Data center campus · Yorkville; south of Corneils Road and east of Beecher Road, west of the Caledonia subdivision, Kendall County, Illinois

Green Door Capital data center near Caledonia (Meyer property)

Withdrawn as of April 15, 2026

A Green Door Capital rezoning for a data center on farmland next to Yorkville's Caledonia subdivision was rejected by the planning commission, tabled by the council and then withdrawn in April 2026. Also known as: Yorkville Nexus V.

Cite← Illinois data centers
Adams CountyAlexander CountyBond CountyBoone CountyBrown CountyBureau CountyCalhoun CountyCarroll CountyCass CountyChampaign CountyChristian CountyClark CountyClay CountyClinton CountyColes CountyCook CountyCrawford CountyCumberland CountyDe Witt CountyDeKalb CountyDouglas CountyDuPage CountyEdgar CountyEdwards CountyEffingham CountyFayette CountyFord CountyFranklin CountyFulton CountyGallatin CountyGreene CountyGrundy CountyHamilton CountyHancock CountyHardin CountyHenderson CountyHenry CountyIroquois CountyJackson CountyJasper CountyJefferson CountyJersey CountyJo Daviess CountyJohnson CountyKane CountyKankakee CountyKendall CountyKnox CountyLake CountyLaSalle CountyLawrence CountyLee CountyLivingston CountyLogan CountyMacon CountyMacoupin CountyMadison CountyMarion CountyMarshall CountyMason CountyMassac CountyMcDonough CountyMcHenry CountyMcLean CountyMenard CountyMercer CountyMonroe CountyMontgomery CountyMorgan CountyMoultrie CountyOgle CountyPeoria CountyPerry CountyPiatt CountyPike CountyPope CountyPulaski CountyPutnam CountyRandolph CountyRichland CountyRock Island CountySaline CountySangamon CountySchuyler CountyScott CountyShelby CountySt. Clair CountyStark CountyStephenson CountyTazewell CountyUnion CountyVermilion CountyWabash CountyWarren CountyWashington CountyWayne CountyWhite CountyWhiteside CountyWill CountyWilliamson CountyWinnebago CountyWoodford CountyGreen Door Capital data center near Caledonia (Meyer property) · Withdrawn
PowerNot statedNot reported in the records found
Site128acres

Who is behind it

ProjectGreen Door Capital data center near Caledonia (Meyer property)Also: Yorkville Nexus V
Developer and teamGreen Door Capital (Yorkville Nexus V LLC)
End userNot found in the recordsNot yet named in any record or credited report we have found.

The record, newest first

  1. WSPY reported the rezoning petition had been withdrawn; the mayor said talks showed the council lacked enough support. (WSPY News, April 15, 2026)

  2. After the developer reduced the plan to about 80 acres of data center use, the city council tabled the rezoning vote. (Shaw Local (Kendall County Now), April 1, 2026)

  3. The Yorkville Planning and Zoning Commission unanimously voted against recommending the rezoning. (WSPY News, Jan. 16, 2026; Shaw Local (Kendall County Now), April 1, 2026)

Conflicts and open questions

  • Acreage differs by stage: about 91 acres proposed for manufacturing zoning plus 37 to 39 acres left residential or agricultural (about 128 to 130 acres in all); the revised plan described an 80-acre data center. Kept because the original petition exceeded 100 acres.

The full record

Evidence
News reports; primary records not yet obtained
Size class
50 MW or more (tracker scope)
Map position approximate, from the reported address or area. Updated Oct. 17, 2026.