Data center project · Licking County, Ohio
Microsoft Heath data center site
Stalled · Microsoft bought 227 acres in Heath for a campus slated to start in summer 2025, then paused it.
- Status
- Stalled · as of April 8, 2025
- Location
- Thornwood Drive, Heath · Licking County
- Status note
- Microsoft paused the project but kept the land.
- Land
- 227 acres
- Developer and team
- Microsoft
- End user
- Microsoft
- Evidence
- News reports; primary records not yet obtained
- Size class
- 50 MW or more (tracker scope)
Updates, newest first
- April 8, 2025 Microsoft paused the Heath campus, which had been slated for construction in summer 2025, saying it would keep evaluating the site. (DatacenterDynamics, April 8, 2025)
Conflicts and open questions
- Microsoft said land at two of the three sites would be kept farmable; the source does not say which.
Have records about this project? Send them to tips@signaldata.org.