Data center project · Coweta County, Georgia

Project Sail

Approved · A nine-building, roughly 900 MW Prologis campus on about 832 forested acres near Newnan that the county rezoned after a moratorium and a zoning rewrite.

← Georgia data centers
Appling CountyAtkinson CountyBacon CountyBaker CountyBaldwin CountyBanks CountyBarrow CountyBartow CountyBen Hill CountyBerrien CountyBibb CountyBleckley CountyBrantley CountyBrooks CountyBryan CountyBulloch CountyBurke CountyButts CountyCalhoun CountyCamden CountyCandler CountyCarroll CountyCatoosa CountyCharlton CountyChatham CountyChattahoochee CountyChattooga CountyCherokee CountyClarke CountyClay CountyClayton CountyClinch CountyCobb CountyCoffee CountyColquitt CountyColumbia CountyCook CountyCoweta CountyCrawford CountyCrisp CountyDade CountyDawson CountyDecatur CountyDeKalb CountyDodge CountyDooly CountyDougherty CountyDouglas CountyEarly CountyEchols CountyEffingham CountyElbert CountyEmanuel CountyEvans CountyFannin CountyFayette CountyFloyd CountyForsyth CountyFranklin CountyFulton CountyGilmer CountyGlascock CountyGlynn CountyGordon CountyGrady CountyGreene CountyGwinnett CountyHabersham CountyHall CountyHancock CountyHaralson CountyHarris CountyHart CountyHeard CountyHenry CountyHouston CountyIrwin CountyJackson CountyJasper CountyJeff Davis CountyJefferson CountyJenkins CountyJohnson CountyJones CountyLamar CountyLanier CountyLaurens CountyLee CountyLiberty CountyLincoln CountyLong CountyLowndes CountyLumpkin CountyMacon CountyMadison CountyMarion CountyMcDuffie CountyMcIntosh CountyMeriwether CountyMiller CountyMitchell CountyMonroe CountyMontgomery CountyMorgan CountyMurray CountyMuscogee CountyNewton CountyOconee CountyOglethorpe CountyPaulding CountyPeach CountyPickens CountyPierce CountyPike CountyPolk CountyPulaski CountyPutnam CountyQuitman CountyRabun CountyRandolph CountyRichmond CountyRockdale CountySchley CountyScreven CountySeminole CountySpalding CountyStephens CountyStewart CountySumter CountyTalbot CountyTaliaferro CountyTattnall CountyTaylor CountyTelfair CountyTerrell CountyThomas CountyTift CountyToombs CountyTowns CountyTreutlen CountyTroup CountyTurner CountyTwiggs CountyUnion CountyUpson CountyWalker CountyWalton CountyWare CountyWarren CountyWashington CountyWayne CountyWebster CountyWheeler CountyWhite CountyWhitfield CountyWilcox CountyWilkes CountyWilkinson CountyWorth CountyProject Sail · Approved · 900 MW
Status
Approved · as of April 7, 2026
Approved by
Coweta County Board of Commissioners
Rezoning of about 832 acres, with a decommissioning and site-restoration condition, April 7, 2026, vote 3-2
The tracker's event names Smith, Fisher and Reidelbach as voting in favor. The same five commissioners are listed on the county site now. (The Atlanta Journal-Constitution, April 2026; DatacenterDynamics, April 10, 2026)
Location
Near Newnan, along U.S. 27 by Welcome Sargent Road and Wagers Mill Road · Coweta County
Status note
Rezoning approved 3-2; Prologis had not closed on the land as of mid-April 2026.
Power
900 MW
Floor area
4,340,000 sq ft
Land
832 acres
Investment
$17 billion (AJC)
Developer and team
Prologis; Atlas Development LLC
Utility
Georgia Power (site chosen in part for proximity to Plant Yates)
Evidence
News reports; primary records not yet obtained
Size class
50 MW or more (tracker scope)
Map position approximate, from the reported address or area. Updated Oct. 17, 2026.

Updates, newest first

  1. April 7, 2026 Commissioners voted 3-2 to rezone the land, with Smith, Fisher and Reidelbach in favor, and attached a decommissioning and site-restoration condition. (The Atlanta Journal-Constitution, April 2026; DatacenterDynamics, April 10, 2026)
  2. May 12, 2025 Coweta adopted a 180-day data center moratorium while it rewrote its zoning rules; the pause chiefly held up Project Sail. (The Atlanta Journal-Constitution, April 2026; SAVRN, Oct. 2026)
  3. Jan. 2025 Atlas Development LLC submitted the original planning proposal. (DatacenterDynamics, April 10, 2026)

Conflicts and open questions

  • The AJC puts the site at more than 800 acres; DCD gives 832 acres.
  • DCD gives two different distances from Atlanta (45 miles and 37.8 miles).
  • Search results in this pass showed headlines (The Citizen, May 11, 2026; Times-Herald; WSB-TV; CBS News Atlanta) saying residents filed suit or an appeal to reverse the rezoning. Those pages could not be opened because of rate limits, so the filing is not recorded as an event. Verify before publishing.
  • DeSmog has reported on the lobbyists working on the project (2025); not opened in this pass.

Have records about this project? Send them to tips@signaldata.org.