Data center project · Adams County, Colorado
Trident Data Center at Windler (Vantage Data Centers)
Proposed · A two-story, 1.5 million-square-foot data center on 108 acres beside Green Valley Ranch that Aurora's mayor has vowed to stop.
- Status
- Proposed · as of Oct. 14, 2026
- Location
- Northwest corner of E-470 and East 48th Avenue, Aurora, next to Green Valley Ranch · Adams County
- Status note
- Site plan in its third city review; data centers are a use by right there, so approval is administrative unless the council calls it up. A council member said Vantage agreed to look at other Aurora sites; Vantage had not confirmed.
- Power
- 334 MW
IT capacity in Vantage's design as reported by Axios, which put total electrical demand near 500 MW; residents also cited about 500 MW. Residents' generator emission estimates are not a capacity figure. - Floor area
- 1,500,000 sq ft
- Land
- 108 acres
- Developer and team
- Vantage Data Centers
- Utility
- Xcel Energy
- Evidence
- News reports; primary records not yet obtained
- Size class
- 50 MW or more (tracker scope)
Updates, newest first
- Oct. 14, 2026 Council member Rob Andrews said Vantage agreed to look at alternative sites in Aurora; Vantage did not respond to the Gazette. (Colorado Politics / The Denver Gazette, Oct. 14, 2026)
- Oct. 1, 2026 Mayor Mike Coffman wrote that the project must be stopped even at the risk of a lawsuit and said he would ask the council to vote it down; Vantage said it wanted the project judged on verified facts. (Colorado Politics / The Denver Gazette, Oct. 2, 2026)
- Sept. 28, 2026 About a hundred Green Valley Ranch residents, including people from the 55-plus Reserve community, packed a council meeting to oppose the plan; the city attorney has said the industrial zoning permits data centers and that denying a plan that meets the code could expose the city to liability. (Colorado Politics / The Denver Gazette, Oct. 2, 2026; Colorado Politics / The Denver Gazette, Oct. 14, 2026)
- Sept. 28, 2026 Axios reported that Vantage's design calls for two two-story buildings of about 860,000 sq ft, 334 MW of IT capacity, roughly 500 MW of total demand and 28 emergency diesel generators, and that the project still needs a state air-quality construction permit. (Axios Denver, Sept. 28, 2026)
- Aug. 25, 2025 Vantage submitted the Trident application to the city. (Colorado Politics / The Denver Gazette, Oct. 15, 2026)
Conflicts and open questions
- Building area differs: Colorado Politics cites 1.5 million square feet on 108 acres from the city portal, while Axios describes two buildings totaling about 860,000 square feet; residents' documents cited at least 60 generators against the 28 in Vantage's design (Axios).
- County: the Census geocoder places the reported corner (E-470 and East 48th Avenue) in the Adams County part of Aurora.
Have records about this project? Send them to tips@signaldata.org.