Data center project · Martin County, Florida
Tesoro Groves PUD (FPL)
Site zoned or marketed · 5,722 acres of FPL land rezoned in Indiantown; possible data center development.
- Status
- Site zoned or marketed · as of April 30, 2026
- Location
- Indiantown, Kanner Hwy. · Martin County
- Status note
- FPL land annexed and rezoned unanimously, with no data center ban. FPL says the vote approved no specific project.
- Land
- 5,722 acres
- Developer and team
- Florida Power & Light
- Utility
- FPL
- Water
- Condition: a non-utility data center must pay a water deposit.
- Evidence
- News reports; primary records not yet obtained
- Size class
- 50 MW or more (tracker scope)
Updates, newest first
- April 30, 2026 Indiantown council approves the PUD after debate over data centers. (WQCS, May 4, 2026; Tampa Bay Times (syndicated by Tribune Content Agency), Aug. 1, 2026)
Political money tied to this project
- NextEra Energy Capital Holdings$1,000,000 to Byron Donalds ($500,000 on Dec. 19, 2025 to Friends of Byron Donalds PAC (PAC); $500,000 on Feb. 19, 2026 to Friends of Byron Donalds PAC (PAC)) · Parent of Florida Power & Light, the utility the Project Tango applicant says it has a power agreement with; FPL also land-banked 5,722 acres in Indiantown. (Florida Division of Elections, Oct. 16, 2026)
FL Division of Elections. Details and every other recipient in the Data Center File. The records do not show that any contribution influenced a decision.
Have records about this project? Send them to tips@signaldata.org.