Data center project · Adair County, Iowa
Applied Digital Adair data center (proposed)
Proposed · A 200 MW, two-building Applied Digital proposal that led Adair County, which has no zoning, to draft setback rules in 2024.
- Status
- Proposed · as of April 24, 2024
- Location
- 1200 block of Fallow Avenue, Adair, next to a NextEra substation · Adair County
- Power
- 200 MW
- Floor area
- 600,000 sq ft
- Developer and team
- Applied Digital
- Evidence
- News reports; primary records not yet obtained
- Size class
- 50 MW or more (tracker scope)
Updates, newest first
- March 18, 2026 The supervisors' agenda listed a data center ordinance and a possible data center moratorium for discussion. (Adair County Board of Supervisors, March 18, 2026)
- April 24, 2024 After a hearing, supervisors voted down a motion to take no action and amended the draft to setbacks for any commercial building over 50,000 square feet, including 1,200 feet from homes. (Western Iowa Today, April 24, 2024)
- April 2, 2024 Applied Digital told supervisors about a site near Adair with 40 to 70 jobs and construction possibly that summer or fall. (Western Iowa Today, April 5, 2024; DatacenterDynamics, April 12, 2024)
Conflicts and open questions
- No record after April 2024 was found showing the project advanced or was dropped; status is the last record found.
- The Creston News Advertiser's original reports could not be opened (links returned 404).
Have records about this project? Send them to tips@signaldata.org.