Data center project · San Francisco County, California
NOVVA San Francisco (400 Paul Avenue)
Paused by moratorium · An existing Bayview data center whose planned expansion falls under San Francisco's 45-day moratorium (under 50 MW).
- Status
- Paused by moratorium · as of Oct. 6, 2026
- Location
- 400 Paul Avenue, Bayview, San Francisco · San Francisco County
- Power
- 36 MW
Under 50 MW: the first phase brought 9 MW online in summer 2026; the company plans to reach 36 MW by 2028 (Mission Local). - Land
- 7.5 acres
- Developer and team
- NOVVA
- Evidence
- News reports; primary records not yet obtained
- Size class
- Under 50 MW (outside main scope; kept for completeness)
Updates, newest first
- Oct. 6, 2026 The Board of Supervisors' unanimous 45-day moratorium on new and expanded data centers took effect, covering this expansion. (SFist, Oct. 7, 2026)
- Sept. 10, 2026 Mission Local reported the first phase, 9 MW, came online that summer, and that Supervisor Shamann Walton planned a moratorium that could delay the expansion; NOVVA did not comment. (Mission Local, Sept. 10, 2026)
- 2016 The San Francisco Planning Commission approved the data center, Mission Local reported. (Mission Local, Sept. 10, 2026)