Data center campus · Edson Road near Friday Road, south of Chicago Rockford International Airport, Rockford, Winnebago County, Illinois

Monarch Energy Rockford data center

Proposed as of Aug. 3, 2026

Monarch Energy is pursuing a 1,400 MW hyperscale campus on industrial land at Rockford's southern edge, with a signed state tax incentive deal but no formal city proposal. Also known as: Monarch Rock Air.

Cite← Illinois data centers
Adams CountyAlexander CountyBond CountyBoone CountyBrown CountyBureau CountyCalhoun CountyCarroll CountyCass CountyChampaign CountyChristian CountyClark CountyClay CountyClinton CountyColes CountyCook CountyCrawford CountyCumberland CountyDe Witt CountyDeKalb CountyDouglas CountyDuPage CountyEdgar CountyEdwards CountyEffingham CountyFayette CountyFord CountyFranklin CountyFulton CountyGallatin CountyGreene CountyGrundy CountyHamilton CountyHancock CountyHardin CountyHenderson CountyHenry CountyIroquois CountyJackson CountyJasper CountyJefferson CountyJersey CountyJo Daviess CountyJohnson CountyKane CountyKankakee CountyKendall CountyKnox CountyLake CountyLaSalle CountyLawrence CountyLee CountyLivingston CountyLogan CountyMacon CountyMacoupin CountyMadison CountyMarion CountyMarshall CountyMason CountyMassac CountyMcDonough CountyMcHenry CountyMcLean CountyMenard CountyMercer CountyMonroe CountyMontgomery CountyMorgan CountyMoultrie CountyOgle CountyPeoria CountyPerry CountyPiatt CountyPike CountyPope CountyPulaski CountyPutnam CountyRandolph CountyRichland CountyRock Island CountySaline CountySangamon CountySchuyler CountyScott CountyShelby CountySt. Clair CountyStark CountyStephenson CountyTazewell CountyUnion CountyVermilion CountyWabash CountyWarren CountyWashington CountyWayne CountyWhite CountyWhiteside CountyWill CountyWilliamson CountyWinnebago CountyWoodford CountyMonarch Energy Rockford data center · Proposed · 1,400 MW
Power1,400MW reported · stated

Who is behind it

ProjectMonarch Energy Rockford data centerAlso: Monarch Rock Air
Developer and teamMonarch Rock Air LLC (Monarch Energy)
End userNot found in the recordsNot yet named in any record or credited report we have found.

The record, newest first

  1. Rockford approved a six-month data center moratorium, 14-0, which does not cover Monarch's land. (Rock River Current, Aug. 3, 2026)

  2. DCEO signed the incentive MOU with Monarch Rock Air, weeks before the state stopped processing new program agreements on July 1. (Rock River Current, June 26, 2026)

  3. City officials said no site plan or development agreement had been filed; the land, zoned I-2 since its 2008 annexation, allows data centers as a permitted use. (Rock River Current, March 6, 2026)

  4. Monarch was reported to have turned a planned landfill-linked aviation fuel project near the airport into a data center plan of up to $12 billion. (Rock River Current, March 1, 2026)

Conflicts and open questions

  • About 1,300 acres lie in the surrounding area; the campus acreage itself was not reported.
  • End user not named.
  • Coordinates approximate, south of the airport near Edson and Friday roads.

The full record

Status note
No site plan or formal proposal filed with the city; a state incentive MOU is signed, and the land is exempt from Rockford's moratorium under an existing annexation agreement.
Power note
1,400 MW multibuilding campus with associated power generation, as described in the DCEO MOU obtained by Rock River Current (record not opened here).
Evidence
News reports; primary records not yet obtained
Size class
50 MW or more (tracker scope)
Map position approximate, from the reported address or area. Updated Oct. 17, 2026.