Data center campus · Yorkville; east of Eldamain Road, north of the BNSF railroad and Faxon Road, west of Beecher Road, Kendall County, Illinois

CyrusOne Yorkville campus

Approved as of July 9, 2024

CyrusOne's subsidiary won Yorkville approval in July 2024 for up to nine data center buildings and a substation on about 230 acres at Eldamain and Faxon roads, to be built in phases over 10 to 20 years. Also known as: C1 Yorkville.

Cite← Illinois data centers
Adams CountyAlexander CountyBond CountyBoone CountyBrown CountyBureau CountyCalhoun CountyCarroll CountyCass CountyChampaign CountyChristian CountyClark CountyClay CountyClinton CountyColes CountyCook CountyCrawford CountyCumberland CountyDe Witt CountyDeKalb CountyDouglas CountyDuPage CountyEdgar CountyEdwards CountyEffingham CountyFayette CountyFord CountyFranklin CountyFulton CountyGallatin CountyGreene CountyGrundy CountyHamilton CountyHancock CountyHardin CountyHenderson CountyHenry CountyIroquois CountyJackson CountyJasper CountyJefferson CountyJersey CountyJo Daviess CountyJohnson CountyKane CountyKankakee CountyKendall CountyKnox CountyLake CountyLaSalle CountyLawrence CountyLee CountyLivingston CountyLogan CountyMacon CountyMacoupin CountyMadison CountyMarion CountyMarshall CountyMason CountyMassac CountyMcDonough CountyMcHenry CountyMcLean CountyMenard CountyMercer CountyMonroe CountyMontgomery CountyMorgan CountyMoultrie CountyOgle CountyPeoria CountyPerry CountyPiatt CountyPike CountyPope CountyPulaski CountyPutnam CountyRandolph CountyRichland CountyRock Island CountySaline CountySangamon CountySchuyler CountyScott CountyShelby CountySt. Clair CountyStark CountyStephenson CountyTazewell CountyUnion CountyVermilion CountyWabash CountyWarren CountyWashington CountyWayne CountyWhite CountyWhiteside CountyWill CountyWilliamson CountyWinnebago CountyWoodford CountyCyrusOne Yorkville campus · Approved
PowerNot statedNot reported in the records found
Site230acres

Who is behind it

ProjectCyrusOne Yorkville campusAlso: C1 Yorkville
Developer and teamCyrusOne (C1 Yorkville, LLC)
End userNot found in the recordsNot yet named in any record or credited report we have found.

The record, newest first

  1. After pausing the second-phase case in November 2025, the petitioner formally asked the city to withdraw all of its phase-two applications. (United City of Yorkville, April 17, 2026)

  2. C1 Yorkville LLC filed revised petitions for a second phase: three buildings totaling about 740,000 sq ft and a substation on about 128 acres east of Beecher Road (case PZC 2025-15). (United City of Yorkville, April 17, 2026; WSPY News, Sept. 20, 2025)

  3. The Yorkville City Council unanimously approved the planned unit development and development agreements for the campus, following a unanimous Planning and Zoning Commission recommendation. (Shaw Local (Kendall County Now), July 20, 2024; DatacenterDynamics, July 11, 2024)

  4. C1 Yorkville LLC, a CyrusOne subsidiary, filed for a planned unit development covering up to nine data center buildings and an on-site substation on about 230 acres (case PZC 2024-15). (United City of Yorkville, June 12, 2024; DatacenterDynamics, June 10, 2024)

Conflicts and open questions

  • Acreage is given as 228 acres in some coverage and about 230 acres in the city case file.
  • The withdrawn second phase (about 128 acres east of Beecher Road) is recorded here as an event rather than a separate project because the city files present it as phase two of the same campus.
  • Coordinates are approximate, based on the Eldamain Road / Faxon Road corner described in the city file.

The full record

Status note
The city council approved the first campus in July 2024; a separate second-phase petition to the east was paused in November 2025 and withdrawn in April 2026.
Power note
No megawatt figure appears in the city records or news coverage opened for this review.
Evidence
Primary public records
Size class
50 MW or more (tracker scope)
Map position approximate, from the reported address or area. Updated Oct. 17, 2026.