Data centers · ArizonaFirst pass Oct. 17, 2026 · not yet complete

18 data center projects in Arizona.

Reviewed Project Blue and Beale's Marana campus, Pinal (La Osa), West Valley gigawatt campuses (Tract, Hassayampa Ranch), Page, Chandler's 2025 denial, local ordinances, the 2026 tax-break pause and ACC power contracts. Notably absent or unverified: Google Mesa, Microsoft El Mirage, Vantage, QTS and Tonopah/Copia proposals; SRP and APS large-load tariff dockets; and the outcome of AG Mayes's Project Blue appeal and her August 2026 call for a statewide pause.

Approved, building or operating13Projects whose latest record is an approval, construction or operation.
Proposed or paused2Proposals, marketed sites, inquiries, and projects paused or stalled.
Withdrawn or denied3They stay on the map with their record.
Reported power, active projects5,150 MWSum of reported capacities for projects not withdrawn or denied; many projects report none, and figures are developers’ claims.

Dot positions are approximate, from the reported address or area. “None found” means our statewide review of news, trackers and county records found nothing; it is not proof none exists.

Every project

All 18 Arizona projects on record
Buckeye Tech Corridor (Tract)MaricopaTract1,800ApprovedAug. 6, 202450 MW+
Hassayampa RanchMaricopaArizona Land Consulting (CEO Anita Verma-Lallian)1,000ApprovedDec. 10, 202550 MW+
La Osa Energy CenterPinalVermaland1,000DeniedAug. 26, 202650 MW+
Page data center site (Huntley LLC)CoconinoHuntley LLC1,000Site zoned or marketedOct. 22, 202550 MW+
Beale Marana data center campus (Luckett Road)PimaBeale Infrastructure750ApprovedJan. 6, 202650 MW+
Project BluePimaBeale Infrastructure (backed by Blue Owl); Humphrey's Peak Power LLC600Under constructionApril 24, 202650 MW+
Apple Mesa data centerMaricopaApple—OperatingOct. 2026Under 50 MW
CyrusOne Chandler campusMaricopaCyrusOne—OperatingOct. 2026Under 50 MW
EdgeConneX Mesa campusMaricopaEdgeConneX—OperatingOct. 2026Under 50 MW
EdgeCore Mesa campusMaricopaEdgeCore—OperatingOct. 2026Under 50 MW
Energy Generation and Technology CampusPinal——Under constructionDec. 17, 202550 MW+
Meta Mesa data centerMaricopaMeta—OperatingOct. 2026Under 50 MW
Microsoft West Valley campus (Goodyear)MaricopaMicrosoft—OperatingOct. 2026Under 50 MW
NTT Mesa campusMaricopaNTT—OperatingOct. 2026Under 50 MW
Price Road Innovation CampusMaricopaActive Infrastructure (New York)—DeniedDec. 11, 2025Under 50 MW
Project Range (Tract)MaricopaTract—Withdrawn2024Under 50 MW
Ranch House data center rezoningPimaThe Planning Center (applicant)—ProposedJune 26, 2026Under 50 MW
Stream Data Centers Phoenix campus (Goodyear)MaricopaStream Data Centers—OperatingOct. 2026Under 50 MW

Select a heading to sort. Operating hyperscale campuses are included for context.

Operating
Built and serving customers.
Under construction
Building permits issued or construction reported under way.
Approved
A government body has approved land use, zoning or a development agreement for data center use. Other permits may still be pending.
Proposed
An application, announcement or public proposal exists; no approval yet.
Site zoned or marketed
Land zoned or marketed for possible data center use; no project filed.
Paused by moratorium
A local moratorium or ban blocks new applications or approvals.
Stalled
No formal application, or blocked by a missing permit or utility capacity.
Inquiry only
A developer asked local officials about a site; nothing was filed.
Withdrawn
The developer withdrew its application or proposal.
Denied
A government body voted it down.

