Data center project · Pinal County, Arizona

La Osa Energy Center

Denied · What would have been Arizona's largest data center plan, cut from 59 buildings to 11 and then rejected by Pinal County supervisors. Also known as: La Osa data center and energy campus.

← Arizona data centers
Apache CountyCochise CountyCoconino CountyGila CountyGraham CountyGreenlee CountyLa Paz CountyMaricopa CountyMohave CountyNavajo CountyPima CountyPinal CountySanta Cruz CountyYavapai CountyYuma CountyLa Osa Energy Center · Denied · 1,000 MW
Status
Denied · as of Aug. 26, 2026
Denied by
Pinal County Board of Supervisors
Rezoning and development plans, Aug. 26, 2026, vote 4-1
The dissenting supervisor was not named in the source read. (KJZZ, Aug. 26, 2026)
Location
About 12 miles outside Eloy · Pinal County
Power
1,000 MW
Reduced plan capped at 1 GW with a 500 MW on-site gas plant; the earlier comprehensive plan (59 buildings) was 3 GW.
Land
3,300 acres
Developer and team
Vermaland
End user
None disclosed.
Utility
Central Arizona Irrigation and Drainage District planned to serve it; on-site 500 MW gas plant and battery storage.
Water
Developer-proposed cap of 600 acre-feet a year of fresh water, with possible effluent offsets; residents cited dry wells, overdraft and subsidence.
Evidence
News reports; primary records not yet obtained
Size class
50 MW or more (tracker scope)
Map position approximate, from the reported address or area. Updated Oct. 17, 2026.

Updates, newest first

  1. Aug. 26, 2026 Pinal County supervisors voted 4-1 to reject the rezoning and development plans. (KJZZ, Aug. 26, 2026)
  2. Aug. 25, 2026 Vermaland submitted 22 self-imposed conditions, including the 11-building cap, the water cap and paying all energy costs. (KJZZ, Aug. 25, 2026)
  3. May 28, 2026 At a hearing with about 60 opposing comments, Vermaland offered to cut the project 80%; supervisors continued the case to Aug. 26. (KJZZ, May 28, 2026)

Conflicts and open questions

  • The dissenting supervisor was not named in the source read.
  • Pinal County's zoning code has no data-center-specific standards (KJZZ).

Have records about this project? Send them to tips@signaldata.org.