Data center project · Weld County, Colorado
Global AI data center, former Kodak/Carestream site
Approved · A permit to reuse part of the former Carestream campus near Windsor as an AI data center, approved 5-0 and now challenged in court and by petition. Also known as: GlobalAI Windsor, USR26-0019.
- Status
- Approved · as of Sept. 9, 2026
- Location
- 2000 Howard Smith Avenue W., unincorporated Weld County southeast of Windsor · Weld County
- Status note
- Use by Special Review approved; a lawsuit and a referendum petition seek to undo it.
- Power
- 27.5 MW
First phase as reported by Colorado Newsline; DCD earlier reported 18-24 MW for phase one and a 50-60 MW target. The company's 1 GW goal is network-wide and not approved here. - Land
- 438 acres
- Developer and team
- Global AI
- End user
- DCD reported Saudi AI company Humain is set to deploy in Global AI facilities.
- Utility
- Poudre Valley Rural Electric Association
- Water
- Closed-loop cooling required as a permit condition; initial fill about 65,000 gallons with small annual top-offs.
- Evidence
- News reports; primary records not yet obtained
- Size class
- Under 50 MW (outside main scope; kept for completeness)
Updates, newest first
- Oct. 6, 2026 GWIP Land Company and Windsor Renewal sued the county and Global AI in state court to vacate the permit, raising noise, water supply, power supply and project-segmentation claims. (Courthouse News Service, Oct. 7, 2026)
- Sept. 28, 2026 The clerk approved two petitions from the group POWER for circulation: a referendum on the approval and an initiative requiring voter approval before any data center gets an occupancy permit; each needs 9,103 signatures. (Colorado Newsline (via KUNC), Oct. 1, 2026)
- Sept. 9, 2026 Weld County commissioners approved permit USR26-0019 for a 41-acre data center use 5-0 after a daylong hearing with mostly opposing comment, conditioning it on closed-loop cooling, ambient noise limits and a decommissioning bond; the county said future phases need more review. (Colorado Newsline (via KUNC), Sept. 12, 2026; ConstructConnect, Sept. 16, 2026)
- Nov. 2025 Global AI completed its $15.6 million purchase of the 438-acre property. (DatacenterDynamics, Feb. 9, 2026)
Conflicts and open questions
- Acres shown are the whole property; the approved use covers 41 acres.
- Purchase timing differs: completed in late November 2025 (DCD) or December 2025 (Colorado Newsline).
- Global AI presented a Poudre Valley REA will-serve letter for 35 MW; the lawsuit says the co-op committed power only through 2030 and would supply 23 MW in the final year against 27.5 MW needed.
Have records about this project? Send them to tips@signaldata.org.