State law and rates

  • The 2026 state budget, signed by Gov. Katie Hobbs in June 2026, pauses new data center sales and use tax exemptions for three years. The program, created in 2013, costs about $38 million a year; the bill number and how existing certificates are treated were not confirmed. (Bloomberg Law, June 15, 2026)
  • Utility large-load contracts: the ACC approved TEP's 10-year energy supply agreement for Project Blue (Docket E-01933A-25-0187, Dec. 3, 2025), with minimum bills and developer-paid dedicated infrastructure. (Arizona Corporation Commission, Dec. 5, 2025)
  • APS: on Oct. 9, 2026, Attorney General Kris Mayes asked the ACC to investigate an analyst's claim that large users underpaid about $600 million; the ACC disagreed and pointed to the pending APS rate case (docket not confirmed). (KJZZ, Oct. 10, 2026)

Local moratoriums and bans

Local moratoriums, bans and proposals
MaranaData center ordinance and proposed amendmentsSept. 30, 2026A 2024 town ordinance requires data center applicants to estimate annual water use and name the source, and bars town potable water for cooling. Amendments heard Sept. 30, 2026 would cap residential-area noise at 55 dB, require testing before and after construction, and require decommissioning plans with money set aside up front. (AZ Luminaria, Jan. 8, 2026; AZBEX, Nov. 7, 2025; KOLD 13 News, Sept. 30, 2026)
TucsonZoning regulations (large-scale data centers)Aug. 5, 2026The council created large-scale data centers as a defined use requiring a half-mile buffer from homes and schools, a 1,000-foot buffer from commercial zones, noise studies, batteries before generators, proof of power and water, and public hearings. Staff were told to keep studying a ban; the city attorney warned that a moratorium carries risk under state law. (AZ Luminaria, Aug. 6, 2026)
Maricopa CountyZoning updateDec. 10, 2025Supervisors limited data centers to the IND-2 and IND-3 industrial districts; other land requires a rezoning. (Bisnow, Dec. 17, 2025)
ChandlerZoning restrictions (Ordinance 5033)Dec. 5, 2022Before the tracker's 2024 window, but still the governing rule: data centers are allowed only in Planned Area Development districts, with neighbor notice, sound studies for five years after opening and limits on generator testing. (City of Chandler, Dec. 8, 2022; E&E News by POLITICO, Dec. 12, 2025)

