Data centers · Erie County, New York

Erie County

1 project on record

← Statewide map
Albany CountyAllegany CountyBronx CountyBroome CountyCattaraugus CountyCayuga CountyChautauqua CountyChemung CountyChenango CountyClinton CountyColumbia CountyCortland CountyDelaware CountyDutchess CountyErie CountyEssex CountyFranklin CountyFulton CountyGenesee CountyGreene CountyHamilton CountyHerkimer CountyJefferson CountyKings CountyLewis CountyLivingston CountyMadison CountyMonroe CountyMontgomery CountyNassau CountyNew York CountyNiagara CountyOneida CountyOnondaga CountyOntario CountyOrange CountyOrleans CountyOswego CountyOtsego CountyPutnam CountyQueens CountyRensselaer CountyRichmond CountyRockland CountySaratoga CountySchenectady CountySchoharie CountySchuyler CountySeneca CountySt. Lawrence CountySteuben CountySuffolk CountySullivan CountyTioga CountyTompkins CountyUlster CountyWarren CountyWashington CountyWayne CountyWestchester CountyWyoming CountyYates CountyRiverview Innovation & Technology Campus · Stalled · 300 MW
Projects in Erie County
Riverview Innovation & Technology CampusRiverview Innovation & Technology Campus, Inc.300StalledJune 3, 202650 MW+

Updates, newest first

  1. June 3, 2026 Riverview Innovation & Technology Campus · The developer asked the town planning board to pause its application because of a NYISO backlog; residents packed a meeting in opposition. (Buffalo Toronto Public Media, June 3, 2026)
  2. Jan. 31, 2025 Riverview Innovation & Technology Campus · Riverview filed a 300 MW data center load request on National Grid's Huntley-Packard 230 kV line. (New York Independent System Operator (NYISO), Sept. 30, 2026)

Statewide

Executive Order 62 (July 14, 2026) tells DEC to hold all incomplete discretionary permit applications for building or expanding data centers that use, or can use, 50 MW or more until the Department of Public Service finishes a statewide environmental impact statement; local permits are not covered, and the order sets no end date. (Office of the Governor of New York, July 14, 2026; Hodgson Russ LLP, July 16, 2026) Responsible Data Center Development Act (S10642/A11560): passed the Senate 43-17 on June 4, 2026 and the Assembly; it would pause state permits for data centers of 20 MW or more for a year, require separate utility rate classes and renewable targets; not yet signed or vetoed as of Oct. 18, 2026. (New York State Senate, June 4, 2026; WBNG, June 5, 2026) PSC Case 26-E-0045 (Energize NY Development) is the large-load interconnection proceeding, opened Feb. 12, 2026 under a beneficiary-pays approach; on Sept. 17, 2026 the PSC issued a draft scope for the data center environmental impact statement, with comments due Oct. 20, 2026. (New York State Public Service Commission (copy hosted by RTO Insider), Feb. 12, 2026; New York State Department of Public Service, Sept. 17, 2026; Office of the Governor of New York, July 14, 2026) Tax breaks: a 2000 state law gives internet data centers state and local sales tax breaks, and local IDAs grant sales, property and mortgage-tax abatements; the governor says she will seek a ban on these breaks for data centers of 50 MW or more in the next budget (no bill number yet). (Investigative Post, July 21, 2026; Spectrum News, Sept. 18, 2026) NYISO load queue: the state reports nearly 12 GW of data center load requests as of May 2026; the Sept. 30, 2026 queue lists data center requests across St. Lawrence, Niagara, Dutchess, Suffolk and other counties. (Office of the Governor of New York, July 14, 2026; New York Independent System Operator (NYISO), Sept. 30, 2026) New York data centers →