Data center project · Maricopa County, Arizona
Price Road Innovation Campus
Denied · AI data center campus that Chandler's council turned down unanimously after more than 200 public comments against it.
- Status
- Denied · as of Dec. 11, 2025
- Denied by
- Chandler City Council
Rezoning for the data center campus, Dec. 11, 2025, vote Unanimous
The planning and zoning commission had approved it against staff's recommendation; the council's vote was the deciding action. (E&E News by POLITICO, Dec. 12, 2025; ABC15 Arizona, Dec. 12, 2025) - Location
- Chandler, Price Road corridor (10-acre site with a vacant office building) · Maricopa County
- Floor area
- 422,000 sq ft
- Land
- 10 acres
- Developer and team
- Active Infrastructure (New York)
- Water
- Applicant said it would use closed-loop cooling.
- Evidence
- News reports; primary records not yet obtained
- Size class
- Under 50 MW (outside main scope; kept for completeness)
Updates, newest first
- Dec. 11, 2025 The Chandler City Council unanimously rejected the rezoning. (E&E News by POLITICO, Dec. 12, 2025; ABC15 Arizona, Dec. 12, 2025)
- Oct. 2025 Former Sen. Kyrsten Sinema, co-chair of the AI Infrastructure Coalition, spoke for the project at a planning and zoning hearing; the zoning board approved it against staff's recommendation. (E&E News by POLITICO, Dec. 12, 2025; ABC15 Arizona, Dec. 12, 2025)
Conflicts and open questions
- Size differs: E&E reports 422,000 sq ft; Bisnow reports 433,000 sq ft.
- Megawatts not reported; may be under 50 MW.
- A KETK story dated Aug. 12, 2026, 'Chandler bans data centers in city limits,' appears to concern Chandler, Texas, and is not used here.