Updates, newest first

  1. Oct. 15, 2026 Microsoft West Valley campus (Goodyear) · ABC15 names Microsoft among the operators in the Goodyear Airpark area data center cluster. (ABC15 Arizona, Oct. 15, 2026)
  2. Oct. 15, 2026 Stream Data Centers Phoenix campus (Goodyear) · ABC15 names Stream Data Centers among the operators in the Goodyear Airpark area data center cluster. (ABC15 Arizona, Oct. 15, 2026)
  3. Oct. 15, 2026 Meta Mesa data center · ABC15 names Meta among the operators in the far East Valley, Mesa data center cluster. (ABC15 Arizona, Oct. 15, 2026)
  4. Oct. 15, 2026 Apple Mesa data center · ABC15 names Apple among the operators in the far East Valley, Mesa data center cluster. (ABC15 Arizona, Oct. 15, 2026)
  5. Oct. 15, 2026 NTT Mesa campus · ABC15 names NTT among the operators in the far East Valley, Mesa data center cluster. (ABC15 Arizona, Oct. 15, 2026)
  6. Oct. 15, 2026 EdgeConneX Mesa campus · ABC15 names EdgeConneX among the operators in the far East Valley, Mesa data center cluster. (ABC15 Arizona, Oct. 15, 2026)
  7. Oct. 15, 2026 CyrusOne Chandler campus · ABC15 names CyrusOne among the operators in the south Chandler data center cluster. (ABC15 Arizona, Oct. 15, 2026)
  8. Sept. 30, 2026 Beale Marana data center campus (Luckett Road) · Marana held a hearing on ordinance amendments for noise and decommissioning; Beale said it would not attend. (KOLD 13 News, Sept. 30, 2026)
  9. Sept. 30, 2026 Marana: Data center ordinance and proposed amendments · A 2024 town ordinance requires data center applicants to estimate annual water use and name the source, and bars town potable water for cooling. Amendments heard Sept. 30, 2026 would cap residential-area noise at 55 dB, require testing before and after construction, and require decommissioning plans with money set aside up front. (AZ Luminaria, Jan. 8, 2026; AZBEX, Nov. 7, 2025; KOLD 13 News, Sept. 30, 2026)
  10. Aug. 26, 2026 La Osa Energy Center · Pinal County supervisors voted 4-1 to reject the rezoning and development plans. (KJZZ, Aug. 26, 2026)
  11. Aug. 25, 2026 La Osa Energy Center · Vermaland submitted 22 self-imposed conditions, including the 11-building cap, the water cap and paying all energy costs. (KJZZ, Aug. 25, 2026)
  12. Aug. 5, 2026 Tucson: Zoning regulations (large-scale data centers) · The council created large-scale data centers as a defined use requiring a half-mile buffer from homes and schools, a 1,000-foot buffer from commercial zones, noise studies, batteries before generators, proof of power and water, and public hearings. Staff were told to keep studying a ban; the city attorney warned that a moratorium carries risk under state law. (AZ Luminaria, Aug. 6, 2026)
  13. June 26, 2026 Ranch House data center rezoning · The town manager confirmed a second data center rezoning application, filed in November, was in review with no approvals. (KOLD 13 News, June 26, 2026)
  14. May 28, 2026 La Osa Energy Center · At a hearing with about 60 opposing comments, Vermaland offered to cut the project 80%; supervisors continued the case to Aug. 26. (KJZZ, May 28, 2026)
  15. May 21, 2026 Page data center site (Huntley LLC) · Hoodline reported that the city clerk rejected the referendum challenge over paperwork errors. (Hoodline, May 21, 2026)
  16. April 24, 2026 Project Blue · Construction began on what is planned as a 10-building campus targeted to open by 2028; the No Desert Data Center Coalition protested at the site. (KOLD 13 News, April 24, 2026)
  17. Jan. 8, 2026 Project Blue · Attorney General Kris Mayes, the City of Tucson and two residents asked the ACC to rehear the TEP agreement. (AZ Luminaria, Jan. 8, 2026)
  18. Jan. 6, 2026 Beale Marana data center campus (Luckett Road) · The Town Council approved the rezoning unanimously among members voting; Council member Herb Kai, whose family trust owns one parcel, was absent. (AZ Luminaria, Jan. 8, 2026; KOLD 13 News, June 26, 2026)
  19. Dec. 24, 2025 Project Blue · The county land sale closed. (AZ Luminaria, Jan. 8, 2026)
  20. Dec. 17, 2025 Energy Generation and Technology Campus · Bisnow listed the $10 billion, 500-acre campus as under construction. (Bisnow, Dec. 17, 2025)
  21. Dec. 17, 2025 EdgeCore Mesa campus · Bisnow cites EdgeCore's 3.1 million-sq-ft Mesa campus as an existing facility. (Bisnow, Dec. 17, 2025)
