Logan Prairie Data Center
Hut 8 Corp. proposes a 500 MW, $5 billion AI/cloud campus on farmland near Latham, which has gone through a contested county moratorium, an annexation attempt and tabled zoning applications. Also known as: Hut 8 Logan County data center.
Who is behind it
The record, newest first
The county canceled its Aug. 6 zoning board meeting; the zoning officer said the applications were tabled and September was the earliest they could return if fixed and resubmitted. (Illinois Times, July 28, 2026)
Latham's village attorney postponed the Aug. 3 meeting with no new date, saying the application had not been withdrawn. (Illinois Times, July 28, 2026; Blockspace Media, July 31, 2026)
Hut 8 was reported seeking annexation into Latham with a community benefit agreement, with a village hearing and vote set for Aug. 3. (Illinois Times, July 22, 2026)
The county zoning officer deemed Hut 8's land-use applications complete. (Illinois Times, July 2, 2026)
The state's attorney advised the board the 12-month moratorium was invalid; a proposed data center zoning ordinance failed 5-6. (Illinois Times, July 2, 2026; Blockspace Media, July 31, 2026)
The County Board approved a 12-month moratorium, 6-4. (Illinois Times, July 2, 2026; Blockspace Media, July 31, 2026)
The Logan County Board approved a 60-day moratorium on data center applications. (Illinois Times, July 2, 2026)
Hut 8 held a community open house on the project. (Hut 8 Corp., Feb. 4, 2026)
Hut 8 withdrew its first county application at the county's request, saying it planned to resubmit (month reported as December). (Illinois Times, May 4, 2026; Illinois Times, July 2, 2026)
Conflicts and open questions
- Site size reported as about 250 acres (May-July 2026) and about 200 acres (late July 2026); Hut 8's own page gives a 50-acre footprint.
- Coordinates approximate, about a mile or two west of Latham.
The full record
- Status note
- County zoning applications were tabled after the state's attorney found technical errors in them, and Latham postponed its annexation vote; Hut 8 had not withdrawn its Latham application.
- Power note
- Developer figure for total capacity; Ameren/MISO interconnection studies not yet complete.
- Evidence
- News reports; primary records not yet obtained
- Size class
- 50 MW or more (tracker scope)