Data center project · Los Angeles County, California
Goodman LAX01 (Vernon)
Under construction · A three-level, 49.5 MW Goodman data center under construction in Vernon (under 50 MW).
- Status
- Under construction · as of July 2026
- Location
- Vernon (address not reported) · Los Angeles County
- Power
- 49.5 MW
Under 50 MW: 49.5 MW total, about 32 MW of IT load. - Land
- 5.6 acres
- Developer and team
- Goodman Group
- Utility
- City of Vernon
- Evidence
- News reports; primary records not yet obtained
- Size class
- Under 50 MW (outside main scope; kept for completeness)
Updates, newest first
- July 2026 KQED pictured the 49.5 MW Vernon data center still under construction. (KQED, Sept. 21, 2026)
- March 20, 2025 Goodman reported construction had begun, with a powered shell expected by mid-2026. (Connect CRE, March 20, 2025)
Conflicts and open questions
- Coordinates are the approximate city location; relationship to the Goodman Energy Park filing not confirmed.
Have records about this project? Send them to tips@signaldata.org.