Data center project · Logan County, Colorado
Granite Renewables data center campus, Peetz Table area
Inquiry only · Early talks with Logan County about a hyperscale campus paired with on-site renewables and gas on wheat and grazing land near the Nebraska line.
- Status
- Inquiry only · as of Dec. 16, 2025
- Location
- About 21 miles northwest of Sterling, near the Peetz Table · Logan County
- Status note
- Commissioners said no application had been received; the county was adopting data center rules first.
- Power
- Not reported
No stated developer figure. A commissioner relayed that the local co-op was asked for a two-gigawatt connection, and Big Pivots heard 'up to two gigawatts' discussed in Sterling. - Investment
- A speaker at a local meeting put total investment at $15 billion, per Big Pivots (unverified).
- Developer and team
- Granite Renewables
- Utility
- Highline Electric Association / Tri-State
- Evidence
- Primary public records
- Size class
- Under 50 MW (outside main scope; kept for completeness)
Updates, newest first
- Feb. 17, 2026 Law Week Colorado reported that Logan County's data center rules, Resolution 2026-5, took effect for facilities of 1 MW or more nameplate capacity. (Law Week Colorado, July 27, 2026)
- Dec. 30, 2025 Big Pivots reported Granite Renewables had been meeting county officials since late summer and that about 4,000 acres had been discussed in Sterling. (Big Pivots (via Kiowa County Press), Dec. 30, 2025)
- Dec. 16, 2025 At a work session, commissioners said no data center application had arrived, that applicants would have to arrange their own power and transmission, and that a hearing on data center rules was set for Jan. 6, 2026. (Logan County Board of County Commissioners, Dec. 16, 2025)
- Oct. 7, 2025 At a business meeting, Logan County commissioners asked the county attorney to draft a moratorium on data center, battery storage, wind and solar projects, for adoption Oct. 21, while rules were written. (Sterling Journal-Advocate (via GovTech / Tribune Content Agency), Oct. 9, 2025)
Conflicts and open questions
- The minutes do not name the developer; Big Pivots does. Acreage (about 4,000) was discussed locally and may include solar and storage; it is not entered as project acres.
- Whether an application was filed after the county's rules took effect was not found.