. (Community Impact, June 17, 2026)
- Feb. 10, 2026 Hood County: Moratorium (failed) · A six-month pause on new industrial development including data centers failed 3-2; a second try failed by the same margin on Feb. 24 after a state senator questioned county authority. (The Texas Tribune, Feb. 10, 2026; CBS News Texas, Feb. 24, 2026)
How this page is built
Each project’s status is the latest public record found in a statewide review of local news, government records, utility filings and trackers; every update links to its source, and the reporting that found it is credited. The review covers campuses of 50 MW or more, or 100 acres or more when power is not reported, plus operating hyperscale campuses for context. Map positions are approximate. A county with no project listed was not found in this review; that is not proof none exists. Political money around these projects has not yet been traced in this state.
Have a filing, agenda or record? Send it to tips@signaldata.org.
Sources
- KERA (via Texas Public Radio), Emmanuel Rivas Valenzuela, “Hood County rejects Comanche Circle data center settlement, permit appeal,” Oct. 13, 2026
- CBS Austin, Erin Slaughter, “Taylor City Council greenlights 664-Acre Data Center Project,” Oct. 8, 2026
- KUT 90.5, Kailey Hunt, “Taylor has struck a deal on a nearby data center, allowing it to annex the site and set conditions,” Oct. 2, 2026
- CRE Daily, Nina Dale, “Texas Data Center Moratoriums Spread as Backlash Grows,” Sept. 8, 2026
- KACU (via KTTZ), Leslie Carrigan, “Panel tackles persistent concerns around Abilene's AI boom,” Sept. 4, 2026
- Elgin Courier, Dylan Roddy, “Developers withdraw tax break requests,” Aug. 25, 2026
- FOX 4 Dallas-Fort Worth, Amelia Jones, “Fort Worth set to vote on data center moratorium,” Aug. 11, 2026
- E&E News by POLITICO, Shelby Webb, “Amazon to run West Texas data center on massive gas plant,” Aug. 11, 2026
- KETK, Daisy Escatel, “City of Athens pauses work on local infrastructure regulations amid state's data center audit,” Aug. 7, 2026
- POWER Magazine, Sonal C. Patel, “Abbott orders full audit of Texas data center interconnection queue, threatens to deny grid access,” Aug. 4, 2026
- City of Brownsville, “City Commission workshop on proposed data center regulations and moratorium (news release),” Aug. 4, 2026
- Waxahachie Sun, Corey Rogan, “County officials speak at community data center meeting,” Aug. 2026
- KRGV, “Brownsville puts data center projects on hold for 90 days,” Aug. 2026
- Texas Public Radio / The Texas Newsroom, Blaise Gainey, “Texas lawmakers question whether multibillion-dollar data center tax break still benefits the state,” July 28, 2026
- Public Citizen (testimony to Texas Senate Finance Committee), Adrian Shelley, “Data Center Investment and State Fiscal Effects - testimony by Public Citizen,” July 27, 2026
- San Antonio Express-News (via GovTech/TNS), Karoline Leonard, “Small Texas town joins group considering data center ban,” July 17, 2026
- KTXS, Kayla Hamlett, “Shackleford County judge encourages open dialogue on reinvestment zones,” July 17, 2026
- KWTX, KWTX News, “Hill County dropped its data center ban after a $100 million lawsuit. Now the developer has dismissed the case.,” July 15, 2026
- Community Impact, Amanda Cutshall, “New $2.2B Cedar Creek data center project, abatements under review,” July 15, 2026
- Fort Worth Report (via Green Source Texas), Cecilia Lenzen; Nicole Lopez, “Majority of Fort Worth council members call for data center moratorium,” July 9, 2026
- KUT 90.5, Leigh Walden, “Hays County creates water review board, pauses discretionary approvals for data centers,” June 23, 2026
- World Oil, “Chevron signs 20-year Microsoft power deal for West Texas AI project,” June 22, 2026
- Community Impact, Michael Milliorn, “San Marcos council votes to prohibit data centers in all zoning districts,” June 17, 2026
- K&L Gates, Thomas G. Allen; Austin D. McCarty; Tad J. Macfarlan; Robert M. Smith, “Facing a Federal Lawsuit, Hill County Repeals Blanket Pause on Data Center Construction, Adopting New Approval Procedures Instead,” June 10, 2026
- KERA (via KWBU), Emmanuel Rivas Valenzuela, “Hood County approves Comanche Circle data center without conditions after contentious meeting,” June 10, 2026