  22. Dec. 11, 2025 Price Road Innovation Campus · The Chandler City Council unanimously rejected the rezoning. (E&E News by POLITICO, Dec. 12, 2025; ABC15 Arizona, Dec. 12, 2025)
  23. Dec. 10, 2025 Beale Marana data center campus (Luckett Road) · The Marana planning commission recommended the rezoning 6-0. (AZ Luminaria, Jan. 8, 2026)
  24. Dec. 10, 2025 Hassayampa Ranch · The Maricopa County Board of Supervisors unanimously approved the rezoning. (Phoenix Business Journal (via Orion Property), Dec. 15, 2025; Connect CRE, Dec. 15, 2025; Bisnow, Dec. 17, 2025)
  25. Dec. 10, 2025 Maricopa County: Zoning update · Supervisors limited data centers to the IND-2 and IND-3 industrial districts; other land requires a rezoning. (Bisnow, Dec. 17, 2025)
  26. Dec. 3, 2025 Project Blue · The Arizona Corporation Commission approved TEP's 10-year energy supply agreement with Humphrey's Peak Power LLC 4-1, with minimum bills, an 18-month load ramp, developer-paid dedicated infrastructure and exit fees; Commissioner Rachel Walden dissented. (Arizona Corporation Commission, Dec. 5, 2025)
  27. Nov. 18, 2025 Page data center site (Huntley LLC) · A resident began gathering signatures to send the sale to voters. (KNAU Arizona Public Radio, Nov. 18, 2025)
  28. Nov. 7, 2025 Beale Marana data center campus (Luckett Road) · AZBEX reported Beale's applications under Marana's data center ordinance for two roughly 300-acre sites. (AZBEX, Nov. 7, 2025)
  29. Oct. 22, 2025 Page data center site (Huntley LLC) · Page City Council passed Ordinance 744-25 approving the land sale agreement. (Hoodline, May 21, 2026)
  30. Oct. 2025 Price Road Innovation Campus · Former Sen. Kyrsten Sinema, co-chair of the AI Infrastructure Coalition, spoke for the project at a planning and zoning hearing; the zoning board approved it against staff's recommendation. (E&E News by POLITICO, Dec. 12, 2025; ABC15 Arizona, Dec. 12, 2025)
  31. Sept. 19, 2025 Project Blue · Beale said it would revive the project on the same county land with a new TEP power deal and closed-loop cooling. (KJZZ (Fronteras Desk), Sept. 19, 2025)
  32. Aug. 6, 2025 Project Blue · Tucson's mayor and council unanimously moved to end city participation, dropping the annexation and water-service agreement. (Construction Reporter, Aug. 7, 2025; KOLD 13 News, April 24, 2026)
  33. July 22, 2025 Project Blue · County memos reported by AZ Luminaria identify Amazon Web Services as the end user; the county had been under a nondisclosure agreement since at least June 2024. (Data Center Dynamics, July 22, 2025)
  34. June 2025 Project Blue · Pima County supervisors voted 3-2 to rezone the parcel to light industrial and approved selling the county land for the project. (Data Center Dynamics, July 22, 2025; KJZZ (Fronteras Desk), Sept. 19, 2025)
  35. Aug. 29, 2024 Buckeye Tech Corridor (Tract) · Tract announced the 1.8 GW park after buying the 2,069-acre site for a reported $136 million-plus. (Data Center Dynamics, Aug. 29, 2024)
  36. Aug. 6, 2024 Buckeye Tech Corridor (Tract) · Buckeye's council unanimously approved the development agreement and plan amendment. (KTAR / Phoenix Business Journal, Aug. 12, 2024)
  37. 2024 Project Range (Tract) · Tract withdrew Project Range, filed in 2023, after local opposition. (Data Center Dynamics, Aug. 29, 2024)
  38. Dec. 5, 2022 Chandler: Zoning restrictions (Ordinance 5033) · Before the tracker's 2024 window, but still the governing rule: data centers are allowed only in Planned Area Development districts, with neighbor notice, sound studies for five years after opening and limits on generator testing. (City of Chandler, Dec. 8, 2022; E&E News by POLITICO, Dec. 12, 2025)

How this page is built

Each project’s status is the latest public record found in a statewide review of local news, government records, utility filings and trackers; every update links to its source, and the reporting that found it is credited. The review covers campuses of 50 MW or more, or 100 acres or more when power is not reported, plus operating hyperscale campuses for context. Map positions are approximate. A county with no project listed was not found in this review; that is not proof none exists. Political money around these projects has not yet been traced in this state.

Have a filing, agenda or record? Send it to tips@signaldata.org.