Data center project · Pima County, Arizona
Project Blue
Under construction · Beale Infrastructure's 290-acre hyperscale campus southeast of Tucson, tied to AWS in county memos, proceeding on county land after Tucson refused to annex it. Also known as: Southeast Employment and Logistics Center, Humphrey's Peak Power LLC (TEP contract party).
- Status
- Under construction · as of April 24, 2026
- Approved by
- Pima County Board of Supervisors
Rezoning of the county parcel to light industrial and sale of the county land for the project, June 2025, vote 3-2
Exact meeting date not given in the sources; the dissenting supervisors were not named in the sources read. The land sale closed on Dec. 24, 2025. (Data Center Dynamics, July 22, 2025; KJZZ (Fronteras Desk), Sept. 19, 2025; AZ Luminaria, Jan. 8, 2026) - Approved by
- Arizona Corporation Commission
TEP 10-year energy supply agreement with Humphrey's Peak Power LLC (Docket E-01933A-25-0187), Dec. 3, 2025, vote 4-1
Commissioner Rachel Walden dissented, per the ACC release. A rehearing request by the Attorney General, the City of Tucson and two residents followed. (Arizona Corporation Commission, Dec. 5, 2025; AZ Luminaria, Jan. 8, 2026) - Location
- Unincorporated Pima County, just north of the Pima County Fairgrounds, southeast of Tucson · Pima County
- Status note
- KOLD reported site construction under way on April 24, 2026, with several permits still under review; legal challenges to the TEP power contract continued.
- Power
- 600 MW
No figure in a public record found. DCD cites reports of up to 600 MW across 10 buildings (2 million sq ft) and up to 700 MW at full build-out including a possible second site; Beale has said phase one fits within TEP's existing capacity. - Floor area
- 2,000,000 sq ft
- Land
- 290 acres
- Investment
- About $3.6 billion (reported, Construction Reporter)
- Developer and team
- Beale Infrastructure (backed by Blue Owl); Humphrey's Peak Power LLC
- End user
- Amazon Web Services, per Pima County memos obtained by AZ Luminaria (DCD); Amazon declined to comment.
- Utility
- Tucson Electric Power (10-year energy supply agreement, ACC Docket E-01933A-25-0187)
- Water
- Original plan relied on Tucson Water potable water, then reclaimed water via a new line; after Tucson declined annexation, Beale moved to a closed-loop, electricity-based cooling design.
- Incentives
- No state or local incentive amount found. Beale projects about $152 million in tax revenue over 10 years, $58.5 million to Pima County (KJZZ).
- Evidence
- Primary public records
- Size class
- 50 MW or more (tracker scope)
Updates, newest first
- April 24, 2026 Construction began on what is planned as a 10-building campus targeted to open by 2028; the No Desert Data Center Coalition protested at the site. (KOLD 13 News, April 24, 2026)
- Jan. 8, 2026 Attorney General Kris Mayes, the City of Tucson and two residents asked the ACC to rehear the TEP agreement. (AZ Luminaria, Jan. 8, 2026)
- Dec. 24, 2025 The county land sale closed. (AZ Luminaria, Jan. 8, 2026)
- Dec. 3, 2025 The Arizona Corporation Commission approved TEP's 10-year energy supply agreement with Humphrey's Peak Power LLC 4-1, with minimum bills, an 18-month load ramp, developer-paid dedicated infrastructure and exit fees; Commissioner Rachel Walden dissented. (Arizona Corporation Commission, Dec. 5, 2025)
- Sept. 19, 2025 Beale said it would revive the project on the same county land with a new TEP power deal and closed-loop cooling. (KJZZ (Fronteras Desk), Sept. 19, 2025)
- Aug. 6, 2025 Tucson's mayor and council unanimously moved to end city participation, dropping the annexation and water-service agreement. (Construction Reporter, Aug. 7, 2025; KOLD 13 News, April 24, 2026)
- July 22, 2025 County memos reported by AZ Luminaria identify Amazon Web Services as the end user; the county had been under a nondisclosure agreement since at least June 2024. (Data Center Dynamics, July 22, 2025)
- June 2025 Pima County supervisors voted 3-2 to rezone the parcel to light industrial and approved selling the county land for the project. (Data Center Dynamics, July 22, 2025; KJZZ (Fronteras Desk), Sept. 19, 2025)
Conflicts and open questions
- Land sale proceeds differ: KOLD says almost $21 million; AZ Luminaria, citing county documents, says more than $27 million.
- Search results indicate the ACC kept its decision, Mayes appealed, and a Maricopa County judge is weighing a final rehearing bid (KJZZ, Sept. 24, 2026), but those pages could not be opened in this pass (rate limit); verify before publishing.
- Megawatt figure is from secondary reporting only; the ACC release gives none.