Project Star Data Center Campus (Aligned, Coal City)
Aligned's five-building, 864 MW proposal on industrial park land south of Coal City, in village PUD review since summer 2026. Also known as: Project Star.
Who is behind it
The record, newest first
The village posted the agenda for a fourth PUD review committee meeting; petitioner responses to review and public comments were posted Oct. 9. (Village of Coal City, undated)
A fiscal report for Aligned described five buildings totaling 3.2 million square feet, built from 2027 to 2033, with a $15.1 billion investment. (Village of Coal City (posted); Mangum Economics for Aligned Data Centers, July 23, 2026)
Aligned held a community open house on the roughly 300-acre proposal. (Village of Coal City, undated; WSPY News, Feb. 2026)
After a 2024 letter of intent from Aligned, the village adopted an inducement resolution allowing a predevelopment agreement to be considered. (Village of Coal City, May 17, 2026)
Conflicts and open questions
- Coordinates approximate, based on the Reed Road and Carbon Hill Road corner south of Coal City.
- Acreage of 300 is from WSPY reporting; village pages say only 'industrial park acreage'.
- Inducement resolution date given only as 'late 2024' in village slides; event dated to month.
The full record
- Status note
- Planned unit development review under way before the village's PUD review committee (fourth meeting agenda posted for Oct. 14, 2026); a Zoning Board of Appeals conditional use hearing is set for a future, unannounced date.
- Power note
- Transmission service level that the village says Aligned's agreement guarantees for 10 years; utility load, not a stated IT load.
- Evidence
- Primary public records
- Size class
- 50 MW or more (tracker scope)