Aligned ORD-03, Northwest Point, Elk Grove Village
Two-building campus replacing office buildings on Northwest Point Boulevard, approved with a Class 6(b) property tax incentive. Also known as: ORD-03, Northwest Point.
Who is behind it
The record, newest first
Aligned listed ORD-03 at 50 NW Point Blvd. on 36 acres and published material on its cooling design. (Aligned Data Centers, Oct. 22, 2026; Aligned Data Centers, Jan. 7, 2026)
The village approved a Class 6(b) incentive for two two-story buildings totaling more than 2 million sq ft, at a reported $285 million. (DatacenterDynamics, Feb. 22, 2024)
Aligned bought neighboring parcels and submitted plans for a data center campus to the village, which sent it to public hearing. (DatacenterDynamics, June 29, 2023)
Aligned bought a 177,000 sq ft office building on 10 acres at 50 Northwest Point Blvd. (DatacenterDynamics, April 14, 2023)
Conflicts and open questions
- Status may now be construction or operating; not confirmed from a record.
- Coordinates approximate, from the street address.
The full record
- Status note
- Village approved a Class 6(b) tax incentive in February 2024; the operator now lists ORD-03 among its Chicago facilities, but no record found states it is operating.
- Power note
- No capacity published for this campus.
- Evidence
- News reports; primary records not yet obtained
- Size class
- Under 50 MW (outside main scope; kept for completeness)