Troup County
2 projects on record · 2 moratorium or ban actions
← Statewide map| Project West | Project West WHP - GA LLC | 600 | Proposed | March 10, 2025 | 50 MW+ |
| Google LaGrange data center | Google; Thor Equities (former owner); Form8ation (former developer) | 100 | Under construction | April 21, 2026 | 50 MW+ |
Moratoriums and bans
- Sept. 16, 2025 Troup County: Moratorium. 90-day pause on data center permits and applications in unincorporated Troup to rewrite its development code. (FOX 5 Atlanta, Sept. 17, 2025)
- Sept. 2025 LaGrange: Moratorium. 180-day pause; the tracker lists it as expired in March 2026. (Georgia Public Broadcasting, Oct. 22, 2025; SAVRN, Oct. 2026)
Updates, newest first
- April 21, 2026 Google LaGrange data center · Google confirmed it is developing the LaGrange data center; Thor said it is no longer involved. (DatacenterDynamics, April 21, 2026)
- Sept. 16, 2025 Project West · Troup County adopted a 90-day moratorium as Project West was pending. (FOX 5 Atlanta, Sept. 17, 2025)
- Sept. 16, 2025 Troup County: Moratorium · 90-day pause on data center permits and applications in unincorporated Troup to rewrite its development code. (FOX 5 Atlanta, Sept. 17, 2025)
- Sept. 2025 LaGrange: Moratorium · 180-day pause; the tracker lists it as expired in March 2026. (Georgia Public Broadcasting, Oct. 22, 2025; SAVRN, Oct. 2026)
- March 10, 2025 Project West · A regional-impact filing described six 252,000 sq ft buildings and a substation, built in phases through 2033, with annexation into LaGrange requested. (DatacenterDynamics, March 10, 2025)
- 2024 Google LaGrange data center · Thor Equities acquired the 270-acre site. (DatacenterDynamics, April 21, 2026)
Statewide
Georgia exempts qualifying high-technology data center hardware and equipment from state and local sales and use tax under O.C.G.A. § 48-8-3(68.1); the exemption runs through Dec. 31, 2031. (Alston & Bird, Feb. 19, 2026; Inside Climate News, April 9, 2026) Gov. Brian Kemp vetoed HB 1192 (2024), which would have suspended new data center exemption certificates. He cited the 2022 extension of the break through 2031. (Capitol Beat News Service, May 7, 2024) In the 2026 session, bills to end or suspend the exemption (SB 408, SB 410, SB 436, HB 559) and a construction pause (HB 1012) all failed; no data center bill passed. (Alston & Bird, Feb. 19, 2026; Inside Climate News, April 9, 2026) The PSC adopted a Georgia Power large-load rule on Jan. 23, 2025 (from Docket 55378). New customers over 100 MW face contracts of up to 15 years with minimum bills, pay for upstream generation and grid costs, and have their contracts reviewed by the PSC. (Georgia Public Service Commission, Jan. 23, 2025) On Dec. 19, 2025, the PSC voted 5-0 to certify 9,885 MW of new Georgia Power resources for expected data center load. Georgia Power backstops the costs for 2029-2031 so existing customers are shielded if the load does not appear. (Georgia Public Service Commission, Dec. 19, 2025) Georgia data centers →