Data center project · Weld County, Colorado
Cielo Hudson Data Center
Proposed · A planned 500-acre, 750 MW campus in Hudson that Rocky Mountain PBS said would be Colorado's largest data center.
- Status
- Proposed · as of July 22, 2026
- Location
- Hudson · Weld County
- Status note
- Announced, with no construction date; no town filing was found in the sources reviewed.
- Power
- 750 MW
Planned power capacity as reported by Rocky Mountain PBS. - Land
- 500 acres
- Developer and team
- Cielo Digital Infrastructure
- Evidence
- News reports; primary records not yet obtained
- Size class
- 50 MW or more (tracker scope)
Updates, newest first
- July 22, 2026 Rocky Mountain PBS reported the Hudson plan while covering neighboring Lochbuie's five-year moratorium, whose mayor cited it as a reason for the pause. (Rocky Mountain PBS, July 22, 2026)
Conflicts and open questions
- Single secondary source; no Hudson agenda, filing or company release was opened. Rocky Mountain PBS linked its description to a Cleanview tracker entry (2024) that lists the project as planned on 500 acres in Weld County.