Rockingham County
1 project on record
← Statewide map| WhiteFiber NC-1 (Madison) | WhiteFiber (Bit Digital) | 99 | Under construction | May 6, 2026 | 50 MW+ |
Updates, newest first
- May 6, 2026 WhiteFiber NC-1 (Madison) · WhiteFiber's page for the Madison campus (last updated May 6, 2026) said the building's electrical and cooling systems were being retrofitted to Tier 3 standards; it listed 24 MW as operational in one place and as expected in late 2025 in another. (WhiteFiber Inc., May 6, 2026)
- June 2, 2025 WhiteFiber NC-1 (Madison) · WhiteFiber said it bought the 96-acre site, had a Duke Energy capacity agreement for 99 MW (24 MW first), could grow to 200 MW, and had been confirmed as a qualifying data center for state sales tax exemptions. (WhiteFiber Inc. (Bit Digital) news release, via Channelchek/PR Newswire, June 2, 2025)
Statewide
G.S. 105-164.13(55a) exempts from state sales and use tax the electricity and support equipment (power, cooling, servers, networking) for a qualifying datacenter: one where the Commerce Secretary finds at least $75 million will be invested within five years and that meets a wage standard for its area and provides health insurance to its full-time employees; the older (55) exemption covers eligible internet datacenters investing $250 million in lower-tier counties. (North Carolina General Assembly, Oct. 20, 2026; North Carolina General Assembly, Oct. 20, 2026) Senate Bill 730, the Ratepayer Protection Act, was rewritten in the House to require utilities to contract with large data centers so they cover the cost of serving them; the House passed it 69-44 on June 3, 2026, and the Senate sent it to its Rules Committee on June 8 with no further action recorded. (North Carolina General Assembly, Oct. 20, 2026; Carolina Journal, June 4, 2026) Duke Energy reached a settlement in October 2026 in its rate cases (NCUC dockets E-7 Sub 1329 and E-2 Sub 1380) making an existing tariff mandatory for data centers and other customers that use large amounts of power nearly all the time, with upfront payment for dedicated facilities such as substations; it would not apply to contracts signed on or before June 1, 2026 and needs Utilities Commission approval. (WUNC / WFAE, Oct. 7, 2026; WUNC / WFAE, Oct. 14, 2026) Local moratoriums rest on G.S. 160D-107; Orange County cited it, and a Superior Court judge ruled in September 2026 that Chatham County's moratorium could not halt a project already under way. (Orange County, N.C., April 21, 2026; NC Newsline, Sept. 22, 2026) North Carolina data centers →