Data center project · Polk County, Iowa

Tract Altoona data center campus

Approved · Tract's first Des Moines-area campus, 453 entitled acres planned for more than 1 GW of data centers.

← Iowa data centers
Adair CountyAdams CountyAllamakee CountyAppanoose CountyAudubon CountyBenton CountyBlack Hawk CountyBoone CountyBremer CountyBuchanan CountyBuena Vista CountyButler CountyCalhoun CountyCarroll CountyCass CountyCedar CountyCerro Gordo CountyCherokee CountyChickasaw CountyClarke CountyClay CountyClayton CountyClinton CountyCrawford CountyDallas CountyDavis CountyDecatur CountyDelaware CountyDes Moines CountyDickinson CountyDubuque CountyEmmet CountyFayette CountyFloyd CountyFranklin CountyFremont CountyGreene CountyGrundy CountyGuthrie CountyHamilton CountyHancock CountyHardin CountyHarrison CountyHenry CountyHoward CountyHumboldt CountyIda CountyIowa CountyJackson CountyJasper CountyJefferson CountyJohnson CountyJones CountyKeokuk CountyKossuth CountyLee CountyLinn CountyLouisa CountyLucas CountyLyon CountyMadison CountyMahaska CountyMarion CountyMarshall CountyMills CountyMitchell CountyMonona CountyMonroe CountyMontgomery CountyMuscatine CountyO'Brien CountyOsceola CountyPage CountyPalo Alto CountyPlymouth CountyPocahontas CountyPolk CountyPottawattamie CountyPoweshiek CountyRinggold CountySac CountyScott CountyShelby CountySioux CountyStory CountyTama CountyTaylor CountyUnion CountyVan Buren CountyWapello CountyWarren CountyWashington CountyWayne CountyWebster CountyWinnebago CountyWinneshiek CountyWoodbury CountyWorth CountyWright CountyTract Altoona data center campus · Approved · 1,000 MW
Status
Approved · as of Oct. 1, 2025
Location
Altoona · Polk County
Power
1,000 MW
Over 1 GW planned (developer).
Land
453 acres
Developer and team
Tract
Evidence
News reports; primary records not yet obtained
Size class
50 MW or more (tracker scope)
Map position approximate, from the reported address or area. Updated Oct. 17, 2026.

Updates, newest first

  1. Oct. 1, 2025 Altoona said it had annexed and rezoned the land and approved a development agreement with Tract. (Altoona Now!, Oct. 1, 2025)
  2. Sept. 11, 2025 Tract said it had bought land in Iowa to prepare for more than 1 GW of data center capacity. (The Tech Capital, Sept. 11, 2025)

Conflicts and open questions

  • Dates of the annexation, rezoning and agreement votes were not found; the city's announcement gives only that they occurred.
  • No end user named.

Have records about this project? Send them to tips@signaldata.org.