Project Vector
DeKalb's city council unanimously approved Edged's four-building, roughly 3 million sq ft Project Vector campus on 560 acres south of Meta's data center in December 2025, less than a month after it became public. Also known as: Edged DeKalb.
Who is behind it
The record, newest first
The city council unanimously approved the project, with one alderman absent. (Shaw Local (Daily Chronicle), Dec. 9, 2025; Northern Public Radio (WNIJ), Dec. 9, 2025)
A public hearing on the petition drew a standing-room crowd; the Planning and Zoning Commission's recommendation was later cited in support of approval. (Shaw Local (Daily Chronicle), Nov. 15, 2025; Shaw Local (Daily Chronicle), Dec. 8, 2025; Northern Public Radio (WNIJ), Dec. 9, 2025)
The 560-acre Project Vector petition from ChicagoWest Business Center (JJK 343 LLC) became public, with four buildings and two substations. (Shaw Local (Daily Chronicle), Nov. 15, 2025)
Conflicts and open questions
- Square footage is the sum of the four phased buildings (980,000; 515,000; 980,000; 490,000 sq ft) reported by the Daily Chronicle, planned from 2027 to 2032.
- Daily Chronicle reports natural gas generators would power the waterless chillers; no MW figure found.
The full record
- Evidence
- News reports; primary records not yet obtained
- Size class
- 50 MW or more (tracker scope)