- KTSM 9 News, Aaron Montes, “City Council votes against ending Meta pact for data center project,” June 9, 2026
- The Texas Tribune, Taylor Goldenstein, “Texas county rescinds data center moratorium after lawsuit,” June 5, 2026
- The Texas Tribune, Alejandra Martinez; Shelby Tauber; Apurva Mahajan; Alex Ford, “The 8 data centers that could transform one Texas county,” June 2, 2026
- Spectrum News, Geraldine Torrellas, “A look at the Texas counties pushing back against data centers,” May 19, 2026
- Epoch AI, Elliot Stewart; Ben Cottier, “OpenAI Stargate: where the US sites stand,” April 17, 2026
- Fort Worth Star-Telegram (via GovTech/TNS), Emily Holshouser, “$10B Fort Worth data center gets win from city amid pushback,” April 9, 2026
- Foley & Lardner, Eric Blumrosen; David G. Cabrales, “Public Utility Commission of Texas issues proposed rules for large load interconnection,” March 31, 2026
- Community Impact, Joel Valley, “EdgeConneX plans second data center campus in Bastrop County,” March 31, 2026
- Crusoe (company announcement), “Crusoe announces new 900 MW AI factory campus in Abilene, Texas to support Microsoft AI infrastructure,” March 27, 2026
- Bisnow Houston, Maddy McCarty, “Houston-area county rejects tax abatement for $3.5B data center development,” March 11, 2026
- Texas Scorecard, Robert Montoya, “Hood County Rejects Data Center Concept Plan,” March 10, 2026
- KFDA/KCBD NewsChannel 10, Paige Stockton, “Fermi America receives nation's second-largest Clean Air permit for Project Matador,” Feb. 25, 2026
- CBS News Texas, CBS Texas Staff, “Hood County commissioners reject data center moratorium again in 3-2 vote; residents call for resignations,” Feb. 24, 2026
- The Texas Tribune, Alejandra Martinez, “A Texas county rejects moratorium on data center development,” Feb. 10, 2026
- KXXV 25 News, Kenny Graves, “Paving the way for progress: Milam County approves tax abatement for new data center,” Feb. 10, 2026
- KFDA (via Fox34), Alissa Spangler, “Project Matador construction paused as Fermi America awaits clean air permit,” Feb. 6, 2026
- The Texas Tribune (from Inside Climate News), Martha Pskowski, “El Paso's plan to build a natural gas power plant for Meta's data center kicks up opposition,” Jan. 26, 2026
- Riot Platforms (company announcement), “Riot announces fee simple acquisition of land and first data center lease with AMD at the Rockdale site,” Jan. 16, 2026
- SB Energy (company announcement), Charlie Adams, “SB Energy to Build Stargate Data Center in Texas,” Jan. 12, 2026
- Data Center Dynamics, Zachary Skidmore, “SoftBank's SB Energy to build and operate OpenAI's 1.2GW Stargate data center in Milam County, Texas,” Jan. 12, 2026
- Haskell County Commissioners Court, “Amended Notice of Consideration of Possible Approval of a Proposed Reinvestment Zone and Tax Abatement Agreement (Haskell County Ranger RZ 2026),” Jan. 9, 2026
- Data Center Dynamics, Georgia Butler, “Google commits $40bn to expand cloud and AI infrastructure in Texas through 2027,” Nov. 17, 2025
- KFDA NewsChannel 10, Canion Cavazos, “Armstrong County AI data center project scaled back from original plan,” Oct. 17, 2025
- Elgin Courier, Niko Demetriou, “$4B data center underway,” Sept. 24, 2025
- Data Center Dynamics, Dan Swinhoe, “Vantage plots 1.4GW data center campus in Texas,” Aug. 19, 2025
- Data Center Dynamics, Zachary Skidmore, “CyrusOne signs 190MW deal with Calpine Energy to power data center in Bosque County, Texas,” July 31, 2025
- Business Insider (via AOL), Ellen Thomas, “Oracle got big tax breaks in Texas for Stargate. Now it's going back for more.,” July 17, 2025
- KTAB/KRBC (BigCountryHomepage.com), Shelly Womack, “Tenant challenges Lancium AI facility property value,” July 9, 2025
- KTAB/KRBC (BigCountryHomepage.com), Shelly Womack, “Crusoe's next phase in Abilene: More jobs, more power, completion in 2026,” March 24, 2025
- Community Impact, Amanda Cutshall, “Bastrop County grants tax abatement incentive to multibillion-dollar data center,” Dec. 12, 2024
- Community Impact, Hannah Norton, “Texas launches new business tax break program to replace Chapter 313,” Feb. 23, 2024