Data center project · Shawnee County, Kansas
Compass Datacenters campus, southwest of Topeka
Paused by moratorium · A 10-building, 400 MW campus proposed on about 600 acres of light-industrial land southwest of Topeka.
- Status
- Paused by moratorium · as of Sept. 9, 2026
- Location
- South of the 3500 block of SW 77th Street, Wakarusa area, unincorporated Shawnee County · Shawnee County
- Status note
- The county deemed the conditional use permit complete on Sept. 9, 2026, but its moratorium bars final action on it until Feb. 17, 2027.
- Power
- 400 MW
400 MW critical power load at completion, as Compass reported in its permit application (KSNT); not backup generation. - Floor area
- 2,670,000 sq ft
- Land
- 600 acres
- Developer and team
- Compass Datacenters
- Utility
- Evergy (will-serve letter filed)
- Water
- Compass says it will use no municipal water for cooling.
- Incentives
- No abatement found; a Topeka commercial broker told Kansas Reflector the project is not receiving the kind of property tax abatement Mars got, which was not checked against a county record.
- Evidence
- Primary public records
- Size class
- 50 MW or more (tracker scope)
Updates, newest first
- Sept. 9, 2026 The county deemed the application complete and began full review; no hearing was set. (Shawnee County Land Use & Development, Sept. 9, 2026)
- Aug. 28, 2026 Compass filed revised exhibits, including an Evergy will-serve letter and a revised sound survey. (Shawnee County Land Use & Development, Sept. 9, 2026)
- Aug. 27, 2026 Kansas Reflector quoted a Topeka commercial broker estimating about $122 million a year in property taxes if the campus is appraised at $3 billion; this is an estimate, not a county figure. (High Plains Public Radio (Kansas Reflector), Aug. 27, 2026)
- Aug. 13, 2026 County commissioners adopted a six-month moratorium that also bars final action on the Compass application. (KSNT 27 News, Aug. 13, 2026)
- Aug. 6, 2026 KSNT summarized the filing: 10 single-story buildings on just over 600 acres with an on-site substation, and a 400 MW critical load at completion. (KSNT 27 News, Aug. 6, 2026)
- Aug. 4, 2026 County staff found the application incomplete. (Shawnee County Land Use & Development, Sept. 9, 2026)
- July 24, 2026 Compass filed conditional use permit application CU-26-203. (Shawnee County Land Use & Development, Sept. 9, 2026; KSNT 27 News, July 27, 2026)
Conflicts and open questions
- The 2.67 million square feet is the combined footprint of 10 buildings of 267,000 square feet each, as described in the application (KSNT).
- The $122 million yearly property tax figure is a broker's estimate assuming a $3 billion appraisal, not a county projection.
Have records about this project? Send them to tips@signaldata.org.