Data center project · Pottawattamie County, Iowa
Google Council Bluffs data centers
Operating · Google's oldest Iowa campus keeps growing: a $1 billion expansion in 2024 and part of a $7 billion statewide pledge in 2025.
- Status
- Operating · as of June 2, 2025
- Location
- Council Bluffs · Pottawattamie County
- Status note
- Operating since 2007, with further expansion announced in 2024 and 2025.
- Power
- Not reported
No figure published. - Investment
- Google says it has invested more than $20 billion in Iowa since 2007; a $1 billion expansion was announced in 2024
- Developer and team
- End user
- Evidence
- Primary public records
- Size class
- Under 50 MW (outside main scope; kept for completeness)
Updates, newest first
- June 2, 2025 Google pledged $7 billion more in Iowa over two years, including a Council Bluffs expansion. (DatacenterDynamics, June 2, 2025; Google (company page), Oct. 20, 2026)
- July 2, 2024 Google announced another $1 billion to expand the Council Bluffs campus, with construction cranes on site. (Omaha World-Herald, July 2, 2024)
Conflicts and open questions
- AP reported in 2023 that Google's Council Bluffs data centers drew more potable water than any of its other sites.
Have records about this project? Send them to tips@signaldata.org.