CyrusOne Wood Dale campus (Bryn Mawr)
A multi-phase CyrusOne campus planned for six data centers on roughly 66 acres in Wood Dale and Bensenville, with its first buildings under construction. Also known as: Bryn Mawr II, Bryn Mawr III, CHI6.
Who is behind it
The record, newest first
Wood Dale's Community Development Commission scheduled a hearing on a final Phase I plan to allow Building 2, citing revised plans driven by prospective tenant needs, across the 24-acre Bryn Mawr II and 42-acre Bryn Mawr III properties. (City of Wood Dale, Sept. 10, 2025)
CyrusOne topped out two buildings totaling more than 500,000 square feet with 18 MW of initial IT capacity. (CyrusOne, May 13, 2025; Data Center Dynamics, May 21, 2025)
DuPage County's economic development group described the project as six data centers totaling about 1.4 million square feet, due for completion by 2032. (Choose DuPage, March 6, 2025)
Wood Dale approved the 42-acre Bryn Mawr III phase, four buildings of about 996,850 square feet, 7-0 (case CDC-2024-0007), per a compilation of city records; the city's 2025 notice confirms council approval of the 42-acre redevelopment in January 2025. (Colocation Scout (powered by Bridgepointe Technologies), Oct. 15, 2026; City of Wood Dale, Sept. 10, 2025)
Illinois DCEO approved C1 Chicago 1 LLC and C1 Chicago 2 LLC in Wood Dale for the Data Center Investment Program with a $250 million commitment. (Illinois Department of Commerce and Economic Opportunity, 2026)
Conflicts and open questions
- Under 50 MW at initial phase; full build-out MW not published. Kept as a confirmed campus under construction.
- Acres use the city notice (about 24 + 42 acres). Choose DuPage once refers to the project as NTT's, apparently in error.
- Outcome of the Oct. 20, 2025 hearing not found.
- Coordinates approximate, Bryn Mawr Avenue area west of Route 83 in Wood Dale.
The full record
- Status note
- Two buildings topped out in May 2025; a hearing on the final Phase I plan to allow Building 2 was set for Oct. 20, 2025.
- Power note
- Initial IT capacity stated by CyrusOne at topping out; scalable, no full build-out figure published.
- Evidence
- Primary public records
- Size class
- Under 50 MW (outside main scope; kept for completeness)