Data center project · Denver County, Colorado
CoreSite Denver DE3 campus
Under construction · A three-building, 600,000-square-foot campus on a former concrete plant site in north Denver, under construction and the focus of neighborhood concern. Also known as: DE3.
- Status
- Under construction · as of Oct. 6, 2025
- Location
- 4900-5050 Race St., Globeville-Elyria-Swansea, Denver · Denver County
- Status note
- First building (about 170,000-180,000 sq ft) targeted for 2026; Denver's moratorium does not stop permitted construction, though later phases could face new rules.
- Power
- 60 MW
Campus critical (IT) capacity per CoreSite; a company spokeswoman put maximum power need at 65-75 MW in 2024, and DCD reported the first building at 18 MW. - Floor area
- 600,000 sq ft
- Developer and team
- CoreSite (American Tower)
- Utility
- Xcel Energy
- Water
- Up to about 805,000 gallons a day at full build, per company figures reported in 2024; average use expected to be lower.
- Incentives
- Proposed 2024 Denver agreement returning half of site sales and use taxes, capped at $9 million over 15 years; council action not found in the sources reviewed.
- Evidence
- Primary public records
- Size class
- 50 MW or more (tracker scope)
Updates, newest first
- May 18, 2026 Denver's one-year moratorium left permitted construction, including this project, untouched. (Colorado Newsline (via KUNC), Aug. 10, 2026)
- Oct. 6, 2025 CoreSite announced a construction milestone for DE3, about 180,000 sq ft, with opening expected in 2026 and a campus total of 60 critical MW. (CoreSite, Oct. 6, 2025)
- Oct. 18, 2024 Council members questioned the tax break over water and power use; CoreSite said maximum demand would be 65-75 MW and typical use under half of capacity. (Governing (Tribune Content Agency), Oct. 18, 2024)
- Aug. 30, 2024 DCD reported CoreSite was seeking a Denver tax agreement returning 50% of site sales and use taxes, up to $9 million, for a three-building campus of about 60 MW. (DatacenterDynamics, Aug. 30, 2024)
Conflicts and open questions
- Addresses appear as 4900 Race St. (CoreSite) and 5050 Race St. (earlier reporting); DCD said they appear to be one site.
- First-building size differs: about 180,000 sq ft (CoreSite, 2025) and about 170,000 sq ft (Colorado Politics photo caption).
Have records about this project? Send them to tips@signaldata.org.