Data center project · Fayette County, Georgia

QTS Fayetteville campus

Under construction · A 16-building QTS campus on about 615 acres in Fayetteville that has been under construction since 2024 and is due to finish in 2030. Also known as: Project Excalibur.

← Georgia data centers
Appling CountyAtkinson CountyBacon CountyBaker CountyBaldwin CountyBanks CountyBarrow CountyBartow CountyBen Hill CountyBerrien CountyBibb CountyBleckley CountyBrantley CountyBrooks CountyBryan CountyBulloch CountyBurke CountyButts CountyCalhoun CountyCamden CountyCandler CountyCarroll CountyCatoosa CountyCharlton CountyChatham CountyChattahoochee CountyChattooga CountyCherokee CountyClarke CountyClay CountyClayton CountyClinch CountyCobb CountyCoffee CountyColquitt CountyColumbia CountyCook CountyCoweta CountyCrawford CountyCrisp CountyDade CountyDawson CountyDecatur CountyDeKalb CountyDodge CountyDooly CountyDougherty CountyDouglas CountyEarly CountyEchols CountyEffingham CountyElbert CountyEmanuel CountyEvans CountyFannin CountyFayette CountyFloyd CountyForsyth CountyFranklin CountyFulton CountyGilmer CountyGlascock CountyGlynn CountyGordon CountyGrady CountyGreene CountyGwinnett CountyHabersham CountyHall CountyHancock CountyHaralson CountyHarris CountyHart CountyHeard CountyHenry CountyHouston CountyIrwin CountyJackson CountyJasper CountyJeff Davis CountyJefferson CountyJenkins CountyJohnson CountyJones CountyLamar CountyLanier CountyLaurens CountyLee CountyLiberty CountyLincoln CountyLong CountyLowndes CountyLumpkin CountyMacon CountyMadison CountyMarion CountyMcDuffie CountyMcIntosh CountyMeriwether CountyMiller CountyMitchell CountyMonroe CountyMontgomery CountyMorgan CountyMurray CountyMuscogee CountyNewton CountyOconee CountyOglethorpe CountyPaulding CountyPeach CountyPickens CountyPierce CountyPike CountyPolk CountyPulaski CountyPutnam CountyQuitman CountyRabun CountyRandolph CountyRichmond CountyRockdale CountySchley CountyScreven CountySeminole CountySpalding CountyStephens CountyStewart CountySumter CountyTalbot CountyTaliaferro CountyTattnall CountyTaylor CountyTelfair CountyTerrell CountyThomas CountyTift CountyToombs CountyTowns CountyTreutlen CountyTroup CountyTurner CountyTwiggs CountyUnion CountyUpson CountyWalker CountyWalton CountyWare CountyWarren CountyWashington CountyWayne CountyWebster CountyWheeler CountyWhite CountyWhitfield CountyWilcox CountyWilkes CountyWilkinson CountyWorth CountyQTS Fayetteville campus · Under construction
Status
Under construction · as of July 13, 2026
Approved by
Fayetteville City Council (Georgia)
Development agreement between the City of Fayetteville and National Acquisition Company, LLC for the QTS data center at 1435 Highway 54 West, June 15, 2023, vote Unanimous
The Planning and Zoning Commission approved the conceptual site plan on Feb. 2, 2023, according to the same report. The council has changed since the vote (see the body record). (The Citizen (Fayette County), June 19, 2023)
Location
West Fayetteville, bounded by Highway 54, Flat Creek Trail and Tyrone Road · Fayette County
Status note
Still under construction, with completion expected in 2030.
Floor area
6,600,000 sq ft
Land
615 acres
Investment
More than $1 billion (2022 estimate); land bought for $153.8 million
Developer and team
QTS Data Centers
Water
Fayette County billed about 109 million gallons across 13 construction water lines; QTS expects about 9,000-12,000 gallons a month once its closed-loop system runs.
Evidence
News reports; primary records not yet obtained
Size class
50 MW or more (tracker scope)
Map position approximate, from the reported address or area. Updated Oct. 17, 2026.

Updates, newest first

  1. May 2025 Low-pressure complaints led the county to find two more QTS water lines and bill the company about $147,000; the county later blamed a smart-meter upgrade for the gap. (Atlanta News First, July 13, 2026)
  2. Feb. 2024 The first county water meter on the site came online. (Atlanta News First, July 13, 2026)
  3. Sept. 20, 2022 A regional-impact (DRI) filing described up to 16 buildings and 6.6 million sq ft of data center space. (DatacenterDynamics, Sept. 20, 2022)
  4. Aug. 2022 QTS bought the 615-acre site for $153.8 million, according to the Fayette County Development Authority. (DatacenterDynamics, Sept. 20, 2022)

Conflicts and open questions

  • No MW figure was confirmed. A 2022 unattributed report of 250 MW was never confirmed.
  • QTS says it used no water improperly or without paying. No wrongdoing has been alleged.
  • Atlanta News First notes the county denied a separate proposed data center in Fayetteville after neighbor opposition. The city later banned new data centers (see moratoriums).

Have records about this project? Send them to tips@signaldata.org.