Data center project · Arapahoe County, Colorado

QTS Aurora-Denver campus

Under construction · Colorado's largest data center and, per CPR and Colorado Newsline, its only hyperscale campus, now adding buildings and seeking a state permit for 98 more diesel backup generators. Also known as: QTS Aurora-Denver 1, QTS Denver 1.

← Colorado data centers
Adams CountyAlamosa CountyArapahoe CountyArchuleta CountyBaca CountyBent CountyBoulder CountyBroomfield CountyChaffee CountyCheyenne CountyClear Creek CountyConejos CountyCostilla CountyCrowley CountyCuster CountyDelta CountyDenver CountyDolores CountyDouglas CountyEagle CountyEl Paso CountyElbert CountyFremont CountyGarfield CountyGilpin CountyGrand CountyGunnison CountyHinsdale CountyHuerfano CountyJackson CountyJefferson CountyKiowa CountyKit Carson CountyLa Plata CountyLake CountyLarimer CountyLas Animas CountyLincoln CountyLogan CountyMesa CountyMineral CountyMoffat CountyMontezuma CountyMontrose CountyMorgan CountyOtero CountyOuray CountyPark CountyPhillips CountyPitkin CountyProwers CountyPueblo CountyRio Blanco CountyRio Grande CountyRoutt CountySaguache CountySan Juan CountySan Miguel CountySedgwick CountySummit CountyTeller CountyWashington CountyWeld CountyYuma CountyQTS Aurora-Denver campus · Under construction · 160 MW
Status
Under construction · as of July 8, 2026
Location
1160 N. Gun Club Road, eastern Aurora, south of Denver International Airport · Arapahoe County
Status note
One building complete, a second nearly finished and a third in site preparation, per CPR.
Power
160 MW
Planned critical (IT) capacity of at least 160 MW per QTS, matching CPR's figure; Big Pivots reported 177 MW of demand (range 160-177 MW). CPR put the full generator fleet near 345 MW, which is backup capacity, not load.
Land
65 acres
Developer and team
QTS Data Centers (Blackstone)
Utility
Xcel Energy
Water
About 2,400 gallons a day with closed-loop cooling, according to Aurora Water as quoted by CPR.
Evidence
Primary public records
Size class
50 MW or more (tracker scope)
Map position approximate, from the reported address or area. Updated Oct. 17, 2026.

Updates, newest first

  1. Oct. 21, 2026 As of Oct. 21, 2026, QTS's campus page lists the Aurora-Denver 1 site at 1160 N. Gun Club Road with 65 acres and more than 160 MW of planned critical capacity. (QTS Data Centers, undated)
  2. Aug. 11, 2026 Colorado Politics called the QTS campus the largest data center project under construction in Colorado, needing about 160 MW when complete. (Colorado Politics / The Denver Gazette, Aug. 11, 2026)
  3. July 8, 2026 CPR reported the generator application was still under review, with a 30-day comment period expected after public notice, and that state compliance staff were checking whether construction so far met air rules; QTS said it was fully authorized to proceed. (Colorado Public Radio, July 8, 2026)
  4. Oct. 26, 2025 Big Pivots described QTS as Colorado's most prominent data center, with a 10-year ramp-up on its Aurora campus. (Big Pivots (via KUNC), Oct. 26, 2025)
  5. July 2025 QTS applied to state air regulators to modify its permit and add 98 diesel backup generators to the 40 already installed, and to raise yearly testing from 24 to 36 hours. (Colorado Public Radio, July 8, 2026)
  6. Feb. 2025 CPR reported QTS received local construction permits for the campus expansion in February 2025. (Colorado Public Radio, July 8, 2026)

Conflicts and open questions

  • Campus size differs by source: 65 acres (QTS; CPR, 2026) and 67 acres (Big Pivots, 2025); power is at least 160 MW (QTS; CPR; Colorado Politics) or 177 MW (Big Pivots).
  • County: the Census geocoder places QTS's listed address in the Arapahoe County part of Aurora.

Have records about this project? Send them to tips@signaldata.org.