Data center project · Kenai Peninsula Borough, Alaska
DeepGreen Cook Inlet subsea data center
Proposed · A Delaware company asked FERC for a preliminary permit to study a 100 MW tidal-powered underwater data center in a roughly 1,650-acre corridor of Cook Inlet off Nikiski. Also known as: FERC Project No. P-15423-000.
- Status
- Proposed · as of Sept. 4, 2026
- Location
- Cook Inlet west of the Nikiski shoreline, East Foreland area (coordinates approximate) · Kenai Peninsula Borough
- Status note
- FERC accepted the preliminary permit application for comment (deadline Nov. 2, 2026); a preliminary permit would allow study only, not construction.
- Power
- 100 MW
100 MW from up to 350 underwater tidal turbines powering 66 server 'hives', per the application as reported. - Land
- 1,650 acres
- Investment
- Preliminary studies estimated at $4.5 million over four years (FERC filing, as reported)
- Developer and team
- DeepGreen Cook Inlet SPV LLC
- End user
- Not identified
- Utility
- Tidal power; the application proposes tying into the Alaska Energy Authority's planned Cook Inlet PowerLink line, which AEA says it was never consulted about
- Water
- Cooled by seawater
- Evidence
- News reports; primary records not yet obtained
- Size class
- 50 MW or more (tracker scope)
Updates, newest first
- Sept. 21, 2026 DeepGreen told FERC the requested modeling and studies would take place during a three-year study period. (Anchorage Daily News, Sept. 24, 2026)
- Sept. 14, 2026 The Kenai Peninsula Borough moved to intervene, joining the Center for Biological Diversity (Sept. 1) and the Alaska Commercial Fisheries Conservation Alliance, which raised salmon, beluga and fishing-gear concerns. (Anchorage Daily News, Sept. 24, 2026)
- Sept. 4, 2026 FERC published notice accepting the application, opening comment through Nov. 2, 2026. (Peninsula Clarion, Sept. 14, 2026; Anchorage Daily News, Sept. 24, 2026)
- June 18, 2026 FERC's hydropower licensing staff listed deficiencies, including missing dimensions for underwater components and missing notice to Kenai and to tribes and Native corporations; the company supplemented its filing June 26. (Anchorage Daily News, Aug. 19, 2026; Peninsula Clarion, Sept. 14, 2026)
- Feb. 11, 2026 DeepGreen Cook Inlet filed a preliminary permit application at FERC. (Peninsula Clarion, Sept. 14, 2026; Anchorage Daily News, Aug. 19, 2026)
Conflicts and open questions
- FERC's acceptance date differs by source: Sept. 1 (ADN) and Sept. 4 notice (Peninsula Clarion).
- The 'three-mile footprint' and 1,650-acre corridor are the application's project boundary, not a built footprint.
- A related DeepGreen proposal off Eastport, Maine, is in the Maine file.